Professional Documents
Culture Documents
®
QuakeWrap.com
Fiber-Reinforced
Polymer Pipe Lining
Columns • Beams • Corrosive Environments • Pipes • Floors • Walls • Slabs • Underwater Pile • Blast Protection
Emergency repair to penstock allows power
plant to enter service
BY MO EHSANI AND CARLOS PEÑA
RAPID RESPONSE
Design
The FRP lining was designed to bridge
cracks in the concrete, provide a mois-
ture barrier, and supply additional hoop
strength to compensate for future loss
of circumferential steel due to corrosion.
We designed the adhered FRP laminate
to achieve full deformation compatibility
with the pipe during pressurization, and
we specified bidirectional glass fibers in
the fabric to ensure that existing or future
cracks are intercepted in orthogonal direc-
tions. It should be noted, however, that
although the laminate will prevent water
from leaking from or into the pipe, corro-
sion of the steel reinforcement will not be
slowed significantly in this case due to the
constant presence of seepage water in the
cracks.
The time urgency associated with the
power plant’s imminent start of opera-
tions required placing the entire design
and manufacturing process on a very tight
schedule. Epoxy and fabric manufacturing
plants were placed on accelerated produc-
tion runs and part of the production was
prepared for air cargo transport.
A technical team of two structural engi-
neers and three field supervisors traveled
to Costa Rica to oversee the project and
train the local installation crews. A techni-
cal team fluent in Spanish was required
for the job to run smoothly. Fig. 2: After conventional crack sealing, the penstock failed to
pass a second pressure test.
Fig. 5: Installation of FRP sheets on the interior surface of Fig. 6: Completed lining, including gray top coat, prior to
the pipe. An access point is visible at the lower left testing
The average rate of production of each of the four Selected for reader interest by the editors.
installation stations was 2,500 ft.² (230 m²) of FRP
lining installed in an average 8-hour work day. The —QuakeWrap, Inc.
operation continued 7 days a week, allowing the CIRCLE 51
complete installation of approximately 150,000 ft.²
(14,000 m²) of the FRP lining system in 15 calendar
days. This time included the application of the epoxy
top coat. The FRP lining installation was completed
on July 8, 2009 (Fig. 6), and pressurized test runs ACI Fellow Mo Ehsani is Presi-
were successfully completed on July 15. dent and CEO of QuakeWrap,
Inc., and a Professor of Civil
SERVICE Engineering at the University of
Arizona. He was a pioneer in
Unique challenges of this project included ex-
the development of structural
tensive prep work needed to smooth irregularities applications of FRP technology
caused by the cast-in-place construction procedure, and is internationally recognized
the need to accommodate changes in the vertical as an expert on the subject. He
and horizontal alignment of the pipeline due to the has received BS, MS, and PhD
mountainous topography, the training of local instal- degrees from the University of
lation crews with no previous experience with FRP, Michigan, Ann Arbor, MI.
and the urgent need to minimize downtime of the
power plant. In spite of these unique challenges, the Carlos Peña is President and
project was completed ahead of schedule, making it CEO of QuakeWrap México and
PipeMedic.com