Material Estimation For Construction of A House
Material Estimation For Construction of A House
Submitt ed to:
Sir Hassan
Submitt ed By:
Muhammad
Shafaat Nawaz
2011-
CRP-28
Shahid Ali
Khan
2011-CRP-
45
Department
of City and
Regional
Planning,
University
of
Engineering
and
Technology
01. Amount of Excavation
As we know that excavation will be carried at very bottom. So, excavation level for walls of width 9” will
be at 27” depth while for walls 4.5” wide will be at 21” depth.
= 26.125’
= 10.6875’
= 11.625’
= 15.8125’
= 8.625’
= 42.375’
Similarly,
We have already found lengths for 22.5” width while finding amount of excavation. We can utilize those
calculations here as under:
= 26.125’ – 4.5”
= 25.75’
= 10.6875’ – 4.5”/2
= 10.5’
= 11.625’ – 4.5”
= 11.25’
Length of L.W 4 = We don’t need to find length of L.W 4 here because this is 4.5”
wall and at this level, for this wall we’ll be using P.C.C.
Length of L.W 5 = We don’t need to find length of L.W 5 here because it is 4.5” wall
and at this level, for this wall we’ll be using P.C.C.
= 42.75’
Similarly,
Length of S.W 6 = We don’t need to find length of S.W 6 here because it is 4.5” wall
and at this level, for this wall we’ll be using P.C.C.
Length of S.W 7 = We don’t need to find length of S.W 7 here because it is 4.5” wall
and at this level, for this wall we’ll be using P.C.C.
At
18"
Numbe Length Width Height Quantity (Cubic
Wall
r (ft.) (ft.) (ft.) ft.)
L.W.1 3 25.75 1.5 0.5 57.94
L.W.
1 10.5 1.5 0.5 7.88
2
L.W.
1 11.25 1.5 0.5 8.44
3
L.W.
1 - - - -
4
L.W.
1 - - - -
5
S.W.1 1 42.75 1.5 0.5 32.06
S.W.
1 9.25 1.5 0.5 6.94
2
S.W.
1 12.25 1.5 0.5 9.19
3
S.W.
1 14.25 1.5 0.5 10.69
4
S.W.
1 29.56 1.5 0.5 22.17
5
S.W.
1 - - - -
6
S.W.7 1 - - - -
Sum 155.30
At 13.5” width Level:
= 25.375’
= 10.5’– 4.5”/2
= 10.3125’
= 11.25’ – 4.5”
= 10.875’
= 15.4375’ – 4.5”/2
= 15.25’
= 7.875’ – 4.5”
= 7.5’
= 43.125 + 4.5”
= 43.5’
Similarly,
Length of S.W 6 = 4’
= 25.375’– 4.5”
= 25’
= 10.3125’– 4.5”/2
= 10.125’
= 10.875’– 4.5”
= 10.5’
= 15.25’– 4.5”/2
= 15.0625’
= 7.5’– 4.5”
= 7.125’
= 43.5’ + 4.5”
= 43.875’
Similarly,
1420
Number of bricks required for 1 ft3 = bricks
100
1420
Number of bricks required for 484.4ft3 = × 484.4= 6,879 bricks
100
Length of Long Walls and Short Walls has been calculated in finding amount of excavation. So using those
values, amount of concrete in foundation can be found as under:
Thus,
= 111.81 x 1.54
1
Quantity of Cement = ×172.1874
13
As we know
So,
13.24 cubic feet of cement will be bags = 13.24/1.25 = 11 bags
It’s important to note that we are not going to provide any D.P.C under doors. Thus we can simply
subtract volume for openings and can find final amount of D.P.C required.
Openings Volume
Length Width Height
Doors Quantity (Cubic ft.)
(ft.) (ft.) (ft.)
D1 7 0.75 0.08 0.44
D2 3 0.75 0.08 0.19
D3 3 0.75 0.08 0.19
D4 3 0.75 0.08 0.19
D5 3 0.75 0.08 0.19
D6 3 0.75 0.08 0.19
D7 2 0.375 0.08 0.06
Sum 1.44
So,
= 20.559 ft3
1
Quantity of cement = × 20.559
7
= 2.937 ft3
At 9"
Length Width Quantity (Cubic
Wall Number Height (ft.)
(ft.) (ft.) ft.)
L.W.1 3 25 0.75 10 562.50
L.W.
1 10.125 0.75 10 75.94
2
L.W.
1 10.5 0.75 10 78.75
3
L.W.
1 15.0625 0.75 10 112.97
4
L.W.
1 7.125 0.75 10 53.44
5
S.W.1 1 43.875 0.75 10 329.06
S.W.
1 10.75 0.75 10 80.63
2
S.W.
1 13.75 0.75 10 103.13
3
S.W.
1 15.75 0.75 10 118.13
4
S.W.
1 31.06 0.75 10 232.95
5
S.W.
1 4.75 0.75 10 35.63
6
S.W.7 1 14.125 0.75 10 105.94
Sum 1889.04
Now, we’ll calculate volume of openings
Openings Volume
Doors/Window Length Width Height
s (ft.) (ft.) (ft.) Quantity (Cubic ft.)
D1 7 0.75 7 36.75
D2 3 0.75 7 15.75
D3 3 0.75 7 15.75
D4 3 0.75 7 15.75
D5 3 0.75 7 15.75
D6 3 0.75 7 15.75
D7 2 0.375 7 5.25
W1 5 0.75 4 15
W2 5 0.75 4 15
W3 5 0.75 4 15
W4 5 0.75 4 15
W5 2 0.375 2 1.5
Sum 182.25
Total Amount of Brick Work = 1889.04 – 182.25 = 1706.79ft 3
1420
Number of bricks required for 1 ft3 = bricks
100
1420
Number of bricks required for 1706.79 ft3 = ×1706.79 = 24,236 bricks
100
As we have calculated the amount of cement required for both P.C.C and D.P.C and also bricks for both
foundation and super-structure, we can simply estimate the cost of material.
Total Number of Bricks Required = Bricks for foundation + Bricks for Super-Structure
= 6789 + 24236
= 31,025
= Rs. 248,200
Total bags of Cement Required = Bags required for D.P.C + Bags required for P.C.C
= 3 + 11
= 14
= Rs. 6720
Apart from this, there will be extra cost for excavation, and aggregates and sand cost, water cost, labor
cost and other miscellaneous costs.