You are on page 1of 2

INCREASE EAST WEST PIPELINE CAPACITY

Project No.: BI-10-01214

Contractor:- PETROJET Sub-Contractor: Month: Year:


Equipment TYPE:- COMPRESSOR Location:
Equipment Serial#: Manufacturer: Model#:
SN. Item Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Equipment has valid certificate of inspection
2 Equipment has monthly inspection sticker
3 Equipment body in good condition and clean
4 Engine Oil level
5 Oil Leaks
6 Fuel Tank Cap
7 Fuel Tank Condition
8 Earth Grounding
9 Earthing Clamp / Terminal Connection
10 Ground Fault Circuit Intertors& Earth Leak Circuit Breaker( GFCI /ELCB)
11 Cable Connection
12 Cable Wire Condition
13 Receptacle Condition
14 Plug Condition
15 Battery Condition
16 Power Switch
17 Air Filter Condition
18 Drip Tray
19 Fire Extinguisher
20 Tyre Condition
21 Towing bar in good condition
22 Machine lifting eye in good condition
23 Others
Checked By: Verified By: Remarks