Technical Site Survey Report

Outdoor – Swap& Expansions


Technical Site Survey Report
AUG4355
Contents

1.Purpose of this document [TSSR].......................................................................................................................................3


2.0 : Site Location/Information.............................................................................................................................................3
3.0 Existing Site & Solution Information:...............................................................................................................................5
3.1 Survey Details:.............................................................................................................................................................5
3.1.1 Site Access Requirements:........................................................................................................................................5
3.1.2 HSE Check & Remarks:.............................................................................................................................................5
3.1.3 Extra Materials/Waste at Site during TSS:................................................................................................................5
3.2: Scope Details..............................................................................................................................................................6
3.3: Site Type.....................................................................................................................................................................6
3.4: Feeder / Feeder less Solution:....................................................................................................................................6
3.5: Existing Huawei 3G Solution.......................................................................................................................................7
3.6: Existing Nokia System Module Details........................................................................................................................7
3.7: Existing Nokia Radios..................................................................................................................................................7
3.8.1 Availability of existing Technologies & Antennae details:........................................................................................8
3.8.2 Antennae Level Information:....................................................................................................................................8
3.8.3 Antennae Port Level Information:..........................................................................................................................10
3.8.3.1 Sector_1 Port Level Details:.....................................................................................Error! Bookmark not defined.
3.8.3.2 Sector_2 Port Level Details:.................................................................................................................................11
3.8.3.3 Sector_3 Port Level Details:.................................................................................................................................12
3.8.3.4 Sector_4 Port Level Details:.....................................................................................Error! Bookmark not defined.
3.10: Existing Power Information....................................................................................................................................14
3.10.1: Existing DC Breaker details & Proposed Design:..................................................................................................15
3.10.2: Location of New Breakers with Picture and description:.....................................................................................16
3.10.3 Rectifier Modules detailed Information:..............................................................................................................17
3.10.4 Rectifier Snapshot with Battery Bank Pictures:....................................................................................................18
3.11: Existing Transmission information..........................................................................................................................18
3.12: Existing Alarm Setup...............................................................................................................................................20
4.0: Proposed Solution [TSSR].............................................................................................................................................20
4.1: Proposed Site Solution:............................................................................................................................................20
5.0: BTS Equipment and RF Requirements..........................................................................................................................20
5.1 System Module Location:..........................................................................................................................................20
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 1 OF 58
AUG4355
Technical Site Survey Report
AUG4355
5.2 New Modules Location:.............................................................................................................................................21
5.3 New Radio Additions:................................................................................................................................................21
5.4 Antennae & RET Requirements:................................................................................................................................23
6.0: Civil Works, Power Consumption and Power Requirements........................................................................................24
6.1 CW Requirements:....................................................................................................................................................24
6.2 Power Consumption:.................................................................................................................................................26
6.3 Power Requirements:................................................................................................................................................27
7.0: Proposed Antenna Location.........................................................................................................................................29
7.1 Sector-1 Proposed Antenna & RET Location:.............................................................................................................29
7.2 Sector-2 Proposed Antenna & RET Location:.............................................................................................................30
7.3 Sector-3 Proposed Antenna & RET Location:.............................................................................................................31
7.4: RF photos gallery ( Sector View )..............................................................................................................................32
Antennas Azimuths.....................................................................................................................................................33
7.5 RF Panoramic Views:.................................................................................................................................................35
8.0: Proposed Location for new System Module & RF Modules ( Floor plan )....................................................................43
8.1 System Module Proposed Location ( Pictures & Floor Plan ).....................................................................................43
8.2 RF Modules Proposed Location:................................................................................................................................44
9.0: Proposed Route for the Additional Power and Fiber Cable..........................................................................................45
9.1: Cabling Diagram ( 3G / 4G )..............................................................................................Error! Bookmark not defined.
9.1.1: Cabling Diagram ( 5G )...............................................................................................Error! Bookmark not defined.
9.2 Cable Summery data:................................................................................................................................................47
10.0: Power Breaker Proposed Location.............................................................................................................................48
11.0: Cables Entry Available Space / Roxtec space..............................................................................................................49
12.0: Site and GSM room Overview Photos........................................................................................................................50
13.0: GPS Antenna Proposed Location................................................................................................................................52
16.0 : TSSR Approvals and Remarks by du Teams...............................................................................................................54

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 2 OF 58
AUG4355
Technical Site Survey Report
AUG4355

1.Purpose of this document [TSSR]


To agree between all parties involved in the site survey, implementation and handover teams on both the
design as well as the Health & Safety arrangements, as stated in the local regulations. This document is, when
fully signed, the go-order for preparing the Engineering Package and to begin the final lease negotiations.

With signing this document, undersigned persons agree with the basic layout and the Health & Safety
arrangements of this site.

NOKIA Networks Team Members during TSS


Area Name Contact# Email ID Remarks
Project Telecom.
SafiullahParacha 055 299 6872 safiullah.paracha@nokia.com
Implementation
Project Telecom.
IslaamAsad 056-4918453 islam_asaad.attia_eissa@nokia.com
Implementation
Project Health
Gilbert Dela Cruz 056 464 6497 gilbert.dela_cruz.ext@nokia.com
and Safety

2.0 :Site Location/Information


Southern Region [Abu Dhabi] # Latitude [decimal]: 24.444556
# Region: □Eastern Region [Al Ain]
□Western Region # Longitude [decimal]: 54.606817

# Site Area:
#
Abu Dhabi [urban, desert, mountain, Urban
Emirate:
etc…
#
Opposite Etihad Plaza
Address:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 3 OF 58
AUG4355
Technical Site Survey Report
AUG4355
# Site Location Map:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 4 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.0 Existing Site &Solution Information:

3.1 Survey Details:


- Site ID: AUG4355

- Technical Survey Date: [03 / 02 / 2021]


- TSSR Submission Date: [06 / 02 / 2021]
- Nokia TI Subcontractor: Innovis Communication & Networks
- POC Name: Abrar

3.1.1Site Access Requirements:

- Padlock Type:DU MasterKey/Yale Lock


- Access Card Type:NA
- Access Permit:NA
- Access Requirements:NA
- Access Time: 24 Hrs
- Access SPOC: NA
- Site Contact Person: NA
- Crane Required: No
- Access Road: Normal
3.1.2HSE Check & Remarks:

- Site main grounding termination:Not Ok……………………………………………………………………………………………………


- Air condition / GSM room temperature:Normal/25 C
- GSM room space status: …Enough space to work for TI Team…………………………………………………………………..
- Issues related to H&S might leads to TI issues:…NA….……………………………………………………………………………………………
- Breakers connected on battery bus bar (other than batteries)No
- Tower/RT structure status: OK
- Fall-Arrest System status: OK

Additional HSE Observations:


……………………………………………………………………………………………………………………………………………………………………………………………………………

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 5 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.1.3Extra Materials/Waste at Site during TSS:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 6 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.2: Scope Details


□New 3G / LTE □New 3G only □3G Additional to LTE
□3G Swap□3G Swap + LTE Addition □3G Swap + LTE Addition + 5G Addition
3G Swap
□New FTTA Solution to be implemented □New 5G only
□________________ Please specify if any other
3.3: Site Type
Greenfield □Site Sharing □Roof Top_6m Pole□GRD□RDU□PalmTree□COW
RDU Monopole__RDU Monopole__ Height:_30m.
Indoor- du GSM Room □Indoor – Sharing □Outdoor- du □Outdoor – Sharing
Sharing Host:__________
3.4: Feeder / Feeder less Solution:
2G_900□Feederless__ Feeder Based_45m
2G_1800□Feederless_45m_Feeder Based_45m
LTE_800□Feeder less_45m □Feeder Based_45m
LTE_1800Feeder less_45m□Feeder Based_45m_
3G_900□Feeder less_100m Feeder Based_45m
3G_2100□Feeder less Feeder Based_45m
5G_3600 Feeder less__ □Feeder Based_45m
5G_2600 Feeder less_45m□Feeder Based
MHA/TMA installed on which feeders, please specify:__3G-2100/TMA_______
Please specify frequencies which are using same feeder line along with Triplexer
__________2G_900/2G_1800/3G_2100__________________________________________

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 7 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.5: Existing Huawei 3G Solution


No. of 3G_900 Sectors__3__ No. of 3G_900 Radios___3___3G_900 Radio Type __MRFU__
No. of 3G_2100 Sectors_3___ No. of 3G_2100 Radios_3__3G_2100 Radio Type _WRFU__
3G Radios installed Indoor Cabinet 3G 900 Radios installed  Indoor Cabinet
BBU Installed Indoor Cabinet BBU Installed □Inside Shelter without Cabinet
BBU Installed □Inside Shelter on 19” Rack

Please add radio / BBU snaps on pictures sections


3.6: Existing Nokia System Module Details
FSMF Installed Air Scale 5G System Module Installed □FSME Installed
FSMF on Ground Installed on Ground □on Ground
□Inside cabinet____ □Installed inside Cabinet_AMOB □Inside Cabinet_____
Indoor Indoor □Indoor
□Outdoor □Outdoor □Outdoor
□FSMF on Pole □Installed on Pole / Wall □on Pole / Wall
# cards:_1XFBBA_1XFBBC# cards:3XABIL,1xASIK# cards:___________

Distance between Airscale& FSMF is __NA__, FSMF shifting required_NA__


3.7: Existing Nokia Radios

2G_900 (Type/Count/Tower/Ground/Height)_____EXGB/3/Ground/0________
2G_1800(Type/Count/Tower/Ground/Height)_____EXDB/3/Ground/0_____
3G_900(Type/Count/Tower/Ground/Height)______NA_________________________
3G_2100(Type/Count/Tower/Ground/Height)_____NA______________________
LTE_800 (Type/Count/Tower/Ground/Height)_____FRMF/1/Tower/28_____
LTE_1800 (Type/Count/Tower/Ground/Height)____FXEB/2/Tower/28___________
5G_3600 (Type/Count/Tower/Ground/Height)_______________
5G_2600 (Type/Count/Tower/Ground/Height)_____AEQD/3/Tower/28__________

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 8 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.8: Existing RF Antennas Information


3.8.1Availability of existing Technologies & Antennae details:
Band [MHz] Existing Antenna Type Antenna Quantity
GSM-900
2G
DCS-1800 DBXLH 6565C 3

4G LTE-1800
LTE-800 KATHREIN 80010869 3
3G 3G-900

3G-2100

7.0: ProposedAntennaLocation

3.8.2 Antennae Level Information:


Sector
Information Sector_1 Sector_2 Sector_3 Sector_4
Model Number Quantity Model Number Quantity Model Number Quantity Model Number Quantity

What is the KATHREIN 80010869 1 KATHREIN 80010869 1 KATHREIN 80010869 1


Manufactur DBXLH 6565C 1 DBXLH 6565C 1 DBXLH 6565C 1
e of the
antenna
Total Antennae in Total Antennae in Total Antennae in Total Antennae
2 2 2
Sector Sector Sector in Sector
Height(HBA Height(HBA
Model Number Model Number Model Number Height(HBA) Model Number Height(HBA)
) )
What are KATHREIN 80010869 28 KATHREIN 80010869 28 KATHREIN 80010869 28
the Antenna
heights(m) ? DBXLH 6565C 28 DBXLH 6565C 28 DBXLH 6565C 28

Model Number M. Tilt Model Number M. Tilt Model Number M. Tilt Model Number M. Tilt
What is the
Mechanical KATHREIN 80010869 0 KATHREIN 80010869 0 KATHREIN 80010869 0
tilt for each DBXLH 6565C 0 DBXLH 6565C 0 DBXLH 6565C 0
antenna?

Model Number Azimuth Model Number Azimuth Model Number Azimuth Model Number Azimuth
What is the
Azimuth for KATHREIN 80010869 110 KATHREIN 80010869 170 KATHREIN 80010869 250
each DBXLH 6565C 110 DBXLH 6565C 170 DBXLH 6565C 250
antenna?

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 9 OF 58
AUG4355
Technical Site Survey Report
AUG4355
Model Number Port Type Model Number Port Type Model Number Port Type Model Number Port Type

What are KATHREIN 80010869 7/16 KATHREIN 80010869 7/16 KATHREIN 80010869 7/16
the port
DBXLH 6565C 7/16 DBXLH 6565C 7/16 DBXLH 6565C 7/16
connector
types ?

If Old
antenna
doesn’t
have Free
ports that
support
LTE Freq,
Is there
available
Pipe on site NA 
to install
new
antenna or
there is
Civil
required for
installing
new pipe.

Additional
Information  NA

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 10 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.8.3.1Sector_1 Antennae Port Level Information:

Sector Information Sector_1

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


Frequency Ranges of existing Antenna? KATHREIN 80010869 698-862(R1) 1695-2690(Y1) 1695-2690(Y2)
880-960(R2)
(Port 1&2 From left to right and from
front of Ant) DBXLH 6565C 824-960(R1) 1710-2180(Y1)

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


How Many Free Ports are free and KATHREIN 80010869 LTE_L800 3G_U900 LTE_L1800 3G_U2100
what is connected?
(2G_G900/2G_G1800/3G_U900/ DBXLH 6565C 2G_G900 2G_G1800
3G_U2100/LTE_L800/LTE_L1800)
     
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

What is the Electrical tilt for each KATHREIN 80010869 Inbuilt Inbuilt Inbuilt Inbuilt
antenna/Freq DBXLH 6565C 8 6

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 Feeder Less Feeder base Feeder Less Feeder base
Feeder/Feeder Less ports ? DBXLH 6565C Feeder base Feeder base

   
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8
KATHREIN 80010869 No No No Yes
TMA/MHAInstalled ?
DBXLH 6565C No No

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

Triplexer / QuadplexemsrModels and KATHREIN 80010869 FREE NA FREE Triplexer


Qty DBXLH 6565C Triplexer Triplexer

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 NA NA NA NA
Combiners Models and Qty
DBXLH 6565C NA NA

Total Ports Free on Sector # 1 with details: NA

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 11 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.8.3.2 Sector_2 Port Level Details:


Sector Information Sector_2

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


Frequency Ranges of existing Antenna? KATHREIN 80010869 698-862(R1) 1695-2690(Y1) 1695-2690(Y2)
880-960(R2)
(Port 1&2 From left to right and from
front of Ant) DBXLH 6565C 824-960(R1) 1710-2180(Y1)

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


How Many Free Ports are free and KATHREIN 80010869 LTE_L800 3G_U900 LTE_L1800 3G_U2100
what is connected?
(2G_G900/2G_G1800/3G_U900/ DBXLH 6565C 2G_G900 2G_G1800
3G_U2100/LTE_L800/LTE_L1800)
     
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

What is the Electrical tilt for each KATHREIN 80010869 Inbuilt Inbuilt Inbuilt Inbuilt
antenna/Freq DBXLH 6565C 6 3

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 Feeder Less Feeder base Feeder Less Feeder base
Feeder/Feeder Less ports ? DBXLH 6565C Feeder base Feeder base

   
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8
KATHREIN 80010869 No No No Yes
TMA/MHAInstalled ?
DBXLH 6565C No No

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

Triplexer / QuadplexemsrModels and KATHREIN 80010869 FREE NA FREE Triplexer


Qty DBXLH 6565C Triplexer Triplexer

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 NA NA NA NA
Combiners Models and Qty
DBXLH 6565C NA NA

Total Ports Free on Sector # 2 with details: NA

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 12 OF 58
AUG4355
Technical Site Survey Report
AUG4355

3.8.3.3 Sector_3 Port Level Details:


Sector Information Sector_3

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


Frequency Ranges of existing Antenna? KATHREIN 80010869 698-862(R1) 1695-2690(Y1) 1695-2690(Y2)
880-960(R2)
(Port 1&2 From left to right and from
front of Ant) DBXLH 6565C 824-960(R1) 1710-2180(Y1)

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


How Many Free Ports are free and KATHREIN 80010869 LTE_L800 3G_U900 LTE_L1800 3G_U2100
what is connected?
(2G_G900/2G_G1800/3G_U900/ DBXLH 6565C 2G_G900 2G_G1800
3G_U2100/LTE_800/LTE_L1800)
     
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

What is the Electrical tilt for each KATHREIN 80010869 Inbuilt Inbuilt Inbuilt Inbuilt
antenna/Freq DBXLH 6565C 7 3

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 Feeder Less Feeder base Feeder Less Feeder base
Feeder/Feeder Less ports ? DBXLH 6565C Feeder base Feeder base

   
Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8
KATHREIN 80010869 NO No No Yes
TMA/MHAInstalled ?
DBXLH 6565C No No

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8

Triplexer / QuadplexemsrModels and KATHREIN 80010869 FREE NA FREE Triplexer


Qty DBXLH 6565C Triplexer Triplexer

Model Number Port_1&2 Port_3&4 Port_5&6 Port_7&8


KATHREIN 80010869 NA NA NA NA
Combiners Models and Qty
DBXLH 6565C NA NA

Total Ports Free on Sector # 3 with details:NA

3.10: Existing Power Information


AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 13 OF 58
AUG4355
Technical Site Survey Report
AUG4355
For more than 01 Rectifier please copy paste the table and fill all of this information *
Site ID AUG4355

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 14 OF 58
AUG4355
Technical Site Survey Report
AUG4355
DC System
Type : DELTA Model Number DPR2000

POWER
BREAKER BREAKER RATING
Breaker CONSUPTIO New EQUIPMENT FEED NR:
SLOT (A)
N (W)
1   FB1 100 A   BATTERY 1  
2   FB2 100 A   BATTERY 2  
3   FB3 100 A   BATTERY 3  
4   FB4 100 A   BATTERY 4  
1   F1 6A   FREE
2   F2 6A   FREE

3   F3 6A   FREE

4   F4 16 A   RTN380AX
REUSE FOR
5   F5 63A 5G_FCOB
AMOD
6   F6 63A   FPFH
7   F7 63A AEQD SEC1
8   F8 10A   FREE COOL

SPACE   FREE

10   F10 63A 2G ESEA


11   F11 63A 2G ESMA
12   F12 SPACE   FREE
13    F13 63A Huawei WCDMA
14    F14 SPACE   FREE
15    F15 63A Huawei MW (M)
16    F16 SPACE   FREE
63A Huawei MW (S)

18    F18 SPACE   FREE


19    F19 63A LTE
20    F20 SPACE   FREE
21          
22          
23            
     
TOTAL: 20

Proposed Breakers: _2 x 125A C.B TRI POLE FPFH(M-S), 63A C.B for AMOD______________

3.10.2: Location of New Breakers with Picture and description:


# Photos:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 15 OF 58
Proposed position FOR 63A C.B FOR Need to be Reshuffle with
1 x 125A C.B TRI POLE AMOD AUG4355
Slim C.B and utilized free
FPFH(S). {REUSE FCOB Space for 1x125amp for
CB} FPEH (M) TRI POLE
Technical Site Survey Report
AUG4355

3.12:Existing Alarm Setup


Total Alarms working on site: _____3_____ Alarms patched on which Technology(2G/3G/4G):____2G_______

4.0: ProposedSolution[TSSR]

4.1:Proposed Site Solution:


Site Model: _____________

□New3G and LTE Site to be Implemented with Single Carrier [900 / 1800 MHz]
□New3G Site to be Implemented with Single Carrier [900 MHz]
□New FTTA solution to be implemented
□New 5G to be implemented
□Existing-LTE [1800 MHz]; 3G SRAN to be Implemented [900 MHz]
Dismantling existing 3G to be replaced by NOKIA. 3G Swap to be implemented.

5.0:BTS Equipment and RF Requirements


5.1 System Module Location:
Indoor – du GSM room □ Outdoor – du
□ Indoor- ETC sharing room □ Outdoor- ETC sharing room
5.2 New Modules Location:
□FSMF Addition Airscale Existing
Location:
AMOD Addition □ AMOB
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 16 OF 58
AUG4355
Technical Site Survey Report
AUG4355
__Ground______
(Ground / Pole / Wall )

□19” RACK(Indoor) □ Other


5.3 NewRadioAdditions:

# NEWRF Module:
□AREA___ARGA_1__
AHPMDA _3___□AHGEA ______□AHGA ______
□AEQE ____ □AQQL ______
□AEHC ____ □AZHL _____□Any other module to be retained _____
# ABIL:
□1 □2 □3
REMARKS: ___________________________

# ASIB:
1 □2 □3
REMARKS: ___________________________

# ABIA:
1 □2 □3
REMARKS: ___________________________

# FBBC:
□1 □2 □3
REMARKS: ___________________________

# RetainedRF Module:
□FXEF___ FXEB__2_
□FXEA __0__ □AREA _1_____ □AHPMDA ______
□FRMA ____ FSMF ___1___
□FRMB ____ □Any other module to be retained _____
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 17 OF 58
AUG4355
Technical Site Survey Report
AUG4355

# ABIL:
□1 □2 □3
REMARKS: ___________________________

# ASIB:
□1 □2 □3
REMARKS: ___________________________

# FBBC:
1 □2 □4
REMARKS: ___________________________

# FBBA:
1 □2 □3
REMARKS: ___________________________

Proposed Solution for New Radios:

Feeder less □ Feeder-Based


□Hybrid □ Outdoor- ETC sharing room
□ Feeder-Based with SBC

5.4 Antennae& RET Requirements:


Antennae Swapping if any : _______YES_______________

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 18 OF 58
AUG4355
Technical Site Survey Report
AUG4355
New Antennae Addition: ______No__________________
# Proposed antennas to be used at each sector: HEXA BAND
# RET cable lengths to be used at each sector: _________3 X 5m___________

□Antennae Addition □Antennae Swap Existing Antennae Utilization


Sec-1: Existing KATHREIN 80010869 port will be use for for 3G Swap.
Option-1: Sec-2 Existing KATHREIN 80010869 port will be use for for 3G Swap.
Sec-3: Existing KATHREIN 80010869 port will be use for for 3G Swap.

Sec-1: Swap KATHREIN 80010869 with HEXABAND for 3G Swap/LTE Expansion.


Option-2: Sec-2 Swap KATHREIN 80010869 with HEXABAND for 3G Swap/LTE Expansion.
Sec-3: Swap KATHREIN 80010869 with HEXABAND for 3G Swap/LTE Expansion

Option-3:

Total Antennae installed on Tower:__6__

6.0: Civil Works, Power Consumption and Power Requirements

6.1 CW Requirements:

CW Requirements OK / Not OK Remarks


Grounding System in Working
Not Ok
Condition.
OK
Grounding Busbar: OK

GSM room space for BBU Ok Available

GSM room space for RRU NA Ok


Air condition system status: Ok OK
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 19 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Cable tray and pole: NOT Ok 7m required


Antennae mounting Pole: NA Not Required

New Radio mounting Pole: OK Use Existing

Roxtec: NOT Ok 1 Required

Concrete Slab: NA Not required

Tower Loading Status: NA Customer need to confirm

Others: NA

# Photos:

GSM room space for RU


Grounding Busbars

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 20 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Air condition system status


Additional power requirements

6.2PowerConsumption:
Power Consumption of SRAN and 5G :
Power Consumption
HW COUNT Total
with 100% load
FCOB 225
AMOD/AMOB 1 1248 1248
AMOD(1xASIB+1xABIA) 170
AMOB
(1xASIA+1xABIA) 287
AMIA
(1xASIA+1xABIA) 210
ASIA 129
ABIA 1 158 158
ASIB 1 129 129

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 21 OF 58
AUG4355
Technical Site Survey Report
AUG4355
ABIL 199
ASIK 180
FSMF 1(Existing) 180 180
FBBC 1(Existing) 147 147
FBBA 1(Existing) 136 136
FRMA 943
FRMB 390
FRMF 1326
FXEA 1031
FWEA_FREA 125
FXEB 2(Existing) 950 1900
FXEF 904
FWEA 125
ARGA 1 1510 1510
AHGA 383
AHPMDA 3 1066 3198
AREA 1481
AHEGA 973
FWGB 125
AQQL 1639
AEHC 1622
AZHL 1030
AEQE 960
Current Consumption DELTA- 54.9V X 124A 6808
Additional Equipment
power required 6243
 TOTAL     13051

6.3 Power Requirements:


Two lengths of 1 x 50mm2 power cableswill be used for FPFH.
2 x 125A DC Circuit breakers to be added in Rectifier forFPFH input
Number of FPFH Required:________1___________

Existing 50mm2 Cable Lengths: ___NA___


New 50mm2 Cable Lengths (Qty): ___2_____
New 50mm2 Cable Lengths (m): ___2x 55m __

FPFH1 to Radios: 3x AHPMDA(25m 16mm2 ), 1 x ARGA (2m 16mm2), 2xFXEB (6m 16mm2)
FPFH2 toRadios:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 22 OF 58
AUG4355
Technical Site Survey Report
AUG4355

# Main GSM room:

View of CB’s inside the rectifier


Available spare breaker inside the Rectifier

Not available

Rectifier current consumption:

# Remote GSM room (in case ACPDB was used):

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 23 OF 58
AUG4355
Technical Site Survey Report
AUG4355

View of CB’s inside ACPDB Available spare breaker inside ACPDB

7.0: ProposedAntenna Location


7.1 Sector-1 Proposed Antenna & RET Location:

Sec-1:RETConnection:Connect RET cable with AHPMDA 1 st priority or ARGA


as 2nd priority

Sec-1-Existing KATHREIN
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS 80010869 will be use. PAGE 24 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.2 Sector-2 Proposed Antenna& RETLocation:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 25 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Option 1: Sec-2:
RET Connection:Connect RET cable with AHPMDA 1st priority or ARGA as 2nd priority

Sec- Existing
KATHREIN 80010869
will be use.

7.3 Sector-3 Proposed Antenna& RETLocation:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 26 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Option 1: Sec-3:
RET Connection:Connect RET cable with AHPMDA 1st priority or ARGA as 2nd priority

Sec-3- Existing
KATHREIN 80010869
will be use.

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 27 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.4: RF photos gallery( Sector View )


Antennas Azimuths

Sector 1: 110 deg

Sector 2: (170) Deg

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 28 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Sector 3: (250) Deg

NA

Sector 4: () Deg

7.5RF Panoramic Views:


Panoramic pictures to be taken in below azimuths Site ENTRANCE
AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 29 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 0

Azimuth 30

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 30 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 60

Azimuth 90

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 31 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 120

Azimuth 150

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 32 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 180

Azimuth 210

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 33 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 240

Azimuth 270

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 34 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Azimuth 300

Azimuth 330

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 35 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-1 Electrical Tilts(KATHREIN 80010869)


LTE-L800 E.tilt-Inbuilt(R1) 3G-U900 E.tilt- Inbuilt (R2)

LTE-L1800 E.tilt- Inbuilt (Y1) 3G-U2100 E.tilt- Inbuilt (Y2)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 36 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-1 Electrical Tilts(DBXLH 6565C)


2G-G900 E.tilt-8(R1) 2G-G1800 E.tilt-3(Y1)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 37 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-2 Electrical Tilts(KATHREIN 80010869)


LTE-L800 E.tilt-Inbuilt(R1) 3G-U900 E.tilt- Inbuilt (R2)

LTE-L1800 E.tilt- Inbuilt (Y1) 3G-U2100 E.tilt- Inbuilt (Y2)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 38 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-2 Electrical Tilts(DBXLH 6565C)


2G-G900 E.tilt-6(R1) 2G-G1800 E.tilt-3(Y1)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 39 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-3 Electrical Tilts(KATHREIN 80010869)


LTE-L800 E.tilt-Inbuilt(R1) 3G-U900 E.tilt- Inbuilt (R2)

LTE-L1800 E.tilt- Inbuilt (Y1) 3G-U2100 E.tilt- Inbuilt (Y2)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 40 OF 58
AUG4355
Technical Site Survey Report
AUG4355

7.6.0 : Sector-3 Electrical Tilts(DBXLH 6565C)


2G-G900 E.tilt-8(R1) 2G-G1800 E.tilt-3(Y1)

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 41 OF 58
AUG4355
Technical Site Survey Report
AUG4355

8.0:Proposed Locationfor newSystem Module & RF Modules( Floor plan )

8.1 System Module Proposed Location( Pictures& Floor Plan )


Both FSMF & Air Scale modules should be close to each other or can be cascaded

FSMF Shifting from old place to new is required or not:__NA_____, cascade FSMF on top of AMOD__Yes_____

Do we need to install new fibers, power cables after FSMF shifting, if Yes please explain:_____NO_________________

Proposed Location for


AMOD.

FCOB Will be replaced


with AMOD and FFSMF
cascade on top

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 42 OF 58
AUG4355
Technical Site Survey Report
AUG4355

8.2 RF Modules Proposed Location:

Space available or not : ______Yes_______ RF Module CW mounts are available or not:___Yes_____

Recommended solution in case if Space is not available:_____Use existing mounts for Radio Mounting_

New CW Mounts required (Yes/No):_____No________ Number of CW mounts required:______No_______

NOTE:

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 43 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Proposed Location for


SEC 1 AHPMDA

Proposed Location for


SEC 2 AHPMDA

Proposed Location for


SEC 3 AHPMDA &
FPFH1

Proposed Location for


ARGA & FPFH

9.0:ProposedRoute for the Additional Power and Fiber Cable

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 44 OF 58
AUG4355
Technical Site Survey Report
AUG4355

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 45 OF 58
AUG4355
5m ½ Jumper Cable

60m Fiber with 2 SFPs

2XFXEB
1X16MM 8m POWER 5m ½ Jumper Cable

AHPMDA
1X16MM 2m POWER

U900/L800
SEC 01 -110˚
9.1: Cabling Diagram ( 3G / 4G )

60m Fiber with 2 SFPs 5m ½ Jumper Cable

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS


5m ½ Jumper Cable

AUG4355
1X16MM 8m POWER

AHPMDA
U900/L800
SEC 02 - 170
AUG4355

NEW AMOD
60m Fiber with 2 SFPs
Technical Site Survey Report

60m Fiber with 2 SFPs 5m ½ Jumper Cable

5m ½ Jumper Cable

ARGA 3G Module
AHPMDA
U900/L800

1X16MM 2m POWER
SEC 03–250˚

1X16MM 9m POWER

2X50MM 55m POWER

Rectifier
FPFH 1

PAGE 46 OF 58
Technical Site Survey Report
AUG4355

9.1.1: Cabling Diagram ( 5G )


Sec1 5G AAU 0”

Sec2 5G AAU 170”

Sec3 5G AAU 240”

16mm DC power
16mm DC power
16mm DC power

5G-FPFH

50mm DC power 55m

GPS
80m Fiber

80m Fiber
80m Fiber

Rectifier
30m GPS Cable

FCOB
25mm DC Power

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 47 OF 58
AUG4355
Technical Site Survey Report
AUG4355

9.2 Cable Summery data:

  From To Length (meter)

BBU (System Module) PDB/Rectifier NA

DC Power Cable RFM/RRH PDB/Rectifier 2 x 55m

Cabinet PDB/Rectifier 10m

AC Power Cable Main AC Rectifier NA

BBU (System Module) Nokia Earth bar 10m

RFM/RRH Nokia Earth bar 15m


Earth cable
Nokia Earth bar Main Earth bar NA

Nokia Cabinet Main Earth bar 10m

BBU (System Module) Customer ODF 1x10m

Optical Fiber Cable 2 x 60m


RFM/RRH BBU (System Module)
2 x 10M

RF Feeder cable RFM/RRH DAS NA

SF Jumper 4.3M-DM 5M
M 12 Jumpers
Jumper Types and Qty.
SF Jumper 4.3MA - DM 6 Jumpers
5M
RET Cable length and Qty.
RRH Antenna 3 X 5m
Connect with AHPMDA

Alarm Cable BBU (System Module) Customer Alarm box 15m

Customer ODF Connector type SC/APC      FC/APC       FC/PC        LC/PC   Other….

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 48 OF 58
AUG4355
Technical Site Survey Report
AUG4355
Jumper Details for each Module:

Module Type Lengt Code Description Require


h d
Quantit
y
AHPMDA/AHG 4.3M-4.3M 3m CS75217.0 SF Jumper 4.3M-4.3M 3M
A 5
AREA/ARGA 4.3M-4.3M 5m CS75107.3 SF Jumper 4.3M-4.3M 5M
5
AHPMDA/AHG 4.3M-DM 5m CS75107.0 SF Jumper 4.3M-DM 5M 12
A 5
AREA/ARGA 4.3MA-DM 5m CS75107.3 SF Jumper 4.3MA - DM 5M
0 6
AREA/ARGA 4.3M-4.3MA 8m CS75107.3 SF Jumper 43MA - 43M 10M
6
AREA/ARGA 4.3MA-DM 8m CS75107.3 SF Jumper 43MA - DM 10M  
1
FXEF/FXEB DMA-4.3M 5M SF Jumper DMA-4.3M 5M

10.0:Power Breaker Proposed Location

Proposed position FOR 63A C.B FOR Need to be Reshuffle with


1 x 125A C.B TRI POLE AMOD Slim C.B and utilized free
FPFH(S). {REUSE FCOB Space for 1x125amp for
CB} FPEH (M) TRI POLE

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 49 OF 58
AUG4355
Technical Site Survey Report
AUG4355

11.0: Cables Entry Available Space / Roxtec space


Existing Roxtex& Cable tray has enough space to install new cables (Yes/No):______Yes________

Entry space available for Monopole towers: __________Yes____________

New RoxtecRequired(Yes/No):____No_____

New Cable Tray Required (Yes / No ):____No________

Any dismantled or Idle cables installed in Roxtec/ Cable Tray:___________No__________________________

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 50 OF 58
AUG4355
Technical Site Survey Report
AUG4355

12.0:Site and GSM room Overview Photos

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 51 OF 58
AUG4355
Technical Site Survey Report
AUG4355

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 52 OF 58
AUG4355
Technical Site Survey Report
AUG4355

13.0: GPS Antenna Proposed Location


Existing GPS cable length Required: ___20M________

Existing LTE GPS

14.0: MW Pole Proposed Location


AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 53 OF 58
AUG4355
Technical Site Survey Report
AUG4355

NA

15.0: Addition Photo gallery taken from site.

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 54 OF 58
AUG4355
Technical Site Survey Report
AUG4355

16.0 :TSSR Approvals and Remarks by du Teams

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 55 OF 58
AUG4355
Technical Site Survey Report
AUG4355

Department Name / Email ID Remarks / Signature / Date

DU TI

DU RF

DU CW

DU TRS
□ IIB Fiber
□ Huawei MW

AUG4355 TECHNICAL SITE SURVEY REPORT – OUTDOOR SWAP & EXPANSIONS PAGE 56 OF 58
AUG4355