You are on page 1of 8

Safety

Bulletin
U.S. Chemical Safety and Hazard Investigation Board

MANAGEMENT OF CHANGE No. 2001-04-SB | August 2001

interrupted process operations and


Introduction also stopped the production of
steam. At the delayed coking unit,

T he U.S. Chemical Safety and Hazard Investigation Board (CSB) issues


this Safety Bulletin to focus attention on the need for systematically
managing the safety effects of process changes in the chemical industry.
the on-line drum had been filling
for about an hour and was
approximately 7 percent full. The
This bulletin discusses two incidents that occurred in the United States in other drum was full and was being
1998. Each case history offers valuable insights into the importance of cooled.
having a systematic method for the management of change (MOC). An
MOC methodology should be applied to operational deviations and Although electric power was
variances, as well as to preplanned changes—such as those involving restored after 2 hours, an
technology, processes, and equipment. additional 10 hours passed before
steam production was re-
established. During the interim,
the tarry oil in the piping between
Case No. 1 though the operation is conducted
continuously.
the furnace and the partially filled
drum cooled and started to
After a drum is filled, the flow of solidify.
Background oil is diverted to a freshly emptied
Once steam was restored, the
On November 25, 1998, a fire at the vessel. The full drum contains a
operators were unsuccessful in
Equilon Enterprises oil refinery tarry mass, which solidifies to a
attempting to inject it into the drum
delayed coking unit in Anacortes, coal-like substance (coke) when
through the normal route because
Washington, caused six fatalities cooled by the addition
(Figure 1). A loss of electric power of steam and then water.
and steam supply approximately The top and bottom of
37 hours prior to the fire had the drum are opened at l Figure 1. Equilon Enterprises oil refinery fire.
resulted in abnormal process the completion of the
conditions. cooling cycle, and the
solid mass of coke is
Process Description then cut into pieces and
removed from the vessel.
A delayed coker converts heavy
tar-like oil to lighter petroleum Incident
products, such as gasoline and fuel
Description
oil. Petroleum coke is a byproduct
of the process. Drums 1 of coke are Pre-Incident Activity—
actually produced in batches, A severe storm on
November 24 caused an
1
electric power outage in
Within the oil industry, a drum is a
the refinery. The storm
tower or vessel in which materials are
processed, heated, or stored. Coke
drums can be very large and typically
stand several stories high.
2

of the plugged piping. (When filled drums. The process established, but the rate of flow
normally injected, steam creates supervisor was aware of the was low.
passages in the tarry mass through seriousness of the previous
Opening the Vessel—Personnel
which cooling water can later flow. incident. He left instructions
expected a tarry mass to drain from
It also drives off remaining residual directing the night shift not to add
the drum. The supervisor and
volatile petroleum and sulfur any water, and instead to allow the
process operator directed that the
compounds from the coke.) drum and its contents to simply
drum be opened with a minimum
stand and cool overnight. On the
A process interruption in 1996 had number of people present. Because
following morning, he met with the
also resulted in a partially filled they were also concerned that the
operators to determine how to
drum. At that time, water was limited flow of steam might not
empty the partially filled drum. No
injected into the drum to cool the sufficiently strip all the toxic
engineers, who could have
material inside. However, when compounds from the tar inside the
provided technical support, were
the drum was opened, a torrent of vessel, they required that the
present at this meeting.
water, heavy oil, and coke spewed workers removing the bolts on the
out—which created a hazard and Preliminary Operations—The drum heads wear self-contained
required a major cleanup. An supervisor and operators observed breathing apparatus.
internal investigation team that the exposed part of the bottom
The top head was unbolted and
recommended that procedures be flange of the drum felt cool to the
lifted from the drum. The bottom
written for cooling/emptying touch. They also noted that
head was also unbolted and held
partially filled drums. However, temperature-sensing devices
in place by a hydraulic dolly. The
this task was not completed. located beneath the insulation on
operator then activated a release
the outside surface of the drum
On the day of the fire, neither the mechanism to lower the dolly.
indicated approximately 230
process supervisor nor the Witnesses reported hearing a
degrees Fahrenheit (°F), as
operators had any written whooshing sound and seeing a
compared to the 800°F of a
procedures for handling partially white cloud of vapor emanate from
typically full drum.
the bottom of the drum. The hot
One operator suggested adding 100 petroleum vapor burst into flames.
barrels of water to the drum. The process supervisor, an
CSB Safety Bulletins offer advisory However, the supervisor was operator, and the four contract
information on good practices for concerned about such a course of personnel assisting were caught in
managing chemical process hazards. action because of the previous the fire and did not survive
Actual CSB case histories provide
supporting information. Safety incident. Upon further discussion, (Figure 2).
Bulletins differ from CSB they decided—because part of the
After the incident, Equilon
Investigation Reports in that they do drum felt cool, and the
not comprehensively review all the relocated the controls for the
temperature-sensing devices read
causes of an incident. hydraulic dolly to allow workers to
only 230ºF—that it was not very
position themselves farther from a
hot inside and it was safe to open
drum when opening it.
the vessel as long as they first
injected some steam. Followup Analysis—The supervisor
U.S. Chemical Safety and Hazard and operators analyzed the
Investigation Board An operator connected a steam
situation and devised process
Office of Investigations and Safety hose to the oil inlet piping at the
Programs changes to empty the drum. The
bottom of the drum. Several
2175 K Street NW, Suite 400 relative coolness of the bottom
witnesses said that the steam
Washington, DC 20037 flange erroneously suggested to
202-261-7600 warmed the top of the piping, but
them that the temperature inside
http://www.chemsafety.gov the bottom remained cool. It is
the drum was also cool—when, in
likely that steam flow had been
3

the low l . . . the Equilon incident


l Figure 2. Fire control efforts at Equilon refinery. temperature
readings were
underscores the need to
Matt Wallis, Skagit Valley Herald
not have MOC policies that
representative of include abnormal
the hot core.
situations, changes to
It was assumed
that the entire
procedures, and
drum contents deviations from standard
had cooled to operating conditions.
safe levels during
the 2 days since
the power failure.
to trigger further review. It is
However, heat
essential to prepare operating
transfer
procedures with well-defined
calculations
limits for process variables for all
would have
common tasks. Once onsite
indicated that
personnel are trained on MOC
weeks would be
policy and are knowledgeable
required for the
about normal limits for process
l The relative coolness of drum contents to cool sufficiently
variables, they can make informed
via heat losses to the ambient
the bottom flange environment.
judgments regarding when to
apply the MOC system.
erroneously suggested
. . . that the temperature Lessons Learned Once a deviation is identified that
triggers the MOC system, it is
inside the drum was also Chemical processing enterprises
management’s responsibility to
should establish policies to
cool—when, in fact, only gather the right people and
manage deviations from normal resources to review the situation.
the material adjacent to operations. Systematic methods
The skills of a multidisciplinary
the inside walls had for managing change are
team may be required to
sometimes applied to physical
cooled. alterations, such as those that
thoroughly identify potential
hazards, develop protective
occur when an interlock is
measures, and propose a course of
bypassed, new equipment is action.
fact, only the material adjacent to
added, or a replacement is “not in
the inside walls had cooled.
kind.” However, the Equilon The Equilon incident could have
Unknown to the coker unit incident underscores the need to been avoided if the “change” was
personnel present, the core of the have MOC policies that include managed by a team experienced in
mass remained insulated from heat abnormal situations, changes to hands-on operations, safety
loss. Within the core, residual heat procedures, and deviations from procedures, and engineering
continued to break down the standard operating conditions. calculations. Written procedures
petroleum, creating a pocket of hot for cooling and emptying partially
For an MOC system to function
pressurized volatile oil. Had the filled drums, as recommended by
effectively, field personnel need to
limitations of temperature- sensing an Equilon investigation team in
know how to recognize which 1996, might also have reduced the
devices been better understood,
deviations are significant enough
personnel may have realized that likelihood of this incident.
4

l The Equilon incident duration of the variance.


Case No. 2
Variances should require the
could have been avoided approval by a suitable level of
if the “change” was management, based on the Background
process risks involved. Also,
managed by a team they should be documented to On October 13, 1998, a reaction
experienced in hands-on assure consistent vessel explosion and fire at the
understanding by all affected
operations, safety individuals and departments
CONDEA Vista Company
detergent alkylate plant in
procedures, and of what specific departure Baltimore, Maryland, injured four
from normal practice is to be
engineering calculations. allowed.
people (Figure 3).

A formal hazard analysis may be Process Description


The Center for Chemical Process appropriate depending on the
Linear alkyl benzene is used to
Safety, an industry-sponsored
produce biodegradable detergents,
organization affiliated with the
American Institute of Chemical
l “To assure that . . . which are widely used in
industrial, commercial, and
Engineers, offers this useful deviations from normal residential cleaners. At CONDEA
guidance in its publication, practice do not create Vista, this chemical was
Guidelines for Technical Management
of Chemical Process Safety (1989): unacceptable risks, it is manufactured by mixing powdered
aluminum chloride (the catalyst)
In any operation, situations will important to have a with liquid hydrocarbons,
arise that were not foreseen variance procedure, or chlorinated hydrocarbons, and
when the operating procedures benzene.
were developed. At such times, to have incorporated
personnel may want to conduct the same means of Incident Description
operations in a way that differs
from, or contradicts, the process control into other Pre-Incident Activity—About 3
technology or the standard management systems.” months prior to the incident, the
operating procedures. Baltimore facility changed its
To assure that these deviations process technology and
from normal practice do not complexity of the change or discontinued the direct addition of
create unacceptable risks, it is variance. A hazard analysis for aluminum chloride to the reactor.
important to have a variance the Equilon situation would have Instead, powdered aluminum was
procedure, or to have likely determined the limitations added to the reactor, where it
incorporated the same means of the temperature readings and combined with hydrogen chloride
of control into other that it was unsafe to open the to form the necessary aluminum
management systems. The
drum. It would have also chloride. Shortly after the plant
variance procedure will
identified the possible release of a switched to the new process, the
require review of the planned
deviation, and acceptance of large volume of very hot liquid as reactor became fouled with a
the risks it poses. The a significant risk. sludge-like catalyst residue.
variance procedure should When the process was shut down
require the explanation of the
for maintenance, the operators were
deviation planned; the reasons
unable to empty the liquid that
it is necessary; the safety,
remained in the reactor. Sludge
health, and environmental
considerations; control had settled in the vessel, plugging
measures to be taken; and the bottom outlet nozzle.
5

sample was tested, recorded a 5 to 10 degree Celsius


l Figure 3. Site of ruptured reactor, CONDEA Vista it reacted with (°C) temperature rise. After
Company detergent alkylate plant. water, yielding a observing the reactor temperature
white gas stabilize, the chemist and the
(hydrochloric engineer went home for the night.
acid) and
Because the process supervisor had
generating heat.
not been in the plant that day, the
Although the
shift supervisor spoke to him by
chemist tested
telephone and suggested injecting
various aqueous
a short burst of steam at the bottom
solutions, he
nozzle of the reactor. The process
concluded that
supervisor agreed. The shift
water—in spite of
supervisor wrote a one-line
its reactivity with
instruction for the night shift to use
the sludge—was
steam to clear the plugging.
an appropriate
solvent for The two shift supervisors had a
clearing the brief conversation at shift turnover.
sludge from the The night shift supervisor
reactor. understood that he was to use
steam to break up the plug.
Unsuccessful attempts were made Later that morning, the technology
However, the procedure intended
to clear the nozzle by injecting manager assigned an engineer to
by the day shift supervisor and the
high-pressure nitrogen into the work with the chemist in solving
process supervisor—though not
piping. The reactor was also the plugging problem. The
detailed—was to inject a short
flushed with a high flow of oil for engineer estimated the volume of
burst of steam, not to apply it
several hours, but this too failed to solid in the reactor and performed
continuously.
clear the plugging. some calculations for potential
energy release and for the ability of The night shift supervisor
The following day, excess liquid
water to absorb the heat generated. instructed an operator to add steam
was removed from the reactor
Together, the chemist and the to the reactor. Minutes after the
through a side nozzle, and a
engineer recommended that water operator started to continuously
sample of the remaining sludge
be added to the reactor to dissolve inject the steam, it reacted with the
was extracted. The next morning,
the solids. They suggested an 8:1 metallic aluminum and the
the sample was given to a plant
ratio, with the water added at as aluminum chloride residue in the
chemist, who was asked for advice
fast a rate as possible. This sludge. The reactor vessel
on dissolving the remaining
approach was based on the idea exploded (Figure 4).
sludge.
that rapidly adding a surplus
Effects of Explosion and Fire—No
Reactivity Testing—The chemist volume of water would absorb the
one was present in the immediate
first conducted a laboratory energy released by the reaction and
vicinity of the reactor when it
experiment to check whether fresh minimize the temperature rise.
exploded, and there were no
powdered aluminum catalyst
Addition of Water and Steam to fatalities. Two employees and one
reacted with water. He concluded
Reactor—Water was added to the contractor received first- and
that it did not. (Facility personnel
reactor while the vessel agitator second-degree burns; they were
were aware that aluminum
was running. A temperature wearing fire-resistant work
chloride reacts with water,
indicator in the control room clothing, which provided a
releasing heat.) When the sludge
measure of protection. Another
6

contractor injured his back when


he fell. Property damage was l Figure 4. CONDEA Vista plant fire.
estimated at $13 million.
WBAL-TV

Lessons Learned
From both a project and an
operational standpoint, the
incident at CONDEA Vista
emphasizes the importance of
systematically managing changes.
Post-incident investigations noted
that the density of the new catalyst
(powdered aluminum) was higher
than that of aluminum chloride.
The higher density material—
combined with problems related to
initial overfeeding of the
aluminum—overtaxed the mixing
capability of the agitator and
allowed aluminum to settle in the
bottom of the reactor, where it
plugged the lower nozzle and
have to be added quickly and
accumulated as sludge. l The higher density without interruption to avoid a
The plan devised by the chemist material—combined with significant heat release.
and the engineer for dissolving the problems related to l The temperature-sensing device
sludge posed hazards. Of
particular concern were the
initial overfeeding of the did not accurately indicate the
process temperature because it
following: aluminum—overtaxed was located in a stagnant
l Gases 2 that evolved during the the mixing capability of pipeline between the reactor and
bench-scale tests could vent the agitator and allowed another vessel. The chemist and
freely. However, the reactor— the engineer relied on misleading
though equipped with vent aluminum to settle in the temperature indications when
piping and a relief system— bottom of the reactor, they noted the stabilization of the
presented a much more reactor temperature before
where it plugged the leaving for the day.
contained environment. The
amount of reactive material lower nozzle and
A hazard analysis of the proposed
involved was much greater; the accumulated as sludge. procedure could have assisted in
scale-up factor was large.
the identification of potential safety
l The concept of absorbing the issues. Ideally, the extent of
quickly adding a surplus of a
energy of reaction by means of analysis undertaken should be
reactive substance (water) was
tailored to the degree of risk.
2 potentially hazardous.
At higher temperatures, water can react The CONDEA Vista incident also
with aluminum to form hydrogen. Water Although the concept was
can also react with aluminum chloride to feasible, it required precise highlights the importance of
produce hydrogen chloride, which—in execution. The water would preparing written procedures for
turn—can react with aluminum to
produce hydrogen.
7

variances in operating conditions


and practices. In this case, the
Summary covers operational variances in
addition to physical alterations. If
absence of written instructions you do not have a systematic
Neither the Equilon Enterprises oil
increased the likelihood of method for handling changes,
refinery fire nor the CONDEA
miscommunication between the develop and implement one.
Vista Company explosion and fire
two shift supervisors, which led to
involved emergencies that required
the unsafe application of steam in
rapid decision making. In each
the reactor vessel. l If your organization has
instance, time was available to
look into the circumstances more an MOC policy, review it
l . . . the absence of thoroughly. Each situation could to be sure that it covers
written instructions have been avoided with a more
operational variances in
increased the likelihood analytical and structured
approach to problem solving. addition to physical
of miscommunication
alterations.
between the two shift
l Neither the Equilon
supervisors, which led to
the unsafe application of Enterprises oil refinery To maximize the effectiveness of
your MOC system, include the
steam in the reactor fire nor the CONDEA following activities:

vessel. Vista Company l Define safe limits for process


explosion and fire conditions, variables, and
involved emergencies activities—and train personnel
Another lesson learned is the value to recognize significant changes.
of having an authorization or that required rapid Combined with knowledge of
approval step as part of an MOC decision making . . . Each established operating
system for abnormal situations. If procedures, this additional
such a procedure had been in
situation could have been training will enable personnel to
place, a technical manager would avoided with a more activate the MOC system when
have reviewed the proposed analytical and structured appropriate.
procedure and may have detected
its deficiencies. approach to problem l Apply multidisciplinary and
specialized expertise when
solving. analyzing deviations.
l Use appropriate hazard analysis
The Occupational Safety and techniques.
Health Administration’s (OSHA)
l Authorize changes at a level
Process Safety Management
commensurate with risks and
standard and the U.S. Environ-
hazards.
mental Protection Agency’s (EPA)
Risk Management Plan require l Communicate the essential
covered facilities to manage elements of new operating
changes systematically. It is good procedures in writing.
practice to do so, irrespective of the
l Communicate potential hazards
specific regulatory requirements. and safe operating limits in
If your organization has an MOC writing.
policy, review it to be sure that it
8

l Define safe limits to For Further Reading


process conditions,
Center for Chemical Process Safety (CCPS), 1992. Guidelines for Hazard
variables, and activities— nd
Evaluation Procedures, 2 Edition With Worked Examples, American
and train personnel to Institute of Chemical Engineers (AIChE).
recognize significant CCPS, 1989. Guidelines for Technical Management of Chemical Process
changes. Safety, AIChE.

Sanders, Roy E., 1999. Chemical Process Safety – Learning From Case
Histories, Butterworth-Heinemann, pp. 215-247.
l Provide training in new
procedures commensurate with
their complexity.
l Conduct periodic audits to
determine if the program is
effective.

The U.S. Chemical Safety and Hazard Investigation Board (CSB) is an independent Federal agency whose mission is
to ensure the safety of workers and the public by preventing or minimizing the effects of chemical incidents. CSB is a
scientific investigative organization; it is not an enforcement or regulatory body. Established by the Clean Air Act
Amendments of 1990, CSB is responsible for determining the root and contributing causes of accidents, issuing safety
recommendations, studying chemical safety issues, and evaluating the effectiveness of other government agencies
involved in chemical safety. No part of the conclusions, findings, or recommendations of CSB relating to any
chemical incident may be admitted as evidence or used in any action or suit for damages arising out of any matter
mentioned in an investigation report (see 42 U.S.C. § 7412(r)(6)(G)). CSB makes public its actions and decisions
through investigation reports, summary reports, safety bulletins, incident briefs, safety recommendations, special
technical publications, and statistical reviews. More information about CSB may be found on the World Wide Web at
http://www.chemsafety.gov.

Information about available publications may be obtained CSB investigation reports may be purchased from:
by contacting:
National Technical Information Service
U.S. Chemical Safety and Hazard Investigation Board 5285 Port Royal Road
Office of Congressional and Public Affairs Springfield, VA 22161
2175 K Street NW, Suite 400 (800) 553-NTIS OR (703) 487-4600
Washington, DC 20037 Email: info@ntis.fedworld.gov
(202) 261-7600 For international orders, see:
http://www.ntis.gov/support/cooperat.htm.

Salus Populi Est Lex Suprema


People’s Safety is the Highest Law

You might also like