SN Description Mark-up SAR SAR 1 Total Manpower 26,760.00 15% 30,774.00 2 Equipment List 6,282.00 15% 7,224.30 3 Consumables and Safety 3,608.00 15% 4,149.20 4 Project Related Material 400.00 15% 460.00 5 Main Materials 0.00 15% 0.00 6 Foreign Services 0.00 0% 0.00
Total 37,050.00 42,608.00
SN Contingency/Risk % Cost in SAR Cost in USD
1 Total Manpower 5.00% 1,338.00 356.80
2 Equipment List 5.00% 314.10 83.76 3 Consumables & Safety 5.00% 180.40 48.11 4 Project Related Material 5.00% 20.00 5.33 5 Main Materials 5.00% 0.00 0.00 6 Foreign Services 5.00% 0.00 0.00
Total Contingency/Risk 1,852.50 494.00
SN Interest/ Finance % Cost in SAR Cost in USD
1 Total Manpower 0.00% 0.00 0.00
2 Equipment List 0.00% 0.00 0.00 3 Consumables & Safety 0.00% 0.00 0.00 4 Project Related Material 0.00% 0.00 0.00 5 Main Materials 0.00% 0.00 0.00 6 Foreign Services 0.00% 0.00 0.00