Professional Documents
Culture Documents
: 01
METHOD STATEMENT FOR DRAINAGE WORK SYSTEM (PLOT 3)
Project Method Statement
6.0 MATERIAL
Materials delivered on site will be inspected and verify prior to use.
5. Jointing
Precast Drain is supplied with plain butt joints in standard length. Cement mortar is
normally used to fill gap between U-Drain units
6. Handling
The weep holes provided the U-Drain units double up as lifting holes for handling. A
spreader beam should be used when slinging the units to avoid crack in the legs
7. Laying
Precast U-Drain should be laid on the prepared bedding. However, in bad ground
condition, it may be necessary to excavate deeper and place with a layer of hard-core
before placing the sand bedding as according to the engineer specification and details
6. The top of brick sump shall be set down to allow for finishes by Others as per approved
shop drawings.
7.6 RC SUMP
1. Excavation and internal dimension for sump shall be in accordance to a depth and size
as shown in the drawing.
2. Concrete bed shall be grade 25 and 300mm thick with reinforcement bar and 50 mm
thick lean concrete or as per approved shop drawings.
3. Reinforced concrete wall shall be 300mm thick with reinforcement except or as per
approved shop drawings.
4. Shall be completed with galvanized steel steps (300mm centres vertically).
5. The sump shall include 225mm thick reinforced concrete capping and forming opening
size 610mm x 405mm to receive finished by Others. FFL to follow as per Landscape
1. Jacking method for lay pipe culvert from SUM 12 to SUM 13A (Wingwall).
2. 900mm Reinforced Concrete jacking pipe will jack toward SUM 12 and SUM 13A.
3. To lower the impact to stadium, RC caisson with 3.6m and 5.0m internal diameter to be
constructed.
4. 3.6m ID for SUM 12 to construct to received tunnel boring machine (receiving pit) while
5.0 ID for SUM 13 as jacking pit.
5. Pit SUM 13 shall be jacking pit with both direction.
6. While at slope surface will introduce temporary concrete wall as exist TBM machine on
jacking at SUM13A direction.
7. Jacking sequence shall be :
a. Jacking from SUM 13 to SUM 12
Mobilization
Pit team and jacking team to be mobilized to the site to carry out the pipe jacking
works. The team shall consist the following:-
1 Construction Manager 1
2 Site Supervisor 1
3 Team Leader 1
4 Worker 4
Pit Excavation
The pit is to be prepared for pipe jacking and manhole construction. Pit shall be
constructed in a proper sequence of steps to ensure the quality and safety of workers
and adjacent structures. The proposed location of pit has to be properly trim flat for
working platform and the position has to set out by competent surveyor. Pit can only
be constructed at a location which is free from buried services/structure. Any
services located within the pit shall be relocated.
Please refer to Enclosure A for information on Type of Pit used at site and detail
design calculation for jacking pit and receiving pit.
Precast Concrete Caisson is to be used at jacking pit and receiving pit for the following:-
Pit Pit
Size
Jacking Pit Internal Diameter: 5.0m (One/two direction jacking)
General
The slurry microtunneling system is complete with all equipment necessary to drive
non man- entry tunnels by the pipe jacking method.
The system is designed for tunnelling, without the use of ground improvement
processes such as compressed air, ground treatment of freezing, in water bearing
grounds with a head of up to 15 metres of ground water.
Owing to the small size of the launch and reception shafts required by the system
and the compact containerised design of the equipment, it is ideal for use in urban
areas.
The dimensions and construction of the thrust pit vary according to specific
requirements of any particular situation with economic being a key factor. Drives by
mechanised excavation may require larger pits than hand excavated drives. Pipe
jacking can be performed from small shafts to meet special site conditions.
The substantial forces required for jacking the pipes that provided by high-pressure
hydraulic power packs. The ram diameter and stroke of the jack may vary
according to an individual contractor's technique. Short stroke jacks with multiple
spacer blocks, medium stroke jacks with shorter length pipes or long stroke jacks
which can push a full length pipe at one setting may be used.
To ensure that the jacking forces are distributed around the circumference of a
pipe being jacked, a thrust ring is provided of a design dependent on the number
of jacks being used. The jacks are interconnected hydraulically to ensure that the
thrust from each is the same. The numbers of jacks used may vary according to
the pipe size, the length to be jacked and the anticipated frictional resistance.
The alignment and level are transfer into the pit using theodolite.
Place steel plate and concrete the thrust wall and the base to the required line and
level. Install the guide rails and check alignment using theodolite.
Place the hydraulic jacks as necessary at the positions against the steel
plate/concrete thrust wall.
Tunnelling Operation
The cutting head is thrust against the tunnel face by hydraulic cylinders
located in the launching shaft.
To commence a drive, particularly in conditions under the ground water level, the
head is capable of cutting its way through the concrete wall of the launch shaft through
a seal assembly bolted to the shaft wall to exclude groundwater
Cutting Head
The cutting wheel is equipped with carbide tipped tools to cut the entire face of
the tunnel. Excavated material passes through openings in the cutting wheel into
the crushing/mixing chamber.
Here, the conical crusher reduces the material to a size suitable for conveying to the
surface settling tank by pump water being injected through nozzles in the
crushing/mixing chamber to assist mixing without blockage.
The cutting wheel is driven by hydraulic motors located within the cutting head
assembly - thus excavating and crushing power is not dependent upon distance
from the launch shaft as with auger driven equipment.
The cutting head assembly consists of two sections, which are articulated to allow
movement of up to approx. 3.5 degree in any direction to enable precise steering
of the thrust.
Cutter disc can be equipped with hard rock cutting wheels. Specially developed
disc cutters for microtunnelling are now available for proven performance with
rock strengths.
Lengths Of Thrust
Limitations are reached by jacking pipe strength and laser resolution, thus reducing
accuracy over longer distances.
The standard machine package includes 100m of hydraulic hoses, electric cables
and slurry pipes.
The control/power pack module is housed within an ISO standard freight container
providing rapid relocation from shaft to shaft.
A target plate is hermetically sealed within the cutting head for the impinging
laser beam to define the exact position of the machine. An encoder is located in
the launch shaft to provide continuous measurement of the length of thrust.
Via the main processor, the actual position of the cutting head is calculated and
displayed graphically on a monitor built into the control panel. A complete record
of the thrust is stored by the processor and a print - out is available at any time
during the thrust via the printer provided in the control/power pack module.
Material Conveyance
A centrifugal pump located next to the settling tank on the surface pressurises the
feed water to the crushing/mixing chamber nozzles. The reduced excavated
material is mixed with the feed water to form slurry which is pumped out by the
slurry pump located in the launch shaft.
The pumps have infinitely variable speed controls to adapt to varying ground
conditions and balance flow rates.
By-pass valve systems within the cutting head enable washing out of the lines and
partial recirculation. These valves also isolate the cutting head whilst the pipeline is
broken to insert a new concrete (or other pipe material) pipe. Thus, face support
can be maintained whilst the slurry material transport system is disconnected when
putting in a new jacking pipe.
The slurry is pimped into a settling tank on the surface from which the feed water
is drawn. The settled excavated material is removed at intervals from the settling
tank as required.
The working crew for pipe network consists of one experienced foreman and 4 - 5
experienced workers. The foreman, experienced in the pipe jacking, shall be present
at all times whilst work is proceeding. He shall be responsible for the checking of the
pipe alignment and level in accordance with this method statement. The foreman shall
be the site designated safety office, responsible for the site safety.
ENCLOSURE A
ENCLOSURE B
1. Leveling working platform and Setting out caisson pile position. Excavate a pilot
bole with depth not exceeding 1000 mm and diameter around 200mm -
300mrn larger than the caisson diameter.
2. Inside the pilot hole a circular steel mould, which has an inner diameter equals
to caisson diameter, is set up in the exact position of the caisson to be
constructed.
3. Pour concrete of grade 25 around the gap between the mould and the vertical soil
surface,
4. After the concrete has gained the required strength the circular steel mould
is dismantled. A concrete caisson lining is thus formed to prevent collapse of
soil,
7. Continue to excavate not more than the ring mould depth of soil each time
and subsequent concrete lining is again formed with the steel mould by
lowering down from the upper ring.
9. Continue excavation and concreting of lining until after reaching the designed
bottom level of caisson or socketing into the bedrock formation as required by
Engineer.
Sheetpile Cofferdam
a) Steel H-Beam (minimum) is placed on ground at the four side of the pit
forming a rectangular shape wailer:
b) Sheet pile FSP3A is drive at the perimeter of the wailer beam by means of
vibro-hammer or excavator up to the required depth-using 6m sheet pile.
c) The soil within the pit is then excavated to the designed depth.
f) Upon reaching the formation level, the base is then clean and concrete using
mass concrete to form a working platform at base.
g) pit.
5. Seal gap between pipe to hacking drain wall with concrete G20
7. Premix