Professional Documents
Culture Documents
1 Environmental Health System Project 136 days? 2/4/21 8:00 AM 8/12/21 5:00 PM
2 Phase 1 - Food License Module 43 days? 2/4/21 8:00 AM 4/5/21 5:00 PM
3 Initiation Phase 12 days 2/4/21 8:00 AM 2/19/21 5:00 PM
4 Develop project charter 8 days 2/4/21 8:00 AM 2/15/21 5:00 PM Neha Kumar
5 Project charter approved 4 days 2/16/21 8:00 AM 2/19/21 5:00 PM 4 Simon Kumar;Eric Rafai
6 Planning Phase 31 days? 2/22/21 8:00 AM 4/5/21 5:00 PM
7 Product activities 16 days? 2/22/21 8:00 AM 3/15/21 5:00 PM
8 Manage scope definition 16 days? 2/22/21 8:00 AM 3/15/21 5:00 PM
9 Create scope document 3 days 2/22/21 8:00 AM 2/24/21 5:00 PM Neha Kumar
10 Scope document approved 1 day 2/25/21 8:00 AM 2/25/21 5:00 PM 9
11 Manage requirements gathering 12 days? 2/26/21 8:00 AM 3/15/21 5:00 PM
12 Interview users & Stakeholders 3 days 2/26/21 8:00 AM 3/2/21 5:00 PM Neha Kumar
13 Verify the process 1 day? 3/3/21 8:00 AM 3/3/21 5:00 PM 12 Neha Kumar
14 Prepare workflow plan 2 days? 3/4/21 8:00 AM 3/5/21 5:00 PM 13 Neha Kumar
15 Workflow plan Approval 1 day? 3/8/21 8:00 AM 3/8/21 5:00 PM 14 CHI
16 Prepare requirements document 3 days 3/9/21 8:00 AM 3/11/21 5:00 PM 15 Neha Kumar
17 Submit Requirements document 1 day 3/12/21 8:00 AM 3/12/21 5:00 PM 16 Neha Kumar
18 Meeting with ITC 1 day? 3/15/21 8:00 AM 3/15/21 5:00 PM
19 Project activities 15 days 3/16/21 8:00 AM 4/5/21 5:00 PM
20 Manage scope/cost/schedule planning 7 days 3/16/21 8:00 AM 3/24/21 5:00 PM
21 Develop project plan 6 days 3/16/21 8:00 AM 3/23/21 5:00 PM
22 Create task list 1 day 3/16/21 8:00 AM 3/16/21 5:00 PM Neha Kumar
23 Create estimates 1 day 3/17/21 8:00 AM 3/17/21 5:00 PM Neha Kumar
24 Create milestone plan 1 day 3/18/21 8:00 AM 3/18/21 5:00 PM Neha Kumar
25 Create resource assignments 1 day 3/19/21 8:00 AM 3/19/21 5:00 PM Neha Kumar
26 Create budget 2 days 3/22/21 8:00 AM 3/23/21 5:00 PM 23 Neha Kumar
27 Project plan approved 1 day 3/24/21 8:00 AM 3/24/21 5:00 PM Simon Kumar;Eric Rafai
28 Manage quality planning 2 days 3/25/21 8:00 AM 3/26/21 5:00 PM
29 Develop quality plan 2 days 3/25/21 8:00 AM 3/26/21 5:00 PM Neha Kumar
30 Manage risk planning 2 days 3/29/21 8:00 AM 3/30/21 5:00 PM
31 Develop risk management plan 2 days 3/29/21 8:00 AM 3/30/21 5:00 PM Neha Kumar
32 Manage procurement planning 2 days 3/31/21 8:00 AM 4/1/21 5:00 PM
33 Develop procurement plan 2 days 3/31/21 8:00 AM 4/1/21 5:00 PM Neha Kumar
34 Manage Training Planning 2 days 4/2/21 8:00 AM 4/5/21 5:00 PM
35 Develop Training Plan 2 days 4/2/21 8:00 AM 4/5/21 5:00 PM Neha Kumar
- page1
Name Duration Start Finish Predecessors Resource Names
- page2
Name Duration Start Finish Predecessors Resource Names
- page3