DAILY REPORT
NO DESCRIPTION
1 Continue washing and cleaning work on spiral casing and turbine pit floor getting ready for surface preparation
inspection on Monday.
2 Clean up dust on pumps and machine at turbine pit floor area.
NO DESCRIPTION
1 Surface preparation inspection before painting of 1st coat.
2 Start paint 1st coat on spiral casing, turbine pit area and draft tube.
NO DESCRIPTION
1 Continue built up 1st coat paint on spiral casing, turbine pit area and draft tube.
FINDINGS
NO DESCRIPTION
1 NIL
MANPOWER LOADINGS
NO MANPOWER LOADING
1 Site Supervisor 1
2 Painter 3
3 Helper 5
No.104,Persiaran Venice Sutera 8
TURCOMP Desa Manjung Raya
32200 Lumut
ENGINEERING SERVICES SDN. BHD. Perak
www.turcomp.com (243046-P) Tel : (05) 6887686
Fax : (05) 6887689
Email: turcomp@turcomp.com
Regional Offices : • Bintulu • Johor Bahru • Kota Kinabalu • Kuala Lumpur • Kuantan • Labuan• Shah Alam• Miri• Manjung
•Malacca• SgPetani
PICTURIOLS
Spiral casing condition before painting works. Spiral casing condition before painting works.
Cover area to avoid painting at turbine pit. Cover area to avoid painting at draft tube.
No.104,Persiaran Venice Sutera 8
TURCOMP Desa Manjung Raya
32200 Lumut
ENGINEERING SERVICES SDN. BHD. Perak
www.turcomp.com (243046-P) Tel : (05) 6887686
Fax : (05) 6887689
Email: turcomp@turcomp.com
Regional Offices : • Bintulu • Johor Bahru • Kota Kinabalu • Kuala Lumpur • Kuantan • Labuan• Shah Alam• Miri• Manjung
•Malacca• SgPetani
PICTURIOLS
Spiral casing 1st coat painting works. Spiral casing 1st coat painting works.
Prepared by:
Derek Reggie Adai
08/10/2018