Professional Documents
Culture Documents
1 Introduction | 3
2 Market trends | 6
5 Conclusion | 23
Glossary | 25
Annex 1:
Summary of state-level updates for open access regulations | 26
Annex 2:
Recent amendments to rooftop solar regulations in India | 28
Annex 3:
Current banking regulations across different states | 29
More and more companies To increase the adoption of 2018). Because the Indian power
are procuring renewable corporate renewable PPAs in market is constantly evolving, we
power for their operations to India, members of the World are producing market and policy
help manage their electricity Business Council for Sustainable updates to keep our members and
costs while contributing to Development (WBCSD) formed other companies informed of the
corporate carbon emissions the India Corporate Renewable latest developments.
reduction targets. In India, PPA Forum in 2017 to exchange
the main drivers for many practical knowledge on the The first update, published in June
companies to do so are effective implementation of 2019, concluded that corporate
rising electricity tariffs for corporate renewable PPAs for both renewable PPAs flourished in India
commercial and industrial rooftop and utility-scale renewable in 2017-18 due to waivers on open
consumers, falling prices electricity installations in India. access charges offered by states
for solar photovoltaic (PV) such as Karnataka, Andhra Pradesh
technology and corporate We combined lessons learned and Telangana. The second update,
sustainability goals. from this work with research on the published in December 2019, found
regulatory environment and market that most states are withdrawing
A frequently used approach for conditions in India to produce the these waivers for third-party sale
companies to purchase renewable WBCSD Accelerating corporate renewable projects and leading
electricity is a corporate renewable procurement of renewable renewable electricity generators to
power purchase agreement (PPA). energy in India report (June shift to alternative business models
A corporate renewable PPA is a like the “group captive” model.
contract between a corporate
buyer(s) and a power producer
(developer, independent power
producer, investor) to purchase
renewable electricity at a pre-
agreed price for a pre-agreed
period. Corporate renewable PPAs
have become increasingly varied
and innovative and are now a
widely used approach worldwide –
companies had signed over 70 GW
of capacity globally as of the end of
November 2020, compared to just
300 MW in 2009.
International context technology costs and growing updates’ for more detail) and the
Corporate renewable PPA uptake awareness of corporate renewable COVID-19 pandemic.
is growing around the world at PPAs among both corporate
buyers and developers are driving State-level regulatory changes in
a remarkable rate. According to Karnataka have had a particularly
BNEF, more than 100 companies this trend.
strong influence on total PPA
in 23 different countries signed capacity additions in India. In
19.5 GW of PPAs in 2019.1 This National market data 2018, nearly 81% of PPA capacity
capacity addition is around 6 GW According to BNEF, in 2019 India additions in India were located
higher than in 2018 and has tripled was the second largest growth in Karnataka as the state had
since 2017. And 2020 is set to be market for corporate renewable offered a 10-year waiver on most
another record-breaking year – for PPAs after the US, with an addition open access charges. After the
the first 11 months of the year, of 1.4 GW of PPA capacity. However, government withdrew these
companies signed 17.9 GW of for the first 11 months of 2020, exemptions, the market in India
corporate renewable PPAs globally, PPA capacity additions in India contracted somewhat in 2019 and
outpacing PPA capacity signed reached only 800 MW, mainly due significantly in 2020 (which the
in the previous year during the to state-level regulatory changes COVID-19 impacts exacerbated), as
same period (as shown in figure 1).2 (see section ‘Policy and regulatory shown in figure 2.
Decreasing renewable generation
15
Capacity (GW)
10
0
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
(Jan-Nov)
Global India
Source: Bloomberg New Energy Finance (BNEF), JMK Research. Note: Data for India includes all captive, group captive and third-party sale solar
and wind PPA projects.
1,2
1
0,8
0,6
0,4
0,2
0
2017 2018 2019 2020 (Jan-Nov)
Offsite PPA Onsite PPA
Source: JMK Research. Note: Data includes all captive, group captive and third-party sale solar and wind PPA projects.
200
Capacity (MW)
150
100
50
0
Tamil Nadu Madhya Gujarat Rajasthan Uttar Andhra Maharashtra Karnataka Others
Pradesh Pradesh Pradesh
120 120
100 100
Capacity (MW)
Capacity (MW)
80 80
60 60
40 40
20 20
0 0
Fourth Partner
AMP Energy
AMP Energy
Fourth Partner
CleanMax
Cleanmax
Greenko
Cleantech
Amplus
Aditya Birla
SunSource
GRT Jewellers
Vedanta Group
Sun Pharma
Cleantech
Continuum Wind*
Adani
Prozeal Infra
Amplus
Aditya Birla
Rays Experts
30,0
25,0
Capacity (MW)
20,0
15,0
10,0
5,0
0,0
Bharati Cement
ACC Ltd.
L&T Metro
Ambuja Cements
Tata Hitachi
Apollo Tyres
Skoda Volkwagon
Grasim Industries
Sangam Ltd.
United breweries
Srinivas Farms
Pepsico
Titagarh Wagons
Snowman Logistics
Cipla
Navya Fashion
Tata Motors
MATE
Ajanta Pharma
Amazon
Ultratech Cement
Cargill
In terms of sectors, construction, From a market perspective, submitted applications for more
infrastructure, automotive and textile the commissioning of the first than 1,900 MW but have reported
companies have been the leading hybrid open access project, the that state DISCOMs in Haryana –
consumer segments, procuring increasing adoption of rooftop Dakshin Haryana Bijli Vitran Nigam
more than 165 MW of renewable solar PPAs, the use of the newly Ltd (DHBVNL) and Uttar Haryana Bijli
power through PPAs in India between launched Green Term Ahead Vitran Nigam Ltd (UHBVNL) – have
April 2019 and August 2020, as Market, and continued company put approvals on hold for third-
shown in figure 5. During this period, appetite for corporate renewable party and group captive consumers
corporate buyers Grasim Industries, PPAs are all evolving market to use their transmission and
Ultratech Cement, Cargill and Apollo dynamics that are promoting distribution networks. The Haryana
Tyres procured the most renewable uptake, while the impacts of the state regulator is now planning to
capacity through corporate COVID-19 pandemic have caused convert the open access projects
renewable PPAs in the country. short-term market constraints. into DISCOM PPAs for 25 years
under cost-plus tariffs.
We examine each of these key
Key evolving trends evolving trends and market After thorough deliberations
and market dynamics dynamics in more detail below. between the developers and the
Several evolving market dynamics government, the Ministry of New and
are impacting the capacity trends Renewable Energy (MNRE) stepped
Reversal of DISCOM
outlined in the previous section. in and asked the state government
approvals for open
to honor the signed renewable
From a regulatory perspective, the access projects in
electricity contracts. We have yet
reversal of DISCOM approvals for Haryana
to see if the state government will
open access projects in Haryana In the previous market and policy uphold these contracts or proceed
and the imposition of additional update published in December with the policy reversal. This policy
surcharges on group captive 2019, we projected that Haryana inconsistency has impacted many
models are developments that are would add significant open access investors, project developers and
limiting the uptake of corporate solar PV capacity – about 550 corporate buyers.
renewable PPAs in India. MW – in 2020. Project developers
150%
100%
0%
-15%
-50% -37%
-50% -54% -59% -60%
-69% -70% -74% -76%
-100% -84% -89% -94% -98%
Kerala
Rajasthan
Karnataka
Telangana
Andhra Pradesh
Madhya Pradesh
Jharkhand
Gujarat
Punjab
Delhi
Maharashtra
Bihar
Chhattisgarh
Haryana
Odisha
West Bengal
Uttar Pradesh
Tamil Nadu
The states initially approved these Imposition of the For financial year 2020-21,
open access projects to fulfill state additional surcharge on Maharashtra has once again
RPO obligations. As of financial group captive models imposed an AS of INR 1.31/kWh
year 2019-20, Haryana had a 94% To promote renewable electricity, on open access consumers
deficit in its solar RPO compliance. various state governments have (both captive and group captive
However, in its tariff order for introduced waivers for third-party consumers). The rationale given
financial year 2020-21, the Haryana sales. In the last two years, however, behind this move is that the
Electricity Regulatory Commission state governments have withdrawn DISCOM may no longer fully use its
(HERC) did not impose any penalty many of these waivers, leading to a existing tied-up capacity, leading to
for this deficit and waived the solar shift from third-party sale models losses for the DISCOM. Given that
and non-solar RPO backlog of to group captive models, where the it is under regulatory proceedings,
1,850 million units (MUs) and 905 cross-subsidy surcharge (CSS) and if approved, it is not possible to rule
MUs respectively. additional surcharge (AS) are not out the risk that other states may
applicable (according to the Indian introduce such a levy.
The removal of the RPO backlog is
one of the key reasons that Haryana Electricity Act 2003).
is backtracking on the approved However, in September 2018,
projects. Had the RPO backlog Maharashtra imposed an AS of INR
been upheld, it would have resulted 1.25/kWh on users of group captive
in the imposition of a penalty on models. The developers opposed
the DISCOM. The DISCOM claims this at the Appellate Tribunal for
that fulfilling the RPO would have Electricity (APTEL), which ruled that
resulted in the passing of an the state may not levy an AS on
additional INR 11 billion in costs to captive users (a judgement that is
electricity consumers. HERC did currently being challenged in the
not approve this, to avoid additional Supreme Court).
financial pressure on top of the
effects of the COVID-19 pandemic.
Table 1: Waivers on open access charges across different states for hybrid projects
1,5
Rs./kWh
0,5
0
2016-17 2017-18 2018-19 2019-20 2020-21
Source: Tariff regulations of various State Electricity Regulatory Commission (SERC’s), JMK Research
Impact of DISCOM with the government’s target As the DISCOM tariffs would
privatization to complete the privatization become more competitive
DISCOM losses in India are of DISCOMs in UTs by January with respect to corporate PPA
significant and have increased 2021, there are also efforts to tariffs, there would be little to
from Rs 338.94 billion in financial encourage this process in states no imposition of restrictions
year 2016-17, to Rs 496.23 billion such as Uttar Pradesh, Haryana, on availing benefits like waivers
in financial year 2018-19. The Gujarat, Karnataka and Assam. in the corporate open access
government has taken various market, allowing the latter
Transformation in the governance market to grow unrestrained.
measures in the past to address and operational management of
this. However, these have not DISCOMs through privatization Despite these efforts, the
generated substantial results would enable an upgrade of government’s DISCOM
to date. The privatization of DISCOM assets, more efficient privatization initiative has
DISCOMs is now under discussion, asset management, quality faced hurdles. Setbacks to
with C&I consumers poised to customer service and improved DISCOM privatization extend the
be one of the most impacted metering and billing processes. deterioration of their financial
beneficiaries of this move. These improvements would lead health, which will in turn continue
In September 2020, the Ministry to greater revenue and profit to adversely affect growth and
of Power issued draft Standard generation for the DISCOMs. the expansion of corporate
Bidding Documents (SBD) for With lucrative business models renewable procurement.
the privatization of DISCOMs managed under private companies Therefore, if delays in the
across all states and Union or public-private partnerships DISCOM privatization procedure
Territories (UTs). The first-of-its- (PPPs), DISCOMs will be able to continue, the amount of additional
kind draft SBD was prepared with lower their tariffs for electricity charges levied on corporate
the objective of enhancing the consumers, especially for C&I renewable PPAs will increase.
operations and finances of India’s consumers as tariffs are currently
loss-making DISCOMs. Along highest for this segment.
INR 180
50%
INR 160
INR 140
40%
INR 120
Billions
30% INR 100
INR 80
20%
INR 60
INR 40
10%
INR 20
0% INR 0
Rajasthan
J&K (including Ladakh)
Jharkhand
Bihar
Madhya Pradesh
Maharashtra
Punjab
Karnataka
Telangana
Andhra Pradesh
Delhi
Uttar Pradesh
Tamil Nadu
AT&C losses (%) State government dues (Rs) Delayed payments to gencos and transcos (Rs)
It is important to note that the and basic custom duties (BCDs) on current SGD regime. These taxes
state-owned non-banking financial imported modules. will lead to increased project costs,
companies (NBFCs) appointed altering the trajectory of solar tariffs
to provide financial assistance to The Ministry of Finance first in India and threatening project
the loss-making DISCOMs (the introduced SGDs between July pipelines. Figure 12 shows the SDG
Power Finance Corporation and its 2018 and July 2020 to promote rate applicability over time.
subsidiary, the Rural Electrification domestic manufacturing and curb
Corporation), have sanctioned imports from China, Taiwan and In the short term, these additional
nearly INR 1.2 trillion under the Malaysia. It subsequently extended duties are likely to increase tariffs for
central government’s liquidity SGDs to 29 July 2021 for all solar corporate renewable PPAs because
package scheme. In addition to cells and modules imported from of cost increases. However, in the
substantially reducing outstanding China, Thailand and Vietnam. From longer term, corporate demand for
DISCOM dues, this liquidity infusion April 2022, the Ministry is expected renewable electricity procurement
could also improve DISCOM to impose 25% and 40% BCD on may significantly drive the market
attractiveness for privatization the import of solar cells and solar for domestic module manufacturers
going forward. modules respectively, to replace the and increase competitiveness.
20%
imported component parts and
15% 14,90%
the importance of self-reliance. 15%
14,50%
impose safeguard duties (SGDs) Source: MNRE, Directorate General of Trade Remedies (DGTR), Ministry of Finance
State Highlights
Chhattisgarh • The Chhattisgarh Electricity Regulatory Commission (CSERC) has waived the CSS for electricity consumers
using open access solar
Gujarat • Withdrawal of all waivers for third-party sale, but to promote wind solar hybrid projects it has offered 50%
concession on CSS and AS
• No restriction on project capacity and the existing ceiling of 50% of the contracted load for setting up rooftop
solar projects will no longer be applicable
Odisha • No CSS payable for one year by consumers using renewable power
• 20% transmission & wheeling charge is payable for one year by consumers using power from renewable sources
(excluding co-generation & biomass)
7
Tariff (Rs/ kWh)
Impact of regulatory
changes on electricity
6
tariffs 5
C&I consumers in India are likely to
4
pay high grid tariffs due to cross-
subsidization. In the last four years, 3
grid tariffs have increased by
Rajasthan
Maharashtra
Karnataka
Madhya Pradesh
Gujarat*
Uttar Pradesh
Andhra Pradesh
Telangana
Chhattisgarh
Haryana
Odisha
Tamil Nadu
Figure 14: Viability of third-party sale and group captive models by state
Haryana
Rajasthan Uttar
Pradesh
Gujarat Chhattisgarh
Madhya Pradesh
Odisha
Maharashtra
Telangana
Andhra
Pradesh
Karnataka
Tamil
Nadu
Third-party sale & group captive
Group captive
None
Expected project Figure 15: Developers with known open access projects in the pipeline
pipeline for 2021 450
CleanMax
Avaada
Cleantech
Fourth Partner
Aditya Birla
Amplus Solar
Hinduja Renewables
Prozeal Infra
SunSource
Enrich Energy
Various developers have entered
the open access segment and
are planning substantial additional
capacity development in the
coming years: Source: JMK Research
This report finds that Despite these market and In the meantime, corporate buyers
additional corporate regulatory hurdles, government have started to explore new
renewable PPA capacity efforts to introduce electricity business models to steer their
in India fell substantially, sector reforms have the potential renewable power procurement
to 800 MW in 2020, due to to significantly stimulate uptake needs. New PPA offerings like
regulatory hurdles imposed of corporate renewable PPAs in hybrid PPAs have already gained
by state regulators and India. If implemented successfully, traction. Alternative options like
the COVID-19 pandemic. the privatization of loss-making GTAM are now also available to
However, the market is set to DISCOMs can open new pathways fulfill consumers’ renewable power
grow in 2021 as companies to reform the power sector. C&I requirements. In the coming months
seek to meet their renewable consumers would be one of the we also expect corporate buyers
electricity targets, manage most impacted beneficiaries if this to investigate alternative PPA
their electricity costs reform is successful, as it would structures, such as VPPAs and inter-
and obtain tariff certainty facilitate access to a wider array of state PPAs. These structures may
in the longer term. electricity procurement options for compete with the existing models in
corporate buyers at lower prices. the longer run, as open access may
In the short term, COVID-19 caused become a less desirable option due
a market slowdown and project The provision of stricter RPO to the risk of state governments
delays due to site access and compliance according to the withdrawing waivers. In the longer
supply chain constraints. Financial draft Electricity Amendment Bill term, structures including battery
repercussions from the pandemic will also drive the market for new storage, such as utility-scale RTC
also resulted in credit rating open access renewable power PPAs, may also be applicable for
downgrades for some corporate projects. A stable and transparent corporate PPAs.
buyers, which has led project policy framework is crucial to
developers to factor in a greater keeping corporate renewable PPAs Going forward, we expect to see
credit risk, resulting in higher PPA attractive and states should ensure greater demand for corporate
prices for new PPAs signed. In the the implementation of consistent renewable PPAs due to ever-
longer term, PPA prices are likely statutory requirements to ramp up growing corporate sustainability
to stabilize or drop again, owing growth. commitments by companies with
to falling technology costs along operations in India. The current
with an increase in demand from Furthermore, with the Indian PPA project pipeline and the
corporate buyers. Government’s renewed focus on expected increase in demand show
the Make in India initiative to limit that signed PPA capacity additions
In addition to impacts from the the country’s dependence on in 2021 are likely to recover to
COVID-19 pandemic, state- imports, corporate demand from reach the higher volumes
level regulatory hurdles, such the renewable PPA market will be observed in 2019.
as backtracking on waivers to imperative to driving domestic solar
open access charges, imposing module manufacturing.
additional surcharges, restricting
banking provisions for power,
limiting net metering connections
for C&I consumers, and reluctance
in giving net metering connection
approvals to renewable projects,
have also impacted corporate
renewable PPAs in 2020.
average power purchase cost commercial and industrial (C&I): open access: A regulatory
(APPC): The weighted average A business segment set up with the mechanism allowing a grid-
pooled price at which the sole motive of gaining profit. connected bulk consumer, holding
distribution licensee has purchased a valid contract demand for 1,000
commercial operation date
the electricity, including cost of self- kVA or more, to meet part of or
(COD): The date on which the
generation. its entire electricity requirements
commercial operation of the power
through alternative sources.
additional surcharge (AS): plant begins, after successful
DISCOMs impose an additional testing and injection of power at OPEX: An operating expenditure-
surcharge to recover stranded costs the point of delivery (the metering based model in which an investor
due to stranded power purchase point between the power producer invests the upfront capital cost
agreements (PPAs) and stranded and the utility at the pre-determined of the project and the consumer
assets due to consumers procuring voltage level). pays for the electricity consumed/
power through open access. supplied by the project developer.
corporate renewable PPA: An
Appellate Tribunal for Electricity agreement between a private power purchase agreement
(APTEL): Hears appeals against the company and a power producer (PPA): A contract between a power
orders of the adjudicating officer (developer, independent power producer and a buyer of electricity
or the Central and State Electricity producer, investor) to purchase for an agreed tariff, tenor and
Regulatory Commissions under the renewable electricity at a mutually capacity.
Electricity Act, 2003. agreed tariff, tenor and capacity.
renewable purchase obligation
banking: When a generator is cross-subsidy surcharge (CSS): (RPO): Obligations imposed
wheeling electricity, it can virtually A charge levied to recover the cost by a state electricity regulatory
bank the electricity for consumption of the utility providing subsidized commission (SERC) on certain
by an end-customer later. The power to certain categories of entities to purchase electricity from
bank is not a physical electricity consumers, such as the poor, renewable sources.
storage facility; rather, accounting religious entities and agriculture.
state electricity regulatory
methods ensure the virtual banking
DISCOM: A local electricity commission (SERC): The electricity
of electricity.
distribution company. regulator in each Indian state; one
basic custom duty (BCD): A tax of their key responsibilities is to
group captive model: Under this
imposed under Customs Act 1962 determine retail electricity tariffs
unique structure provided under the
that is applicable to imported items; and open access charges.
2003 Electricity Act, C&I consumers
the government has the right to
can set up power plants for their safeguard duty: A tax imposed
create exemptions or reduce the
collective use; they should have at on imported products in order
BCD on any item.
least 26% of the equity in the plant to protect the domestic industry
capacity utilization factor: and must consume at least 51% of against a surge in imports of a
The ratio of the actual electricity the power produced. competing products.
generated by a renewable electricity
independent power producer tariff: The cost per unit of
project over the year to the
(IPP): An entity that is not a public electricity that a buyer pays.
equivalent electricity output at its
utility but that owns facilities to
rated capacity over the year. virtual PPA (VPPA): A contract
generate electric power for sale to
structure where the corporate
captive buyer: The end user of the utilities and end-users.
consumer agrees to purchase a
electricity generated by the captive
net metering: A billing mechanism project’s renewable electricity for a
generating plant.
allowing onsite projects to feed pre-agreed price, without physical
captive model: A power asset in excess electricity to the grid, delivery of electricity.
which the captive buyer consumes reducing their own electricity bills;
hybrid PPA: A contract structure
at least 51% of the electricity usually limited to solar rooftop,
combining the renewable electricity
generated and owns at least 26% of though some states allow other
sources of solar and wind to
the equity. sources to qualify as well.
generate power.
off-taker: The buyer of electricity
in a PPA.
Uttar Pradesh In September 2019, the state In December 2019, the state introduced the Uttar Pradesh Electricity
introduced its regulations for Regulatory Commission (Terms and Condition for Open Access) Regulations,
captive and renewable energy 2019, including:
generating plants, including: • Consumers availing open access facilities will have to pay the transmission
• A 50% exemption on wheeling & wheeling charges, CSS, AS, standby charges (to the distribution
and transmission charges for companies), imbalance charges (if applicable) as described in the regulation
captive and third-party sale and amended from time to time
• A 100% waiver on transmission • No additional surcharge for FY 2020-21
for interstate sales and 100%
exemption of state CSS for
interstate sales of power for
captive/third-party use
Gujarat CSS exempted for third-party sale In May 2020, GERC issued a tariff framework for the procurement of solar
and captive renewable power plants power, including:
• Wheeling charges applicable for third-party sale, while 50% exempted for
captive power
• Transmission losses and charges applicable for both third-party and
captive
• CSS applicable to third-party at 50% of normal CSS
• Additional surcharge of INR 0.37/kWh for open access consumers (third-
party sale only) to be effective from 1 April 2020 to 30 September 2020
Rajasthan The government had waived CSS In December 2019, the state introduced the Rajasthan Solar Energy Policy
for all solar plants commissioned 2019, with transmission and wheeling charges exempted for solar projects of
between April 2014 and March maximum 25 MW capacity, setup between December 2019 and March 2023,
2019; however, it did not extend the as per the following criteria:
exemptions beyond 31 March 2019 • For solar projects setup for captive consumption outside the premises of
the consumer, there is a 50% exemption for transmission and wheeling
charges for 7 years
• For third-party sale open access projects, there is a 50% exemption for
transmission and wheeling charges for 7 years
• For solar projects with storage, for captive/third-party sale, there is a 75%
exemption for transmission and wheeling charges for 7 years.
Additional surcharge of INR 0.80/kWh for open access consumers (third-party
sale) for FY 2020-21.
In November 2020, the state incorporated the RERC (Terms and Conditions
for Tariff determination from Renewable Energy Sources) Regulations, 2020,
including:
• Renewable energy with storage projects installed after the date of
notification of these regulations and before 31 March 2023, shall receive
a 75% exemption in intra-state transmission and wheeling charges. These
projects could be for captive use or for third-party sale under open access.
This exemption is applicable for the first seven years of operation from the
project’s date of commissioning.
Tamil Nadu As per Open Access Regulations, • 50% of transmission and wheeling charges
2005, CSS waived for captive plants • 70% of CSS in case of third-party open access consumers
No AS for captive renewable • 100% exempted in captive power consumer
power plants • AS exempted for captive consumers
• Electricity tax exempted for 2 years
• No additional surcharge for FY 2020-21
Uttarakhand In April 2018, CSS imposed on CSS waived for 3rd party as well
open access consumers except AS of INR 1.11/kWh for open access consumers (third-party sale only) to be
captive plants effective from 1 April 2020 to 30 September 2020.
Uttar All electricity consumers are eligible According to the January 2019 notification, C&I consumers are no longer
Pradesh for net metering eligible for net metering. They can now only opt for gross metering.
Under gross metering, C&I electricity customers will receive 25% higher
compensation than the weighted average tariff of large-scale solar
projects (>5MW), as determined through competitive bidding in the last
financial year.
Tamil Nadu Net metering available for domestic, According to the March 2019 notification, C&I consumers (except low-
commercial and government tension (LT) commercial consumers) are no longer eligible for net metering.
buildings Gross metering is also not allowed for high-tension (HT) C&I consumers.
Himachal All consumers of DISCOMs are Since April 2019, only domestic electricity consumers with a letter of
Pradesh eligible for net metering approval are eligible for net metering, while C&I consumers are no longer
eligible. Gross metering is also not allowed.
Karnataka All electricity consumers are eligible In December 2019, an order passed by the Karnataka Electricity
for net metering Regulatory Commission (KERC) allows net metering or gross metering for
all LT residential electricity consumers. For all other LT & HT categories of
electricity consumers, only gross metering is allowed.
Gujarat RESCO model not allowed Consumers may set up rooftop solar system under the RESCO model
and lease them to third parties; group ownership of solar projects for self-
consumption is also allowed.
West Bengal Net metering available for domestic, In January 2021, the West Bengal Electricity Regulatory Commission
C&I and government consumers issued an amendment stating that consumers having a sanctioned load
demand of up to 5 kW may set up a solar PV system under the net metering
provision. For consumers installing rooftop solar systems with a capacity
greater than 5 kW, only the gross metering facility shall be allowed.
Andhra In November 2019, the state amended its solar, wind and hybrid policies:
Pradesh • The state will withdraw the power to bank energy given to generators for solar, wind and hybrid projects.
• It will treat any injection of electricity between synchronization and declaration of the commercial operation date
(COD) as inadvertent power and the state DISCOMS will pay no fee for it.
Rajasthan In line with the RERC (terms and conditions for tariff determination from renewable energy sources) Regulations
released in November 2020:
• Banking of energy is allowed only for captive consumption within the state, provided that there is a maximum
ceiling of 25% of the energy injected by the renewable electricity captive generating station at the consumption
end on a 15-minute time block basis.
• 10% of the banked energy deducted as banking charges prior to banked energy withdrawal.
Gujarat In May 2020, the Gujarat Electricity Regulatory Commission issued an order that:
• Allows a one-month banking facility.
• Allows the offsetting of excess generation in one billing cycle in proportion to generation in peak and normal
hours.
• Does not allow banking for a third-party and allows offset to take place on a 15-minute time block with open access
consumer consumption. Distribution licensee to purchase surplus power after offsetting at INR 1.75 per unit.
According to the Gujarat Solar Power Policy 2021 released in December 2020:
• For projects under captive use and under third-party sale, a banking charge of INR 1.50/kWh for both high-tension
(HT) and low-tension (LT) consumers is applicable. For MSME units and others that are not demand-based
consumers, it will be INR 1.10 /kWh.
Tamil Nadu The October 2020 order issued by TNERC for the procurement of solar power has the following provisions:
• Banking permitted on a monthly basis.
• Purchase of excess generation/unused banked energy shall be at 75% of lowest tariff as determined during the
year through competitive bidding in the state or by the Solar Energy Corporation of India (SECI).
Madhya October 2019 saw the announcement of the 8th amendment of the co-generation and generation of electricity
Pradesh from renewable energy sources, stating that:
• Banking is no longer available for the captive generation of renewable energy plant generators.
• A captive renewable generation source is a renewable power plant set up by any person to generate electricity
primarily for their own use and includes a power plant set up by any cooperative society or association of persons
to generate electricity primarily for the use of the members of the cooperative society or association.
Source: Tariff orders of various state electricity regulatory commissions, JMK Research
1. Source: Bloomberg New 5. Source: Bridge To India (2020). 9. Note this is larger in scope
Energy Finance (BNEF) (2020). “Rooftop Map”. June 2020. than the RPO, which only refers
“Corporate Clean Energy Buying to targets for wind and solar
Leapt 44% in 2019, Sets New 6. Bloomberg (2020). COVID-19: generation.
Record”. 28 January 2020. Indian companies are getting
Retrieved from: https://about. downgraded like never before. 10. RE100, Climate Group, CDP
bnef.com/blog/corporate- Deccan Herald. 13 May 2020. (2020). Growing renewable
clean-energy-buying-leapt-44- Retrieved from: https://www. power: Companies seizing
in-2019-sets-new-record/. deccanherald.com/business/ leadership opportunities, RE100
business-news/covid-19- 2020 Annual Report. Retrieved
2. edie newsroom (2020). “BNEF: indian-companies-are-getting- from: https://www.there100.
Covid-19 causing drop in downgraded-like-never- org/growing-renewable-power-
US corporate clean energy before-837122.html. companies-seizing-leadership-
purchases”. 14 August 2020. opportunities.
Retrieved from: https://www. 7. International Energy Agency
edie.net/news/10/BNEF-- (IEA) (2021). “Covid-19 impact 11. For more information, see
Covid-19-causing-drop-in- on electricity”. Retrieved from: WBCSD (2018). Innovation in
US-corporate-clean-energy- https://www.iea.org/reports/ Power Purchase Agreement
purchases/. covid-19-impact-on-electricity. Structures.. Available at: https://
www.wbcsd.org/Programs/
3. Ministry of New and Renewable 8. RE100, The Climate Group, Climate-and-Energy/Energy/
Energy (MNRE) (2018). “National CDP (2019). Annual Report. REscale/Resources/Innovation-
Wind Solar Hybrid Policy”. May Going 100% renewable: how in-Power-Purchase-Agreement-
2018. Retrieved from: https:// committed companies are Structures.
mnre.gov.in/img/documents/ demanding a faster market
uploads/2775b59919174bb response – Progress and
7aeb00bb1d5cd269c.pdf. Insights. December 2019.
Retrieved from: https://www.
4. For more information, see there100.org/sites/re100/files/
WBCSD (2019). How multi- 2020-09/RE100Progressand
technology PPAs could InsightsAnnualReport2019.pdf.
help companies reduce
risk. Available at: https://
www.wbcsd.org/Programs/
Climate-and-Energy/Energy/
REscale/Resources/How-multi-
technology-PPAs-could-help-
companies-reduce-risk.
Surbhi Singhvi
Manager, Energy
Singhvi@wbcsd.org
www.wbcsd.org