You are on page 1of 13

PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.

: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

5.0 PLANT & MACHINERIES


Detail of plant, machinery and tool proposed to be used to perform work:

No. Plant (mobile), Machinery (static) and Qty.


tool (if any)
1. Backhoe
2. Lorry / Loader
3. Rammer / Compactor According to site condition
4. Tools box
5. Measuring tape

6.0 MATERIAL
Materials delivered on site will be inspected and verify prior to use.

No. Type of Material Remark


1. Common brick
2. Cement
3. Sand
4. Concrete Grade 30
5. BRC A7
6. Precast Concrete Cover
7. Pipe Culvert

7.0 WORK EXECUTION METHOD

7.1 Precast U-Drain / Block Drain


1. Stacking
All unit should be stacked uniformly on levelled ground
2. Setting Out
Setting out/pegging for precast drain line shall be established by surveyor
3. Excavation
Excavation for surface drainage shall be carried out to the dimensions
4. Compaction
The drain shall be laid on 150mm thk layer by layer of crush aggregate to the proper
falls and joined straight true to lines and levels.

Revision: 00 Revision Date: 30 Jun 2020 Page: 5 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

5. Jointing
Precast Drain is supplied with plain butt joints in standard length. Cement mortar is
normally used to fill gap between U-Drain units
6. Handling
The weep holes provided the U-Drain units double up as lifting holes for handling. A
spreader beam should be used when slinging the units to avoid crack in the legs
7. Laying
Precast U-Drain should be laid on the prepared bedding. However, in bad ground
condition, it may be necessary to excavate deeper and place with a layer of hard-core
before placing the sand bedding as according to the engineer specification and details

7.2 Brick Drain


1. The contractor shall notify
any excavation. Excavation for drain shall be carried out to the dimensions as shown in
the drawing.
2. Reinforced compact base slab shall be 225mm thick with one layer of BRC A7 and 50
mm lean concrete grade 15 blinding under.
3. 225mm diameter half round stoneware glazed ware drain shall be laid on concrete base
with benching both sides rendered in cement mortar(1:2) rendering internally with 20mm
cement and sand (1:6).
4. Brickwall shall be 230mm thick for height not exceeding 1050mm, 345mm thick for height
exceeding 1050mm but not exceeding 1500mm and 460mm thick for height exceeding
1500mm.
5. 20mm thick cement mortar rendering shall be applied to internal face of brickwall.
6. 75mm diameter stoneware pipes shall be laid as weepholes at 3000mm center to center
with 230mm X 230mm X 230mm crushed stoned as filter pocket.
7. 125mm X 125mm reinforced concrete struts at 3000mm center to center shall be
provided at height 1000mm.
8. All excavated area shall be backfilled with suitable material which shall be free from large
lumps, wood and other extraneous material.
9. The top of the brickwall shall be set down to allow for finishes by Others. FFL to follow as
per

Revision: 00 Revision Date: 30 Jun 2020 Page: 6 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

7.4 Pipe Culvert Class 2 (600mm dia 1500mm dia)


1. Excavation for pipe culvert shall be carried out to the dimensions and size as shown in
the drawing complete with strutting and formwork. Temporary strutting design and
calculations with PE endorsement shall be submit in separate submission.
2. The trench to receive a culvert pipe shall be of sufficient width and depth to enable the
placing of bedding material and construction of pipe joints.
3. Hardcore for bedding shall be laid and compacted, then 50mm thk lean concrete shall
be laid on top.
4. 150mm thick concrete bedding shall consist of clean,natural sand or gravelly sand of
suitable gradation and quality.
5. The pipes shall be laid on bedding in conformity with the dimensions shown on the
drawings and true to the line and level.
6. The annular gap shall be filled with cement sand mortar (1:3) with only sufficient water
added to ensure adequate workability.
7. All spaces excavated shall be backfilled with material that is free from large lumps and
wood. Backfill shall be placed in layers not more than 250mm in depth (compacted
measurement) and shall be compacted to s density comparable with the adjacent
undisturbed material.

7.5 BRICK SUMP


1. Excavation and internal dimension for sump shall be in accordance to a depth and size
as shown in the drawing.
2. Concrete bed shall be grade 20 and 230mm thick with one layer of BRC A7 and 50 mm
thick lean concrete.
3. Brickwall shall be 225mm thick for height not exceeding 900mm and 345mm thick for
the remaining.
4. Rendering all exposed surface with 20mm thick cement and sand (1:3) plastering and
shall be completed with galvanized steel steps (300mm centres vertically).
5. The sump shall include 225mm thick reinforced concrete capping and forming opening
size 610mm X 405mm to receive finished by Others FFL to follow as per Landscape

6. The top of brick sump shall be set down to allow for finishes by Others as per approved
shop drawings.

Revision: 00 Revision Date: 30 Jun 2020 Page: 7 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

7. Backfill with suitable earth stockpiled and compact the sides.

7.6 RC SUMP
1. Excavation and internal dimension for sump shall be in accordance to a depth and size
as shown in the drawing.
2. Concrete bed shall be grade 25 and 300mm thick with reinforcement bar and 50 mm
thick lean concrete or as per approved shop drawings.
3. Reinforced concrete wall shall be 300mm thick with reinforcement except or as per
approved shop drawings.
4. Shall be completed with galvanized steel steps (300mm centres vertically).
5. The sump shall include 225mm thick reinforced concrete capping and forming opening
size 610mm x 405mm to receive finished by Others. FFL to follow as per Landscape

7.7 CONSTRUCTION SEQUENCE FROM SUM 12 TO EXISTING DBKL MAIN DRAINAGE


GENERAL SCOPE OF WORKS PIPE JACKING METHOD

1. Jacking method for lay pipe culvert from SUM 12 to SUM 13A (Wingwall).
2. 900mm Reinforced Concrete jacking pipe will jack toward SUM 12 and SUM 13A.
3. To lower the impact to stadium, RC caisson with 3.6m and 5.0m internal diameter to be
constructed.
4. 3.6m ID for SUM 12 to construct to received tunnel boring machine (receiving pit) while
5.0 ID for SUM 13 as jacking pit.
5. Pit SUM 13 shall be jacking pit with both direction.
6. While at slope surface will introduce temporary concrete wall as exist TBM machine on
jacking at SUM13A direction.
7. Jacking sequence shall be :
a. Jacking from SUM 13 to SUM 12

b. Jacking from SUM 13 to SUM 13A

Revision: 00 Revision Date: 30 Jun 2020 Page: 8 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

Mobilization

Pit team and jacking team to be mobilized to the site to carry out the pipe jacking
works. The team shall consist the following:-

No. Manpower Unit

1 Construction Manager 1

2 Site Supervisor 1

3 Team Leader 1

4 Worker 4

5 Excavator (S100 or S200) 1

6 Mobile Crane (20 tonnes) 1

7 Tipper Lorry (10 wheeler) 1

8 Microtunneling Machine (sized 500mm) 1

Pit Excavation

The pit is to be prepared for pipe jacking and manhole construction. Pit shall be
constructed in a proper sequence of steps to ensure the quality and safety of workers
and adjacent structures. The proposed location of pit has to be properly trim flat for
working platform and the position has to set out by competent surveyor. Pit can only
be constructed at a location which is free from buried services/structure. Any
services located within the pit shall be relocated.

Please refer to Enclosure A for information on Type of Pit used at site and detail
design calculation for jacking pit and receiving pit.

Revision: 00 Revision Date: 30 Jun 2020 Page: 9 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

Precast Concrete Caisson

Precast Concrete Caisson is to be used at jacking pit and receiving pit for the following:-

Pit Pit
Size
Jacking Pit Internal Diameter: 5.0m (One/two direction jacking)

Receiving Internal Diameter: 3.6m


Pit

a) The top 600mm of soil to be removed. The precast concrete caisson


Ø3600/ 5000mm to be installed at the excavated hole.
b) Further 600mm depth of soil to be removed. The caisson ring to be
lower to further 600mm deep and a new ring to be installed on top.
c) Step to be repeated until the caisson ring reached to the proposed level.
d) If the underground water or seepage is encounter or soil strata are found
different from the soil investigation during excavation, the designer shall
be notified immediately for necessary design review.
e) Dewatering to be carried out by mean of a water pump at the bottom of
the caisson or point well system if required.
f) In case of sand blowing and piping occurs in the sandy layer or basal
heave in collapsible soil, sheetpile cofferdam or jet grouting shall be
used to cut off the inflow of groundwater to the less permeable layer
before proceeding with excavation.
g) The excavation works is carried out by means of manual digging using
hand tolls and pneumatic tools such as pick hammer and jack hammer
if hard materials are encountered. Manual rock splitting technique will
be used if encounter boulders or socketing into bedrock.
h) The base for the caisson ring to be concreted with Concrete G20.

Revision: 00 Revision Date: 30 Jun 2020 Page: 10 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

PIPE JACKING METHOD (MICROTUNNELING SYSTEM)

General

The slurry microtunneling system is complete with all equipment necessary to drive
non man- entry tunnels by the pipe jacking method.
The system is designed for tunnelling, without the use of ground improvement
processes such as compressed air, ground treatment of freezing, in water bearing
grounds with a head of up to 15 metres of ground water.
Owing to the small size of the launch and reception shafts required by the system
and the compact containerised design of the equipment, it is ideal for use in urban
areas.

Thrust Pit or Launching Shaft

A working shaft is constructed at the beginning of the section of pipeline to be


jacked and specialist equipments are installed. Jacking operations are carried
out from this point.

The dimensions and construction of the thrust pit vary according to specific
requirements of any particular situation with economic being a key factor. Drives by
mechanised excavation may require larger pits than hand excavated drives. Pipe
jacking can be performed from small shafts to meet special site conditions.

The initial alignment of the pipe to be jacked is ensured by accurately positioning


guide rails on which the pipes are to be laid.

The substantial forces required for jacking the pipes that provided by high-pressure
hydraulic power packs. The ram diameter and stroke of the jack may vary
according to an individual contractor's technique. Short stroke jacks with multiple
spacer blocks, medium stroke jacks with shorter length pipes or long stroke jacks
which can push a full length pipe at one setting may be used.

To ensure that the jacking forces are distributed around the circumference of a
pipe being jacked, a thrust ring is provided of a design dependent on the number
of jacks being used. The jacks are interconnected hydraulically to ensure that the
thrust from each is the same. The numbers of jacks used may vary according to
the pipe size, the length to be jacked and the anticipated frictional resistance.

Revision: 00 Revision Date: 30 Jun 2020 Page: 11 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

Setting Out Inside Jacking Pit

The alignment and level are transfer into the pit using theodolite.

Place steel plate and concrete the thrust wall and the base to the required line and

level. Install the guide rails and check alignment using theodolite.

Place the hydraulic jacks as necessary at the positions against the steel
plate/concrete thrust wall.

Check the road level by using theodolite.

Tunnelling Operation

The cutting head is thrust against the tunnel face by hydraulic cylinders
located in the launching shaft.

To commence a drive, particularly in conditions under the ground water level, the
head is capable of cutting its way through the concrete wall of the launch shaft through
a seal assembly bolted to the shaft wall to exclude groundwater

Cutting Head

The cutting wheel is equipped with carbide tipped tools to cut the entire face of
the tunnel. Excavated material passes through openings in the cutting wheel into
the crushing/mixing chamber.

Here, the conical crusher reduces the material to a size suitable for conveying to the
surface settling tank by pump water being injected through nozzles in the
crushing/mixing chamber to assist mixing without blockage.

The cutting wheel is driven by hydraulic motors located within the cutting head
assembly - thus excavating and crushing power is not dependent upon distance
from the launch shaft as with auger driven equipment.

The cutting head assembly consists of two sections, which are articulated to allow
movement of up to approx. 3.5 degree in any direction to enable precise steering
of the thrust.

Cutter disc can be equipped with hard rock cutting wheels. Specially developed
disc cutters for microtunnelling are now available for proven performance with
rock strengths.

Revision: 00 Revision Date: 30 Jun 2020 Page: 12 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

Lengths Of Thrust

Limitations are reached by jacking pipe strength and laser resolution, thus reducing
accuracy over longer distances.

The standard machine package includes 100m of hydraulic hoses, electric cables
and slurry pipes.

Control/Power Pack Module

The control/power pack module is housed within an ISO standard freight container
providing rapid relocation from shaft to shaft.

A target plate is hermetically sealed within the cutting head for the impinging
laser beam to define the exact position of the machine. An encoder is located in
the launch shaft to provide continuous measurement of the length of thrust.

Via the main processor, the actual position of the cutting head is calculated and
displayed graphically on a monitor built into the control panel. A complete record
of the thrust is stored by the processor and a print - out is available at any time
during the thrust via the printer provided in the control/power pack module.

Material Conveyance

A centrifugal pump located next to the settling tank on the surface pressurises the
feed water to the crushing/mixing chamber nozzles. The reduced excavated
material is mixed with the feed water to form slurry which is pumped out by the
slurry pump located in the launch shaft.

The pumps have infinitely variable speed controls to adapt to varying ground
conditions and balance flow rates.

By-pass valve systems within the cutting head enable washing out of the lines and
partial recirculation. These valves also isolate the cutting head whilst the pipeline is
broken to insert a new concrete (or other pipe material) pipe. Thus, face support
can be maintained whilst the slurry material transport system is disconnected when
putting in a new jacking pipe.

The slurry is pimped into a settling tank on the surface from which the feed water
is drawn. The settled excavated material is removed at intervals from the settling
tank as required.

Revision: 00 Revision Date: 30 Jun 2020 Page: 13 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

TBM Jacking Operation (Pipe 900mm ID )

a. Jacking operation to be commenced once both the jacking pit and


receiving pit is completed.
b. First place the cutting head with pilot pipe in position.
c. Then place the first length of the Jacking Pipe on the guide rail behind the
cutting head.
d. Start the tunnelling operation as highlighted in earlier section.
e. Place the second piece of Jacking Pipe to the first Jacking Pipe with collar
joint.
f. Proceed with the tunnelling operations.
g. Repeat steps `d' and `e' until the required distance of the crossing to be
jacked.
h. The alignment and level of the pipeline will be checked using laser theodolite.

Option : Manshield Jacking Operation ( Pipe 1200mm ID shall be used)

a. Jacking operation to be commenced once both the jacking pit and


receiving pit is completed or the alignment establish.
b. First place pilot pipe in position true to line and level and jack into the
ground. Check line and level using theodolite.
c. Excavate the soil/rock inside the pilot pipe using manual equipment/hand
tools, retrieve excavated materials to jacking pit pipe end. The gap
between the pilot pipe and front face of the soil/rock will be always
minima.
d. Then follow with the first length of reinforced concrete jacking pipe.
Check line and level using theodolite. Repeat the jacking and excavation
operation.
e. Place the second reinforced concrete jacking pipe on the guide rail by
proceed jacking and excavating. Checks line and level at each new pipe
length installed.
f. Repeat step `c' and `d' until up to the required distance of the crossing to be
pipe jacked.
g. Horizontal alignment of the pipeline will be checked by plumb and offset
or by using a theodolite. The vertical alignment will be checked by using
a levelling instrument.
h. If the alignment or level of the pipes is deviated, the pipe alignment can
be adjusted by introduce saddle/hard material under cutter head.
i. The pipeline will be checked and reported for final alignment at completion of
the crossing.
j. The jacking operation will be continued right underneath the road crossing.

Revision: 00 Revision Date: 30 Jun 2020 Page: 14 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

k. Recheck the road level to ensure no settlement.


Personnel and Workmanship

The working crew for pipe network consists of one experienced foreman and 4 - 5
experienced workers. The foreman, experienced in the pipe jacking, shall be present
at all times whilst work is proceeding. He shall be responsible for the checking of the
pipe alignment and level in accordance with this method statement. The foreman shall
be the site designated safety office, responsible for the site safety.

ENCLOSURE A

SCHEMATIC DIAGRAM OF Tunnel Boring Mechine METHOD

ENCLOSURE B

SCHEMATIC DIAGRAM OF Mansheild METHOD

Revision: 00 Revision Date: 30 Jun 2020 Page: 15 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

7.8 CONNECTION TO DBKL MAIN DRAINAGE

A HAND-DUG CAISSON FOR SUM 14

The caissons shall be carried out in a proper sequence of steps so as to ensure


quality and safety of workers and adjacent structures.

1. Leveling working platform and Setting out caisson pile position. Excavate a pilot
bole with depth not exceeding 1000 mm and diameter around 200mm -
300mrn larger than the caisson diameter.

2. Inside the pilot hole a circular steel mould, which has an inner diameter equals
to caisson diameter, is set up in the exact position of the caisson to be
constructed.

3. Pour concrete of grade 25 around the gap between the mould and the vertical soil
surface,

4. After the concrete has gained the required strength the circular steel mould
is dismantled. A concrete caisson lining is thus formed to prevent collapse of
soil,

5. Before further excavation is continued, a supporting frame about 3.0m high is


erected in the ground surface above and across the caisson opening. This
temporary frame supports an l chain block, which is used to transport
excavated material form the caisson bottom to the ground surface.

6. A safety barrier is then set up on top of the caisson opening.

7. Continue to excavate not more than the ring mould depth of soil each time
and subsequent concrete lining is again formed with the steel mould by
lowering down from the upper ring.

8. If underground water is encountered at time during the excavation,


dewatering is done by means of a water pump installed at the bottom of the
caisson.

9. Continue excavation and concreting of lining until after reaching the designed
bottom level of caisson or socketing into the bedrock formation as required by
Engineer.

Revision: 00 Revision Date: 30 Jun 2020 Page: 16 of 23


PNB 118 Document No: BP03-QA-MS-CIV-01846 Rev.: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement

B SHEET PILE FROM SUM 14 to EXIST DBKL DRAIN

Sheetpile Cofferdam

Pit Size Pipe Material Pipe Size

9 m x 2.4 m x 3.0m (D) Reinforced Concrete Pipe (RCJP) ID Ø 900mm

a) Steel H-Beam (minimum) is placed on ground at the four side of the pit
forming a rectangular shape wailer:
b) Sheet pile FSP3A is drive at the perimeter of the wailer beam by means of
vibro-hammer or excavator up to the required depth-using 6m sheet pile.
c) The soil within the pit is then excavated to the designed depth.

d) Wailer beam is to be provided at the designed level (if required).

e) The excavation and placing of wailer beam is to be done in stages.

f) Upon reaching the formation level, the base is then clean and concrete using
mass concrete to form a working platform at base.
g) pit.

C CONNECTION TO EXIST DBKL DRAIN

1. Existing paver will cut using diamond cutter

2. Excavate till depth required

3. Hack existing DBKL drain

4. Slot pipe culvert into existing drain

5. Seal gap between pipe to hacking drain wall with concrete G20

6. Backfill with sand

7. Premix

Revision: 00 Revision Date: 30 Jun 2020 Page: 17 of 23

You might also like