Professional Documents
Culture Documents
SL Particulars PG
NO
NO
1 Procedure for construction
2 Plan
3 details Reinforcement
3.1 Beam
3.2 Column
3.3 Slab
4 On -Site observation
Shuttering or formwork for slab, beam and
staircase
5 Shuttering or formwork for column
6 Brick Work
Electrical work
8 Plumbing
9 Plastering
RMC
Concrete Mixer
12 Chipping
13 Spacing in reinforcement (slab)
14 Nominal cover
15 Lateral ties Spacing ,uses
16 Stirrup spacing ,uses
17 Doors
18 UPVC Windows
19 Curing
Concrete Mixer:
Fig 1 –mixer, Fig 2-Handle, Fig 3- Hopper, Fig 4- cylinder with blades
1)In the site the above mixer used to make concrete for columns
2)Here the cement, fine aggregate and coarse aggregate are taken in ratio 1:2:3
5)W
e add water of required (generally for above ratio we take 0.5 proportion)
Here in above figure, we can see jack screw which can be adjusted to required height
Fig 3: Preparing for channel placement on which shutter boxes where laid
FIGURE –4
Fig 4: Ready for channels placing to support the shutter boxes from below
Note: Here steels nails are used to join the shutter boxes to wooden pieces and shutter
boxes have already holes to place the nails.
Fig 5: It Shows the beam shuttering
Fig 6: sometimes we use reinforcement bars between shutter boxes
Fig 7: Bottom view after placing shutter boxes on the channels
Figure –8 Figure – 9
Fig –8: Here the laborer was applying oil on shutter boxes, to prevent the shutter boxes
sticking to concrete after casting.
Fig-9: Here wooden pieces were used in shuttering because sometimes the room
dimensions will not have exact shutter boxes to fit. So wooden pieces were cut on sight
and placed as required.
Figure-10 Figure-11
Fig 10: Monolithically the Staircase Shuttering will be done along with slab.
Fig 11: Different sizes of shutter boxes were used. Here 3ft/1ft and 3ft/9ft and 2ft/2ft
were in picture.
Figure –12,13
NOTE: In our site RMC is used for slab ,beams and staircase
1)During night times only RMC is placed Because construction site is in a commercial
area which has transportation problems during daytime due to traffic.
2)Admixtures were used to increase setting time.
3)Shuttering labor is also present during placing of RMC because sometimes due to
improper fixing of shuttering boxes some of them may lose the joints so concrete falls
down.
4)Before the RMC truck came Motor Pumps and the pipes were fitted in site.
FIGURE 14
FIGURE15
FIG 14: Motar for transferring concrete from truck to required floor.
FIG 15: As work done during night-time Lights were used.
FIGURE-16 FIGURE-17
FIGURE-18 FIGURE-19 FIGURE-20
FIGURE-21
FIGURE-16: A cover with sand is kept below the junction box in slab because of that
there will be no settling of concrete so that we can take connections for that room that’s
the reason cover with sand is kept below the junction box
FIGURE-17: Before the concrete is poured, the ceiling Conduits must be laid in the
prepared shutter works of the ceiling slab. - Pipes, junction boxes, components, joints,
etc. should be placed along the pipes.
Use a deep junction box for fan, spotlight, surface mounted lighting fixtures and cable
pulling.
FIGURE-18: We are checking that the junction box is kept as per per plan or not it can
slightly vary.
The junction box should keep in middle of the room.
FIGURE-19: we are checking that electrical connections are given as per dimension
given in plan or not.
FIGURE -20: we can look that hole is given for switch board.
FIGURE-21: after completing steel work they are doing electrical work as per give in
plan