Drawing 

of Longitudinal Section and MHD 
 

Example: Table below shows ground and formation levels for road construction. Embankments are to be built with side slopes 1:2.5 and cuttings with slopes of 1:3.0.  

The embankment crest width and cutting base width is 13m. Calculate soil volumes between Ch.: 0‐100 and Ch.: 100‐200.    

Chainage Ground  Formation  Chainage Ground  Formation 


(m)  Level  Level  (m)  Level  Level 
(m AD)  (m AD)  (m AD)  (m AD) 

0  28 35 800 4 11

100  29 32 900 3 8

200  32  29  1000  2  5 

300  35  26  1100  ‐5  2 

400  30  23  1200  ‐5  2 

500  19  20  1300  10  5 

600  11  17  1400  15  8 

700  7  14  1500  23  11 

 
Calculations 
Chainage   Ground  Formation  Depth/Height  Motorway  Side slopes  Width D Cross  Volume Cumulative 
  level  Level    width  S    section    volume 
(m)    (m AD)  (m)  (m)  (m)  area  (m3)  (m3) 
(m AD)  (m2) 
0  28  35  ‐7 13 2.5  48 ‐213.5 0 0 
100  29  32  ‐3 13 2.5  28 ‐61.5 ‐13750 ‐13750 
150  30.5  30.5  0 13 2.5  13 0 ‐1537.5 ‐15287.5 
200  32  29  3 13 3  31 66 1650 ‐13637.5 
300  35  26  9 13 3  67 360 21300 7662.5 
400  30  23  7 13 3  55 238 29900 37562.5 
480  20.75  20.75  0 13 3  13 0 9520 47082.5 
500  19  20  ‐1 13 2.5  18 ‐15.5 ‐155 46927.5 
600  11  17  ‐6 13 2.5  43 ‐168 ‐9175 37752.5 
700  7  14  ‐7 13 2.5  48 ‐213.5 ‐19075 18677.5 
800  4  11  ‐7 13 2.5  48 ‐213.5 ‐21350 ‐2672.5 
900  3  8  ‐5 13 2.5  38 ‐127.5 ‐17050 ‐19722.5 
1000  2  5  ‐3 13 2.5  28 ‐61.5 ‐9450 ‐29172.5 
1100  ‐5  2  ‐7 13 2.5  48 ‐213.5 ‐13750 ‐42922.5 
1200  ‐5  2  ‐7 13 2.5  48 ‐213.5 ‐21350 ‐64272.5 
1260  3.6  3.6  0 13 2.5  13 0 ‐6405 ‐70677.5 
1300  10  5  5 13 3  43 140 2800 ‐67877.5 
1400  15  8  7 13 3  55 238 18900 ‐48977.5 
1500  23  11  12 13 3  85 588 41300 ‐7677.5 
 

Note: Red values correspondent to intersection between cut and fill on the longitudinal section. These values needed to be computed in order to get accurate values of the 
cumulative volume (max and min). 

 
  Scale:   Hori. 1:4000 
35 Ground level Longitudinal Section  
    Ver. 1:700 
30
Reduced level (m) 

  25

  20 Formation level 

  15

  10

  5
0
  0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
‐5
  Chainage (m)

 
Mass Haul Diagram  
50000

40000

30000
Cumulative volume (m3) 

20000

10000
Chainage (m) 
0
0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500
‐10000

‐20000

‐30000

‐40000

‐50000

‐60000
Scale:   Hori. 1:4000 
‐70000
  Ver. 1mm = 1250 m3 