Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as
per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd
over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent
as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove
cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as
per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2018-19, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. LII, Sl.No. 118, Code No. 137 1839 Per hour
For 6 hr 11034
Additional 10% for Over Head Charges 1103.40
Additional 10% for Contractor Profit 1103.40
Sub Total 13240.80
Add 5% of Area Weightaaage 662.04
Total 13902.84
For 1 Cum 132.41 Cum
Tender Premium-+4% 5.30
Rate to be reduced for manual concrete pavement 137.71 Per Cum
Rate Quoted by the Contractor 6332.51 Per Cum
Less Rate for mechanical paving 137.71 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 6194.80 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be
done if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with
unreinforced M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and
Admixture confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades
as per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth
coverd over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint
with sealent as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the
groove cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc.,
complete and as per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2016-17, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. L, Sl.No. 118, Code No. 137 2170 Per hour
For 6 hr 13020
Additional 10% for Over Head Charges 1302.00
Additional 10% for Contractor Profit 1302.00
Sub Total 15624.00
Add 5% of Area Weightaaage 781
Total 16405
For 1 Cum 156.24 Cum
Tender Premium- -0.1882% -0.29
Rate to be reduced for manual concrete pavement 155.95 Per Cum
Rate Quoted by the Contractor 7842.45 Per Cum
Less Rate for mechanical paving 155.95 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 7686.50 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be
done if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with
unreinforced M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and
Admixture confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades
as per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth
coverd over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint
with sealent as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the
groove cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc.,
complete and as per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2016-17, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. L, Sl.No. 118, Code No. 137 2170 Per hour
For 6 hr 13020
Additional 10% for Over Head Charges 1302.00
Additional 10% for Contractor Profit 1302.00
Sub Total 15624.00
Add 5% of Area Weightaaage 781
Total 16405
For 1 Cum 156.24 Cum
Tender Premium-+4.2% 6.56
Rate to be reduced for manual concrete pavement 162.80 Per Cum
Rate Quoted by the Contractor 9000.00 Per Cum
Less Rate for mechanical paving 162.80 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 8837.20 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as
per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd
over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent
as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove
cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as
per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2018-19, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. LII, Sl.No. 118, Code No. 137 1839 Per hour
For 6 hr 11034
Additional 10% for Over Head Charges 1103.40
Additional 10% for Contractor Profit 1103.40
Sub Total 13240.80
Add 5% of Area Weightaaage 662.04
Total 13902.84
For 1 Cum 132.41 Cum
Tender Premium - 1.6% -2.12
Rate to be reduced for manual concrete pavement 130.29 Per Cum
Rate Quoted by the Contractor 5991.53 Per Cum
Less Rate for mechanical paving 130.29 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 5861.24 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as
per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd
over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent
as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove
cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as
per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2016-17, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. L, Sl.No. 118, Code No. 137 2170 Per hour
For 6 hr 13020
Additional 10% for Over Head Charges 1302.00
Additional 10% for Contractor Profit 1302.00
Sub Total 15624.00
Add 5% of Area Weightage 781.20
Total 16405.20
For 1 Cum 156.24 Cum
Tender Premium-+4.99% 7.80
Rate to be reduced for manual concrete pavement 164.04 Per Cum
Rate Quoted by the Contractor 9000 Per Cum
Less Rate for mechanical paving 164.04 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 8835.96 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid manually, finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as per drawing,
texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd over concrete
surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent as per IRC-15
as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove cutting shall be
1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as per the
direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2018-19, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. LII, Sl.No. 118, Code No. 137 1839 Per hour
For 6 hr 11034
Additional 10% for Over Head Charges 1103.40
Additional 10% for Contractor Profit 1103.40
Sub Total 13240.80
Add 5% of Area Weightage 662.04
Total 13902.84
For 1 Cum 132.41 Cum
Tender Premium-+4.97% 6.58
Rate to be reduced for manual concrete pavement 138.99 Per Cum
Rate Quoted by the Contractor 8600 Per Cum
Less Rate for mechanical paving 138.99 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 8461.01 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as
per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd
over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent
as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove
cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as
per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2018-19, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. LII, Sl.No. 118, Code No. 137 1839 Per hour
For 6 hr 11034
Additional 10% for Over Head Charges 1103.40
Additional 10% for Contractor Profit 1103.40
Sub Total 13240.80
Add 5% of Area Weightage 662.04
Total 13902.84
For 1 Cum 132.41 Cum
Tender Premium- -0.4856% -0.64
Rate to be reduced for manual concrete pavement 131.77 Per Cum
Rate Quoted by the Contractor 8200 Per Cum
Less Rate for mechanical paving 131.77 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 8068.23 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40)

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be
done if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with
unreinforced M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and
Admixture confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades
as per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth
coverd over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint
with sealent as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the
groove cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc.,
complete and as per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2016-17, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. L, Sl.No. 118, Code No. 137 2170 Per hour
For 6 hr 13020
Additional 10% for Over Head Charges 1302.00
Additional 10% for Contractor Profit 1302.00
Sub Total 15624.00
Add 5% of Area Weightaaage 781.20
Total 16405.20
For 1 Cum 156.24 Cum
Tender Premium- 0 0.00
Rate to be reduced for manual concrete pavement 156.24 Per Cum
Rate Quoted by the Contractor 8750.00 Per Cum
Less Rate for mechanical paving 156.24 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 8593.76 Per Cum
Rate Analysis for Median earh filling Rs
Construction of sub-grade and earthen shoulders with approved material Gravel/Murrum with all lifts & leads, transporting to site,
spreading, grading to required slope complete as per specifications (including cost of earth, .etc complete and as per the direction
of the Engineer-in-charge.

a
SR 2017-18, Dharwad Circle rate forKSRRB 300-58. Compaction of original ground with maximum of 6 passes of 8 to 10 tonnes power
roller including filling in depression occuring during rolling including cost of all·:abour, HOM of machinery complete as per
specifications.
MORTH / Chapter 3 vide Item no.19.64, Page no. 149
4.7 Per Sqm
Rate for 0.20Cum ( Considering 200mm thick) per layer = 4.7 Per 0.20Cum
Rate for 1 Cum 23.50 Per Cum
b KSRRB 300-64.1. Extra for watering the earth to bring the earth upto required optimum moisture content manually including cost of all
labour complete as per specifications. MORTH / Chapter 3 vide Item no.19.71, Page no. 149 7.50 Per Cum
Sub total 31.00
Add 5% of area weightage 1.55
Total 32.55 Per cum
Tender Premium- +4.99% 1.62
Rate to be reduced for median earth filling 34.17 Per Cum
Rate Quoted by the Contractor 500 Per Cum
Reduced Rate For Median earh filling 465.83 Per Cum
Rate Analysis for Median earh filling for Road Package-02 Rs
Construction of sub-grade and earthen shoulders with approved material Gravel/Murrum with all lifts & leads, transporting to site,
spreading, grading to required slope complete as per specifications (including cost of earth, .etc complete and as per the direction
of the Engineer-in-charge.

a
SR 2017-18, Dharwad Circle rate for KSRRB 300-58. Compaction of original ground with maximum of 6 passes of 8 to 10 tonnes power
roller including filling in depression occuring during rolling including cost of all·:abour, HOM of machinery complete as per
specifications.
MORTH / Chapter 3 vide Item no.19.64, Page no. 149
4.7 Per Sqm
Rate for 0.20Cum ( Considering 200mm thick) per layer = 4.7 Per 0.20Cum
Rate for 1 Cum 23.50 Per Cum
b KSRRB 300-64.1. Extra for watering the earth to bring the earth upto required optimum moisture content manually including cost of all
labour complete as per specifications. MORTH / Chapter 3 vide Item no.19.71, Page no. 149 7.50 Per Cum
Sub total 31.00
Add 5% of area weightage 1.55
Total 32.55 Per cum
Tender Premium- +4.20% 1.37
Rate to be reduced for median earth filling 33.92 Per Cum
Rate Quoted by the Contractor 500 Per Cum
Reduced Rate For Median earh filling 466.08 Per Cum
Rate Analysis for Median earh filling for Road Package-03 Rs
Construction of sub-grade and earthen shoulders with approved material Gravel/Murrum with all lifts & leads, transporting to site,
spreading, grading to required slope complete as per specifications (including cost of earth, .etc complete and as per the direction
of the Engineer-in-charge.

a
SR 2017-18, Dharwad Circle rate for KSRRB 300-58. Compaction of original ground with maximum of 6 passes of 8 to 10 tonnes power
roller including filling in depression occuring during rolling including cost of all·:abour, HOM of machinery complete as per
specifications.
MORTH / Chapter 3 vide Item no.19.64, Page no. 149
4.7 Per Sqm
Rate for 0.20Cum ( Considering 200mm thick) per layer = 4.7 Per 0.20Cum
Rate for 1 Cum 23.50 Per Cum
b KSRRB 300-64.1. Extra for watering the earth to bring the earth upto required optimum moisture content manually including cost of all
labour complete as per specifications. MORTH / Chapter 3 vide Item no.19.71, Page no. 149 7.50 Per Cum
Sub total 31.00
Add 5% of area weightage 1.55
Total 32.55 Per cum
Tender Premium- - 0.4856% -0.16
Rate to be reduced for median earth filling 32.39 Per Cum
Rate Quoted by the Contractor 500 Per Cum
Reduced Rate For Median earh filling 467.61 Per Cum
Rate Analysis for Manually laid Pavement concrete (M40) - WT-12

Providing and laying White Topping as per IRC:SP76-2008 over bituminous surface (Existing bituminous surface preparation to be done
if necessary either by miiling or leveiling course with BM/DBM to correct surface profile and to be paid separately) with unreinforced
M40 grade pavement quality concrete (PQC) using 43 grade OPC @ 420 kg/cum, coarse aggregate, fine aggregate and Admixture
confirming to IS 9130-1999 (R-2004) using polymeric synthetic fibre as per ASTM (1116) such as polyester / polyethylene /
polypropylene at 1.20 kg/cum, mixed in batching and mixing plant or weigh batcher as per approved mix design to achieve minimum
flexural strength or modulus of rupture of concrete 4.50 MPa at 28 days limiting maximum water cement ratio to 0.40, transported to
site, laid with Mechanical paver finisher, spread, vibrated, compacted and finished in a continuous operation to the lines and grades as
per drawing, texture finishing of surface, spraying two layers of curing compound, curing with water sprayed on hessian cloth coverd
over concrete surface, groove cutting to a depth of 1/3 of the slab depth and of width 3-5 mm including cost of filling joint with sealent
as per IRC-15 as per design (grove cutting to be paid separately). For Thin white Topping and ultra thin white topping the groove
cutting shall be 1.25m x 1.25 m grid including cost of all materal, side form work,labour and HOM of machineries etc., complete and as
per the direction of the Engineer-in-charge.

Paver required for 6hrs for laying 105 cum of PQC/White Topping
CSR 2018-19, Belagavi Circle rate for hire charges of mechanical Paver vide Page no. LII, Sl.No. 118, Code No. 137 1839 Per hour
For 6 hr 11034
Additional 10% for Over Head Charges 1103.40
Additional 10% for Contractor Profit 1103.40
Sub Total 13240.80
Add 5% of Area Weightage 662.04
Total 13902.84
For 1 Cum 132.41 Cum
Tender Premium- -3.5222% -4.66
Rate to be reduced for manual concrete pavement 127.75 Per Cum
Rate Quoted by the Contractor 5900 Per Cum
Less Rate for mechanical paving 127.75 Per Cum
Reduced Rate For Manually laid Pavement Concrete (M40) 5772.25 Per Cum
Rate Analysis for Median earh filling Rs Unit
Construction of sub-grade and earthen shoulders with approved material Gravel/Murrum with all lifts & leads, transporting to site,
spreading, grading to required slope complete as per specifications (including cost of earth, .etc complete and as per the direction
of the Engineer-in-charge. for median filling

KSRRB M300-55. Construction of sub-grade and .earthen shoulders wilh approved material Gravel/Murrum with all lifts & leads,
transporting to site,spreading, grading to required slope and compacted to meet requirement of Table No. 300-2 complete as per
424 Per Cum
specifications, including cost of earth, watering charges & compaction by Vibratory roilerto 97% of proctors density) MORTH
Specification No. 305 Item no 19.62, page no 148

a
SR 2017-18, Dharwad Circle rate forKSRRB 300-58. Compaction of original ground with maximum of 6 passes of 8 to 10 tonnes power
roller including filling in depression occuring during rolling including cost of all·:abour, HOM of machinery complete as per
specifications.
MORTH / Chapter 3 vide Item no.19.64, Page no. 149
4.7 Per Sqm
Rate for 0.20Cum ( Considering 200mm thick) per layer = 4.7 Per 0.20Cum
Rate for 1 Cum 23.50 Per Cum
b KSRRB 300-64.1. Extra for watering the earth to bring the earth upto required optimum moisture content manually including cost of all
labour complete as per specifications. MORTH / Chapter 3 vide Item no.19.71, Page no. 149 7.50 Per Cum
Sub total (a+b) 31.00
Net Rate 393.00 Per Cum