TGP SULFUR HANDLING FACILITIES

PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

I PIPE SLEEPERS (ZONE-1, SLEEPER CORRIDOR) WEEK NO. 11 WEEK NO. 12

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Sleeper Foundation Footing Base,


I Sleeper Foundation Pedestal) H H

Concrete Placement & Sampling (Sleeper


J Foundation Footing Base, Sleeper Foundation I W
Pedestal)

K Concrete Coating pre-installation Inspection H H

Inspection & Installation of embedded Items (incl


L Rebars receiving inspection)
TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

II PIPE SUPPORT AREA

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

III IRRIGATION TANK

A Visual Inspection for Site Prep.& Excav. (-) (-)

B Fill Placement & Compaction I S

C Compaction Testing & Sampling I W

D Grade & Site Preparation I W

E Formwork Inspection for Blinding H H

F Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


G Items and Form Closure Inspection H H

H Formwork Instl'n (Ring wall formwork) H H

Concrete Placement & Sampling (Ring wall


I formwork) I W

J Concrete Coating pre-installation Inspection H H

k Inspection of embedded Items (Anchor Bolts)

IV Sulfur Block Area

A Visual Inspection for Site Prep.& Excav. (-) (-)

B Fill Placement & Compaction I S

C Compaction Testing I W

D Material Receiving for HDPE Membrane

V STP RIO Building

A Visual Inspection for Site Prep.& Excav. (-) (-)


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

B Fill Placement & Compaction I S

C Formwork Inspection for Blinding I S

D Concrete Placement & Sampling for Blinding I S

VI CSW drain channel

A Visual Inspection for Site Prep.& Excav. (-) (-)

B Fill Placement & Compaction I S

C Formwork Inspection for Blinding I S

D Concrete Placement & Sampling for Blinding I S

VII Pipe Bridge 04

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Foundation Footing Base, Pipe


I support Pedestal) H H

Concrete Placement & Sampling ( Foundation


J Footing Base, Pipe support Pedestal) I W
TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

Concrete Placement & Sampling ( Foundation


J Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

VIII Pipe Bridge 05

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

IX Pipe Rack 03

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

IX Pipe Rack 04

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H
TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

IX Pipe Rack 08

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n Foundation Footing Base, Pipe


I support Pedestal) H H

Concrete Placement & Sampling ( Foundation


J Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

IX Pipe Rack 09

A Soil Sampling, Testing and Review of Test Reports H H


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n Foundation Footing Base, Pipe


I support Pedestal) H H

Concrete Placement & Sampling ( Foundation


J Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

X Pipe Rack 10

A Soil Sampling, Testing and Review of Test Reports H H

B Visual Inspection for Site Prep.& Excav (-) (-)

C Fill Placement & Compaction I S

D Compaction Testing I W

E Grade & Site Preparation I W

F Formwork Inspection for Blinding H H


TGP SULFUR HANDLING FACILITIES
PACKAGE 14

Nesma & Partners Cont. Co. Ltd


Contract No- 10044546
INSPECTION TWO WEEKS LOOK AHEAD SCHEDULE (Mar-07,2021 TO March-20, 2021)

Inspection Responsibility
Assignments
S/N Activity/Description Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Remarks
NESMA SA
7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar
Package # 14

G Concrete Placement & Sampling for Blinding I W

Installation of Uncoated Steel Rebars, Embedded


H Items and Form Closure Inspection H H

Formwork Instl'n (Pipe Support Foundation Footing


I Base, Pipe support Pedestal) H H

Concrete Placement & Sampling (Pipe Support


J Foundation Footing Base, Pipe support Pedestal) I W

k Concrete repair application & Inspection

l Concrete Coating pre-installation Inspection H H

XI Soil Improvement on Sulfur Storage Tanks 1 & 2

A Material Receiving H RH

Inspection of working level before soil


B Improvement work. W R

Soil Improvement Vibro Replacement (Stone


C Columns) Pre-Installation (Survey) and installtion H H
inspection.

D Installation of Stone Column and Depth H RH

E Daily Vibro Record H RH

Inspection Schedule
PREPARED BY: Tarek Dandachli
Lead Civil Engineer Friday