Name Duration Start Finish Predecessors Resource Names

1 Environmental Health System Project 136 days? 2/4/21 8:00 AM 8/12/21 5:00 PM
2 Phase 1 - Food License Module 43 days? 2/4/21 8:00 AM 4/5/21 5:00 PM
3 Initiation Phase 12 days 2/4/21 8:00 AM 2/19/21 5:00 PM
4 Develop project charter 8 days 2/4/21 8:00 AM 2/15/21 5:00 PM Neha Kumar
5 Project charter approved 4 days 2/16/21 8:00 AM 2/19/21 5:00 PM 4 Simon Kumar;Eric Rafai
6 Planning Phase 31 days? 2/22/21 8:00 AM 4/5/21 5:00 PM
7 Product activities 16 days? 2/22/21 8:00 AM 3/15/21 5:00 PM
8 Manage scope definition 16 days? 2/22/21 8:00 AM 3/15/21 5:00 PM
9 Create scope document 3 days 2/22/21 8:00 AM 2/24/21 5:00 PM Neha Kumar
10 Scope document approved 1 day 2/25/21 8:00 AM 2/25/21 5:00 PM 9
11 Manage requirements gathering 12 days? 2/26/21 8:00 AM 3/15/21 5:00 PM
12 Interview users & Stakeholders 3 days 2/26/21 8:00 AM 3/2/21 5:00 PM Neha Kumar
13 Verify the process 1 day? 3/3/21 8:00 AM 3/3/21 5:00 PM 12 Neha Kumar
14 Prepare workflow plan 2 days? 3/4/21 8:00 AM 3/5/21 5:00 PM 13 Neha Kumar
15 Workflow plan Approval 1 day? 3/8/21 8:00 AM 3/8/21 5:00 PM 14 CHI
16 Prepare requirements document 3 days 3/9/21 8:00 AM 3/11/21 5:00 PM 15 Neha Kumar
17 Submit Requirements document 1 day 3/12/21 8:00 AM 3/12/21 5:00 PM 16 Neha Kumar
18 Meeting with ITC 1 day? 3/15/21 8:00 AM 3/15/21 5:00 PM
19 Project activities 15 days 3/16/21 8:00 AM 4/5/21 5:00 PM
20 Manage scope/cost/schedule planning 7 days 3/16/21 8:00 AM 3/24/21 5:00 PM
21 Develop project plan 6 days 3/16/21 8:00 AM 3/23/21 5:00 PM
22 Create task list 1 day 3/16/21 8:00 AM 3/16/21 5:00 PM Neha Kumar
23 Create estimates 1 day 3/17/21 8:00 AM 3/17/21 5:00 PM Neha Kumar
24 Create milestone plan 1 day 3/18/21 8:00 AM 3/18/21 5:00 PM Neha Kumar
25 Create resource assignments 1 day 3/19/21 8:00 AM 3/19/21 5:00 PM Neha Kumar
26 Create budget 2 days 3/22/21 8:00 AM 3/23/21 5:00 PM 23 Neha Kumar
27 Project plan approved 1 day 3/24/21 8:00 AM 3/24/21 5:00 PM Simon Kumar;Eric Rafai
28 Manage quality planning 2 days 3/25/21 8:00 AM 3/26/21 5:00 PM
29 Develop quality plan 2 days 3/25/21 8:00 AM 3/26/21 5:00 PM Neha Kumar
30 Manage risk planning 2 days 3/29/21 8:00 AM 3/30/21 5:00 PM
31 Develop risk management plan 2 days 3/29/21 8:00 AM 3/30/21 5:00 PM Neha Kumar
32 Manage procurement planning 2 days 3/31/21 8:00 AM 4/1/21 5:00 PM
33 Develop procurement plan 2 days 3/31/21 8:00 AM 4/1/21 5:00 PM Neha Kumar
34 Manage Training Planning 2 days 4/2/21 8:00 AM 4/5/21 5:00 PM
35 Develop Training Plan 2 days 4/2/21 8:00 AM 4/5/21 5:00 PM Neha Kumar

- page1
Name Duration Start Finish Predecessors Resource Names

36 Execution phase 70 days? 4/6/21 8:00 AM 7/12/21 5:00 PM


37 Product activities 70 days? 4/6/21 8:00 AM 7/12/21 5:00 PM
38 Manage design 52 days? 4/6/21 8:00 AM 6/16/21 5:00 PM
39 Develop use cases 3 days 4/6/21 8:00 AM 4/8/21 5:00 PM Developer
40 Create data architecture 2 days 4/9/21 8:00 AM 4/12/21 5:00 PM Developer
41 Design Product 12 days 4/13/21 8:00 AM 4/28/21 5:00 PM
42 Design UI 5 days 4/13/21 8:00 AM 4/19/21 5:00 PM Developer
43 Design rules 2 days 4/20/21 8:00 AM 4/21/21 5:00 PM Developer
44 Design database 3 days 4/22/21 8:00 AM 4/26/21 5:00 PM 43 Developer
45 Create SAD documentation 2 days 4/27/21 8:00 AM 4/28/21 5:00 PM Developer
46 Product Design Approval 1 day 4/29/21 8:00 AM 4/29/21 5:00 PM Simon Kumar;Eric Rafai
47 Develop product 26 days? 4/30/21 8:00 AM 6/4/21 5:00 PM
48 Develop UI 5 days 4/30/21 8:00 AM 5/6/21 5:00 PM Developer
49 Develop rules 1 day 5/7/21 8:00 AM 5/7/21 5:00 PM Developer
50 Develop database 2 days 5/10/21 8:00 AM 5/11/21 5:00 PM 49 Developer
51 Product development complete 18 days? 5/12/21 8:00 AM 6/4/21 5:00 PM Developer
52 Develop Use Case Testing 8 days 6/7/21 8:00 AM 6/16/21 5:00 PM
53 Create test cases 2 days 6/7/21 8:00 AM 6/8/21 5:00 PM Neha Kumar
54 Perform User Acceptance Test 2 days 6/9/21 8:00 AM 6/10/21 5:00 PM 53 Neha Kumar
55 Prepare Testing eeport 2 days 6/11/21 8:00 AM 6/14/21 5:00 PM 54 Neha Kumar
56 Approval of test document 2 days 6/15/21 8:00 AM 6/16/21 5:00 PM 55 Taina R
57 Manage deployment 18 days? 6/17/21 8:00 AM 7/12/21 5:00 PM
58 Schedule release 1 day 6/17/21 8:00 AM 6/17/21 5:00 PM Neha Kumar
59 Develop User manual 3 days? 6/18/21 8:00 AM 6/22/21 5:00 PM
60 Prepare User manual 3 days? 6/18/21 8:00 AM 6/22/21 5:00 PM
61 Schedule training 5 days 6/23/21 8:00 AM 6/29/21 5:00 PM
62 Schedule user training 5 days 6/23/21 8:00 AM 6/29/21 5:00 PM Neha Kumar
63 Rollout 8 days 6/30/21 8:00 AM 7/9/21 5:00 PM
64 Back up database 2 days 6/30/21 8:00 AM 7/1/21 5:00 PM Developer
65 Install system on web server 2 days 7/2/21 8:00 AM 7/5/21 5:00 PM 64 Developer
66 Conduct verification tests 2 days 7/6/21 8:00 AM 7/7/21 5:00 PM Developer
67 Confirm successful rollout 2 days 7/8/21 8:00 AM 7/9/21 5:00 PM 66 Neha Kumar
68 Announce Launch 1 day 7/12/21 8:00 AM 7/12/21 5:00 PM 67 Neha Kumar
69 Closing phase 22 days 7/13/21 8:00 AM 8/11/21 5:00 PM
70 Product activities 22 days 7/13/21 8:00 AM 8/11/21 5:00 PM

- page2
Name Duration Start Finish Predecessors Resource Names

71 Manage maintenance 22 days 7/13/21 8:00 AM 8/11/21 5:00 PM


72 Perform impact analysis 1 day 7/13/21 8:00 AM 7/13/21 5:00 PM Neha Kumar
73 Monitor user acceptance 3 days 7/14/21 8:00 AM 7/16/21 5:00 PM 72 Neha Kumar
74 Monitor performance 2 days 7/19/21 8:00 AM 7/20/21 5:00 PM 73 Neha Kumar
75 Monitor defects 3 days 7/21/21 8:00 AM 7/23/21 5:00 PM 74 Neha Kumar
76 Resolve training and support issues 3 days 7/26/21 8:00 AM 7/28/21 5:00 PM 75 Neha Kumar
77 Resolve technical problems 3 days 7/29/21 8:00 AM 8/2/21 5:00 PM 75 Neha Kumar
78 Analyze statistics 2 days 8/3/21 8:00 AM 8/4/21 5:00 PM 77 Neha Kumar
79 Gather requirements for enhancements 2 days 8/5/21 8:00 AM 8/6/21 5:00 PM Neha Kumar
80 Prepare Final Report 3 days 8/9/21 8:00 AM 8/11/21 5:00 PM Neha Kumar
81 End project 1 day 8/12/21 8:00 AM 8/12/21 5:00 PM 80 Neha Kumar