DAILY REPORT
NO DESCRIPTION
1 Continue washing works on turbine spiral casing.
2 Continue washing works on turbine pit area and draft tube area.
3 Marking defected area for inspection
NO DESCRIPTION
1 Inspection defected area before power tooling works.
2 Start power tooling works on spiral casing, turbine pit and draft tube surface.
NO DESCRIPTION
1 Continue power tooling works on spiral casing, turbine pit and draft tube surface.
FINDINGS
NO DESCRIPTION
1 NIL
MANPOWER LOADINGS
NO MANPOWER LOADING
1 Site Supervisor 1
2 Painter 3
3 Helper 5
No.104,Persiaran Venice Sutera 8
TURCOMP Desa Manjung Raya
32200 Lumut
ENGINEERING SERVICES SDN. BHD. Perak
www.turcomp.com (243046-P) Tel : (05) 6887686
Fax : (05) 6887689
Email: turcomp@turcomp.com
Regional Offices : • Bintulu • Johor Bahru • Kota Kinabalu • Kuala Lumpur • Kuantan • Labuan• Shah Alam• Miri• Manjung
•Malacca• SgPetani
PICTURIOLS
Spiral casing power tooling works. Spiral casing power tooling works.
Spiral casing power tooling works. Spiral casing power tooling works.
No.104,Persiaran Venice Sutera 8
TURCOMP Desa Manjung Raya
32200 Lumut
ENGINEERING SERVICES SDN. BHD. Perak
www.turcomp.com (243046-P) Tel : (05) 6887686
Fax : (05) 6887689
Email: turcomp@turcomp.com
Regional Offices : • Bintulu • Johor Bahru • Kota Kinabalu • Kuala Lumpur • Kuantan • Labuan• Shah Alam• Miri• Manjung
•Malacca• SgPetani
PICTURIOLS
Prepared by:
Derek Reggie Adai
01/10/2018