Costing & Estimation HOW TO CALCULATE CONSTRUCTION COST PER SQUARE FEET OF A HOUSE

It is very essential to calculate the construction cost of a house for making budget or arrange finance,
as construction cost is increasing day by day.

I have made a complete series regarding learning how to calculate the construction cost of a house
per square feet. Also, in last I will upload a excel sheet of construction estimate, you have to just
update the new rates and measurements and you will get the cost of your house.

Today, we will discuss about the total construction cost of a g+1 floor house.

We divide into four parts for calculating the construction cost of a house.

Understanding the stages involves in construction of house

There are several parts of a building house, 1- RCC stage, 2- Finishing Stage, 3-Decor stage,4-
Handover stage.

1- RCC stage

contains Excavation, Back filling, Concreting (beam-columns, slab, lintel, chajjas, footing, coping,
etc.), shattering, BBS, Curing, etc.

2- finishing stage

contains masonry, plaster, color work, electrical wiring, plumbing, fabrication, glass work, door-
window fittings, flooring, false ceiling, kitchen point, dedo tiles, etc.

3- Décor stage

contains plantation, furniture, wallpaper, decorative paints, curtain, etc.


4- Handover stage

means the testing of a house for living, it include some of minor works or some remaining revision
works to be done.

In this article, we will discuss about the construction cost of RCC part of the house.

Construction cost of RCC work (material)

Before calculations we need all the relative drawings and information regarding the house.

Here are some data regarding construction,

Cement- Ambuja, 53 Grade

Grade of concrete - M20 (1:1.5:3)

Grade of PCC - M15 (1:2:4)

Sand - local fine sand

Grade of mortar- 1:4 and 1:6

Plaster thickness - 20 mm external walls

; 10 mm internal walls

Thickness of walls- 9 inch outer wall

; 4.5 inch partition wall

Here are drawings for the calculations of construction cost of house.


3D view

You can see 3D design of the house, which we will calculate the construction cost.
Architectural plan

Two master bedroom, kitchen and living room with common bathroom are provided in this plan.
Beam-columns layout plan

Here you can see beam column layout plan with the dimensions.
Section-plan

This is the front side section plan of the house.

You can see a vertical dimensions of each level. Also, every columns contains the footing.

Size of structural members are given in below table.

Sr. No. Beam No Length Breadth Width


1 B1 Varies 9 18

2 B2 Varies 9 15

3 B3 Varies 9 12

4 C1 Varies 9 18

5 C2 Varies 9 15

6 Coping 1 Varies 9 4.5

7 Coping 2 Varies 4.5 4.5

8 Lintel 1 Varies 9 4.5

9 Lintel 2 Varies 4.5 4.5

10 Footing 4’ 4’ 1’6” height

11 Main Door 7’ - 4’ height

12 Internal door 7’ - 3’ height

13 W1 4’ - 5’ height

14 W2 4’ - 4’ height

15 V 2’ - 2’ height

We will start numbering from bottom left to right and left bottom to top for beam and column you
can see that numbering in beam column layout plan.

Before calculating the construction cost of a house we need quantities of various structural members
like beam, columns, slabs, footing, lintels, coping, PCC, etc.

Column quantity
First we will calculate rectangular column of 9x18 inch. Formula for calculating volume of rectangle is
L x B x H.

We have 18.5 feet height and width of 9 inch means 9/12= 0.75 feet breadth of 18/12 = 1.5 feet.

We will multiply 0.75x1.5x18.5 and we will get 20.8 cum. Ft.

We will do the same calculation for all the columns.

After calculating all the columns we are getting 239.3 cum. ft. volume of the concrete in columns
only.

We will convert it on to cum. m. for ease of calculation.

Beam quantity
For beams, the calculation is same as beam is also rectangular in shape.

In the case of beam, we will consider in to in distance for finding the length of the beam.

You can see B1-1 beam is 11.16 feet long and cross sectional dimensions are 9 x 18 inch means 0.75 x
1.5.

Volume for B1-1 is 11.16x0.75x1.5 = 12.56 cum. ft.

After finding all the length we need a final quantity of concrete used in the all beams.

I have provided Ground beam and first floor beam with same dimensions for ease of calculations.

So, for all beams we have quantity of concrete is 222.31 x 2 = 444.62 cum. ft.

Slab quantity
For slabs, the calculation is same but the area will be varies for each slab, you can find the
dimensions in the plan and calculation in above image.

Footing quantity

I have provided the same footing for all the columns for ease of understanding. You can find a
calculation in above image.

We have footing size of 4'x4'x1.5' = 24 cum. ft.

Lintel & coping quantity


We generally provide lintels at 7 feet from plinth level, 9 inch lintel is used in the outer wall and 4.5
inch thick lintel used in the all internal walls.

Sometimes coping is provided below the window for screwing purpose or some other purpose.

In our case we will consider lump sump of 12 cum. ft. concrete in coping.

Also in parapet wall we will provide coping.

PCC quantity calculations

PCC means plain cement concrete. We don't use reinforcement in PCC. PCC can not beam tensile
load, as steel rebar is not used on it.

In footing bed we use PCC, Thickness of PCC is 4 Inch and 6 inch bigger than footing in all the
directions.

So we will get PCC of 5 x 5 x 0.25 feet which is 6.25 cum. ft.

We have 12 footings So total PCC will be 12 x 6.25 = 75 cum. ft. which is 2.16 cum. m.

In ground/plinth slab we also use PCC. So, we get total 4.95 cum. m. of M15 grade PCC slab at the
plinth level.

Now the total 2.16+4.95 = 7.11 of PCC work to be done.

Steel quantity calculations

For calculating steel in the structural members, we use thumb rule for now.

As we know the density of steel is 7850 kg/m3. which means in 1 m3 of steel weight is 7850 kg.

For columns, we take 2.5% steel.

So, 2.5% of 6.75 m3 of concrete in the case of columns.

Steel in columns= (2.5x7850x6.75)/100 = 1324.68 kg


In the case of beams, we will take 2% of 12.6m3,

So, steel in beam = (2x7850x12.6)/100= 1978.2 kg

For slab, we will take 1%.

Steel in slab = (1x7850x4.95)/100=388.57 kg

For footings, we will take 0.8%.

Steel in footing = (0.8x7850x8.61)/100=540.71 kg

For lintels = (2x7850x2.46)/100 = 386.22 kg

Total steel = 1324.68+1978.2+388.57+540.71+386.22= 4618.38 kg

We will consider 5000 kg steel (wastage, additional work) for this house.

After this calculations, we have below values.

Concrete in columns - 6.78 cum. m.

Concrete in beams - 12.6 cum. m.

Concrete in slabs - 4.95 cum. m.

Concrete in footings - 8.61 cum. m.

Concrete in lintels & coping (M15) - 2.46 cum. m.

PCC(M15)- 2.16 cum. m.

PCC slab(M15) - 4.95 cum. m.

Concrete = 6.78+12.6+4.95+8.61= 32.94 m3

We will need total 32.94 m3 M20 grade concrete.

In M20 (1:1.5:3) grade concrete, 8.22 bags cement, 616.5 kg sand and 1233 kg aggregate is used.

So in our case we will need,

Cement = 8.22 x 32.94 = 271 bags

Sand = 616.5 x 32.94 = 20308 kg


Aggregate = 1233 x 32.94 = 40615 kg

We need, 2.46+2.16+4.95 = 9.57 m3 of M15 grade concrete.

In M15 (1:2:4) grade concrete, 6.34 bags cement, 634 kg sand and 1268 kg aggregate is used.

Cement = 6.34 x 9.57 = 61 bags

Sand = 634 x 9.57 = 6068 kg

Aggregate = 1268 x 9.57 = 12135 kg.

Now, we have material cost of RCC structure from rates and quantity of various items.

Material rates varies from place to place and time to time, currently I am using the rates of Gujarat
region.

For 1 ton of steel we will take 10 kg of binding wire and 10 kg nail as per past experience.

We don't consider the shattering material cost because it will be in the scope of the contractor.

Unit Volume Rate Total

Cement (Bags) 332 420 1,39,440 ₹

Sand (ton) 26.380 650 17,150 ₹

Aggregate (ton) 52.750 580 30,600 ₹

Steel (kg) 5000 72 3,60,000 ₹

Binding wire (kg) 50 80 4,000 ₹

Nail (kg) 50 80 4,000 ₹

Total - - 5,55,190 ₹

Conclusion

From the above calculations and discussion we can say that construction cost material of RCC of
supposed house is 5,55,190 INR.

We have 22' x 40' feet which is 880 square feet house. So, construction cost per square feet will be
555190/880 = 630.9 INR.

We have two slabs in this plan (G+1) , In some region people provide the rates according to slabs.

So, in our case the construction cost per square feet is 316 INR.
After quantity calculations and material rate calculation we will discuss about the labor rates for RCC
construction in the next article.

 Tweet

 Share

 Share

 Share

 Share

NEWEST

PREVIOUS
concrete mix design as per is 10262 (2009)

Conversion Emoticon

Popular Posts

Design of beam as per IS: 456

Part-4: Design of RCC beam The work of the structure designer is to provide the beam size and
reinforcement detailing plan to the architect ...

Size of beams, slab load distribution and beam layout plan

Part-3: Beam grid After placing the column position and orientation , the next step is to draw a beam
grid and to define the slabs on all fl...

Design of slab : Two way slab design as per IS : 456 - 2000

Design of two way slab The design of the RCC slab classified by the spanning as one way and two-way
slab. We have calculated the one-way sl...

Design of cantilever beam, point load on beam and doubly reinforced beam

Cantilever beam If the one end is fixed and another end is free in a beam, then the beam is called a
cantilever beam. The top surface or the...

Design of slab : one way slab design

Part 5 - One way and two-way slab design To design the slab, we specify the reinforcement detail
according to the span length by either one-...

CATEGORIES

 Admixtures in concrete

 civil career

 concrete

 concrete mix design

 Construction material

 Costing & Estimation

 FiberReinforcedConcrete

 FLOOR PLANS

 HouseStructureDesign

 infrastructure


 RECENT

 POPULAR

 COMMENTS

 How to calculate construction cost per square feet of a house

2022-12-01Learneverything

 concrete mix design as per is 10262 (2009)

2022-11-10Learneverything

 Role of civil engineer in construction of building: skills, tips for improving career as civil
engineer

2022-11-01Learneverything

 Cement sheet : price, use, size

2022-10-21Learneverything

 Small house plan : Indian style small house design with photos

2022-10-15Learneverything

SUBSCRIBE HERE

PAGES

 Home

 Privacy Policy

 Terms and Conditions

 sitemap

AUTHOR

Learneverything

View my complete profile


POPULAR POSTS

Design of beam as per IS: 456

Part-4: Design of RCC beam The work of the structure designer is to provide the beam size and
reinforcement detailing plan to the architect ...