PROJECT :

JASA PERBAIKAN SILINCER & DINDING DALAM GAS DUCT MI GT


1.1 MUARA KARANG 2020
CLIENT : PT. PJB UNIT PELAYANAN WILAYAH B REPORT NO : 001/WIR/GAM/XI/2020
CONTRACTOR : PT. GUNUNG API MULIA MAS DATE : NOV 8,2020
WELDING INSPECTION REPORT PART : SILINCER 4 PAGE 1 OF 1
DOC NO ;
FIT-UP WELDING RESULT
NO JOINT NO
DATE DATE ACCEPTED REJECTED
JOINT 3 1 JOINT 1 NOV 7, 2020 NOV 8, 2020 ACCEPTED
2 JOINT 2 NOV 7, 2020 NOV 8, 2020 ACCEPTED
3 JOINT 3 NOV 7, 2020 NOV 8, 2020 ACCEPTED
4 JOINT 4 NOV 7, 2020 NOV 8, 2020 ACCEPTED

J J
O O
I I
N N
T T
4 2

JOINT 1

Inspected By, Reviewed By Approved By,


PT. GUNUNG API MULIA MAS PT. GUNUNG API MULIA MAS PT. PJB UNIT PELAYANAN WILAYAH B

Name : Name : Name :


Date : Date : Date :
Page : 1 of 3
PROJECT :
JASA PERBAIKAN SILINCER & DINDING DALAM GAS DUCT MI GT
1.1 MUARA KARANG 2020
CLIENT : PT. PJB UNIT PELAYANAN WILAYAH B REPORT NO : 002/WIR/GAM/XI/2020
CONTRACTOR : PT. GUNUNG API MULIA MAS DATE : NOV 8,2020
WELDING INSPECTION REPORT PART : SILINCER 1 PAGE 1 OF 1
DOC NO ;
FIT-UP WELDING RESULT
NO JOINT NO
DATE DATE ACCEPTED REJECTED
JOINT 3 1 JOINT 1 NOV 7, 2020 NOV 8, 2020 ACCEPTED
2 JOINT 2 NOV 7, 2020 NOV 8, 2020 ACCEPTED
3 JOINT 3 NOV 7, 2020 NOV 8, 2020 ACCEPTED
4 JOINT 4 NOV 7, 2020 NOV 8, 2020 ACCEPTED

J J
O O
I I
N N
T T
4 2

JOINT 1

Inspected By, Reviewed By Approved By,


PT. GUNUNG API MULIA MAS PT. GUNUNG API MULIA MAS PT. PJB UNIT PELAYANAN WILAYAH B

Name : Name : Name :


Date : Date : Date :
Page : 1 of 3