Professional Documents
Culture Documents
03 Cost Deplaoyment Yamashina
03 Cost Deplaoyment Yamashina
Download by: [University of Nebraska, Lincoln] Date: 20 October 2015, At: 11:45
int. j. prod. res., 2002, vol. 40, no. 16, 4077±4091
successfully. In the worst case, manufacturing cost rises with the introduction
of such activities. This is an important issue in manufacturing, but strangely in
the academic literature there have been no studies that have been addressed
directly to the methodology of manufacturing cost reduction. The aim was to
develop a good method that establishes a cost-reduction programme scienti®cally
and systematically. This method, termed `manufacturing cost deployment’, is
a very powerful tool to identify production losses to reduce costs. A simple
algorithm to establish a cost-reduction programme is presented and one case
study is given.
1. Introduction
Each company must continue to make a reasonable pro®t to survive and prosper
in the global competition. Therefore, in manufacturing plants, cost reduction is
one of the major problems in the attainment of this business objective. Therefore,
activities that reduce or eliminate various production losses are promoted in many
companies. For example, TPM (Total Productive Maintenance) for maximizing the
overall equipment e ectiveness, TQM (Total Quality Management) for assuring the
quality of product, IE (Industrial Engineering) for maximizing the e ciency of
operating motion, and JIT (Just In Time) for averaging the production quantity
and reducing the inventory are often curried out in di erent departments (Huang
1991). However, these activities do not necessarily guarantee cost reduction even if
they have been implemented successfully because each activity is not necessarily
performed with the connection between its loss reduction and its possible cost reduc-
tion in mind. In the worst case, manufacturing cost rises with the introduction of
such activities.
There have been no papers that have addressed directly the methodology of
manufacturing cost reduction. Against this background, the purpose of the present
paper is to develop a good methodology that establishes scienti®cally and system-
atically a cost-reduction programme. The following issues will be solved here.
International Journal of Production Research ISSN 0020±7543 print/ISSN 1366±588X online # 2002 Taylor & Francis Ltd
http://www.tandf.co.uk/journals
DOI: 10.1080/00207540210157178
4078 H. Yamashina and T. Kubo
. Investigating various production losses and classifying them into causal losses
and resultant losses.
. Looking for the relationship among the losses, their processes-generatin g cost
and the cost factors. Finding the connection between various kinds of loss
reduction and their possible cost reduction is important.
. Clarifying if the know how on each loss reduction is available and if not
obtaining it if not available.
. Estimating the cost of reducing or eliminating each identi®ed loss and putting
priority to the loss items for the total cost reduction from the viewpoint of cost
and bene®t.
This method has been coined as manufacturing cost deployment because a pro-
Downloaded by [University of Nebraska, Lincoln] at 11:45 20 October 2015
cess leading to cost reduction is deployed based on the programme from the above
four points. In this paper, as the ®rst phase of this study, a manufacturing cost-
deployment approach is developed for a production system that consists of multiple
facilities. After the production system is de®ned, an algorithm to establish a cost-
reduction programme is presented and one case study is given at the end of the
paper.
Figure 2. Matrix.
Figure 5. Relationship among a causal loss, its resultant losses and cost factors.
by each loss. Then, to convert losses into manufacturing cost, they will be classi®ed
into two types: time-related loss type and physical loss type. The former can be
measured in terms of time such as machine stoppages; the latter can be measured
in terms of a quantity such as the number of defectives. An example of a breakdown
in a process will be described below.
In this case, both kinds of loss type can occur. As the time-related loss type, when
the production capacity is smaller than the planned quantity for the period, depre-
ciation cost will rise for lack of production quantity; when the capacity is larger than
the planned quantity, its cost will not rise since the planned quantity can be still
ensured, but direct labour cost and energy cost will rise due to the loading time
prolonged as a result of the breakdown loss. As the physical loss type, defectives
produced as a result of the breakdown will increase the direct material cost as well as
the indirect material cost, tool cost, die and jig cost, and energy cost which were
required for machining in the previous processes (Senju and Fushimi 1982). It is
4082 H. Yamashina and T. Kubo
important and essential that the manufacturing cost increased by resultant losses
must be understood as cost increased by their causal loss.
charge (Yen/h). This method may very often lead to erroneous conclusions. In
fact, the cost reduction when calculated based on this method will never be guaran-
teed. When the production capacity is larger than the planned quantity for the
period, in the worst case, manufacturing cost may rise because of the improvement
cost for reducing the breakdown loss. To obtain the correct results, it should be
calculated as described below.
As shown in ®gure 5, breakdown loss increases the various kinds of cost factor
associated with the time-related and physical loss types in addition to the indirect
labour cost for maintenance workers and the maintenance cost required for repairing
the facility. These cost factors can be calculated by using three indicators: break-
down rate ¶j …1=h†, repair rate ·j …1=h† and the quantity of defectives produced by
the breakdown qj (unit) of facility j. The breakdown loss increases each cost factor as
shown in table 2 depending on the production capacity. Case 1 is when it is below the
planned quantity; Case 2 is when it is above. Thus, improvement for breakdown loss
reduces manufacturing cost in di erent ways in Cases 1 and 2. Detailed descriptions
of the other losses are given in Okazaki (1996).
4.4. Clarifying connections between losses and manufacturin g cost using the C
matrix
The C matrix (®gure 6) is adopted to convert losses into manufacturing cost
based on their equations as given in table 2 and to analyse their results in detail.
This matrix places causal losses and locations of their occurrence as the vertical axis
and cost factors as the horizontal axis. The cost value Cljk is entered into each
component corresponding to the loss l, the process j orP the cost factor k. Also,
the followingP results
P are included in this matrix, the sum Pk P CljkP
of the cost factor
k, the sum l j Cljk of P the loss l and the process j, and l l k Cljk that is the
total of all components. P k CPljk shows how each loss increases the manufacturing
cost at each process, and l j Cljk shows how each factor of the manufacturing
cost is increased by losses in the production system. Thus, the C matrix allows the
quantitative analysis of connections among losses, and the locations of their occur-
rence and cost factors as opposed to the A matrix that focuses on qualitative analysis
of losses.
Breakdown Breakdown rate of facility j …1=h†: ¶j Speed down loss Theoretical cycle time of facility j …s†: ¬*j
loss Repair rate of facility j …1=h†: ·j Actual cycle time of facility j(s): ¬ ‡ j
Number of defectives produced by the breakdown (unit): qj Defective loss Defective rate of facility j (1/unit): ®j
Set-up loss Number of set-ups in a period: Ns Management loss Man power of the production system (Men): f1
Set-up time of facility j (min): ¸j Operating motion loss Man power of the production system (Men): f2
Number of defectives produced during the adjustment Logistics loss Man power of the production system (Men): f3
(unit): nj
Tool change Number of units produced between the two tool changes of Line organization loss Man power of the production system (Men): f4
loss facility j (unit): ½j Measurement loss Measurement rate of facility j (1/unit): kj
Tool changing time of facility j (min): j Measurement time of facility j (min): Áj
Number of defectives produced during the adjustment Yield loss Yield ratio: r
(unit): nj
Start up Number of start-ups in a period: Np Indirect material loss Theoretical and actual cost of facility j (Yen/unit)
loss Start-up time of facility j (min): sj Die and jig losses The number of units produced between the two
Number of defectives produced during the adjustment die and jig changes of facility j (unit): ²j
Manufacturin g cost deployment
(unit): nj
Short stop- Short stop rate of facility j (1/unit): ± j Energy loss Theoretical and actual cost of facility j (Yen/unit)
page loss Repair time of facility j (min): tj
Loss Case Factor Parameter Formula (Yen/unit) Loss Case Factor Parameter Formula (Yen/unit)
4084
… CVj †NS nj =d
DLC NS ; ¸j CL C L NS …¸j =60†=d TC ®j CTj
P CP
(1) Case 1: d > Capacity of the production system. Case 2: d < Capacity of the production system.
(2) Facility b: bottleneck in the production system
CM : direct material cost (Yen/unit); CL : direct labour cost (Yen/h); CI : indirect labour cost (Yen/h); C* V j , CVj : theoretical and actual energy costs of facility j (Yen/unit); CPja : repair cost of item of
facility j (Yen/unit). a: broken part.
(3) CF : depreciation cost of the production system (Yen/period); C* Sj . CSj : theoretical and actual indirect material costs of facility j (Yen/unit); CTj : tool cost of facility j (Yen); CDj : die and jig costs
of facility j (Yen); CE : energy costs of the production system (Yen/h).
®es causes of each loss and eliminates it in the short-term. The other type is the
systematic approach such as operative maintenance and preventive maintenance,
which are continuous activities in the long-term. As shown in ®gure 7, the D
matrix is made to consider the e ective improvement techniques for each loss with
reference to signi®cant knowledge in the past. This matrix places causal losses and
locations of their occurrence as the vertical axis and improvement techniques as the
horizontal axis. The mark * indicates which improvement technique should be
adopted for each loss at each process. By using this matrix, it is possible to clarify
what improvement activities should be implemented for each loss at each process in
the production system as well as what kinds of knowledge are required to reduce
losses.
production quantity d is indicated as Ew …yj³ ). The bene®t value of the activity xj³
is obtained by further subtracting the cost for the activity from this value, shown as
Ew …yj³ † ¡ z…yj³ †.
Based on the foregoing, when the group of activities in each period is indicated as
Xw , the problem of establishing a cost-reduction programme that can maximize the
cumulative bene®t value throughout the whole period can be formulated as follows
when considering the cost and the period required for the activity xj³ :
X
W X
Y X
J
Objective function: max fEw …yj³ † ¡ z…yj³ †g!j³w
wˆ1 ³ˆ1 j ˆ1
!j³w ˆ 0 or 1:
This problem is to determine the group of activities Xw in each period and
identify the group throughout the whole period (X1 ; X2 ; . . . ; XW ) such that the objec-
tive function can be maximized under some constraints above. This is an integer
programming problem to determine !j³w ˆ 0 or 1. It means that one determines
whether or not the activity xj³ should be implemented under some constraints.
The scale of this problem depends on the number of facilities J, all kinds of loss
Y and the subject period W. In general, this problem is NP-complete in an actual
production system.
Figure 8. E matrix (matrix of estimated cost to improve loss and expected cost reduction).
X
W
fEw …yj³ † ¡ z…yj³ †g
wˆ1
Investment efficiency in activity xj³ ˆ :
X
Yj³
z…yj³ †
yj³ ˆ1
7. Example of an application
The manufacturing cost-deploymen t approach proposed here was applied to a
case study to evaluate its viability. Improvement activities for breakdown, set-up,
tool change, start up, short stoppage, speed down and defective losses in each facility
of the production system shown in ®gure 9 are considered in this case study. Table 3
shows the values of indicators to do with losses. The conventional approach in TPM
(which promotes various activities for maximizing the overall equipment e ective-
ness) and the manufacturin g cost-deployment approach were applied respectively to
this case study to compare the results.
Figure 10 shows the results of cost reduction achieved by the conventional and
manufacturing cost-deployment approaches. The horizontal and vertical axes in
®gure 10 show the activity periods and rate compared with the manufacturing cost
Manufacturin g cost deployment 4089
Figure 11. Comparisons of the total economic e ect among the approaches.
the conventional approach has not necessarily led to an e cient cost reduction, and
by applying the manufacturing cost-deployment approach, a cost-reduction pro-
gramme that can ensure maximum bene®t with minimum cost for improvement
can be established.
8. Conclusion
Various activities in manufacturin g plants do not necessarily guarantee cost
reduction even if they have been implemented successfully, since each activity is
not necessarily promoted with ®nding a connection between its loss reduction and
possible cost reduction. Against this background, the manufacturing cost-deploy-
ment approach that can establish a cost-reduction programme scienti®cally and
systematically has been developed.
. A and B matrices that can be used to identify losses in a production system and
clarify cause-and-e ect relationships among them have been proposed.
. A concept and equations for converting losses into manufacturing cost have
been described, and the C matrix to give detailed analysis of the results has
been proposed.
. The D matrix to clarify improvement techniques for losses and the E matrix to
analyse investment e ciency in each activity has been proposed.
. A method to establish an improvement programme that will lead to an e cient
cost reduction has been described, and its viability has been veri®ed in the case
study.
The manufacturing cost-deployment approach makes it possible to clarify a
process leading to cost reduction by using these ®ve matrices. Therefore, it is possible
to establish a programme that can ensure maximum bene®t with minimum cost for
improvement activities. Thus, this approach is a very powerful tool in the promotion
of various activities to achieve business objectives.
Manufacturin g cost deployment 4091
Acknowledgements
The study was sponsored by research funds from the Ministry of Education and
Science of the Japanese Government.
References
Huang, P. Y ., 1991, World-class manufacturing in the 1990s. Integrating TQC, JIT, FA and
TPM with worker participation. Manufacturing Review, 4, 87±95.
Ishimatsu, Y ., 1987, Cost Management and Cost Improvement for Design and Manufacturing
Divisions (Tokyo: Nikkan Kogyo Shinbun).
Okazaki, K ., 1996, Study on manufacturing cost deployment. Master’s thesis, Department of
Precision Engineering, Graduate School of Engineering, Kyoto University, Japan.
Oshima, E. and Morooka, T., 1992, Introduction of Plant Engineering (Tokyo: Japanese
Downloaded by [University of Nebraska, Lincoln] at 11:45 20 October 2015
Standards Association).
Senju, S. and Fushimi, T ., 1982, Economics Engineering (Tokyo: Japan Management
Association).
Son, Y. K ., 1991, A cost estimation model of advanced manufacturing systems. International
Journal of Production Research, 28, 441±452.