1 Introduction
GPG-Indo, PD, GPG-China, Ningbo Group Leaders
Page 1 of 2
c) Dismantling GPG-China, Ningbo
1) Identification of Contractors
2) No. of contractors
3) Permits
4) Scope of work
5) Container laydown area at the Ningbo mill during
dismantling and refurbishment
d) Refurbishment (of Main Equipment) GPG-China, Indo
1) Machine roll grinding and balancing; On-machine
and Off-machine possibilities
2) Vendors for Refurbishments and Locations
3) Vendor capabilities (tools and equipment,
containers, packing and shipping etc)
4) New name plate
a) Assessment of auxiliary items GPG-China, Indo, PD
1) Included in Main Eq Vendor package (option)
2) Ningbo record
3) Condition monitoring and marking of items
4) Cleaning, Painting, packing and shipping
e) Contract and other procurement process GPG-Indo, China
1) Roles and Responsibilities
2) Schedule
f) Shipping GPG-China, Indo
1) Roles and Responsibilities
2) Customs inspection next year (before dismantling)
3) Containers (required for storage at PD4)
g) MMS and Existing Inventory list (incl all spares) Ningbo
1) Available spares
2) Suppliers list
3) MMS information
4) Manuals
5) Recent change record
h) Unshipped equipment and Waste disposal GPG-China, Ningbo
i) Responsibility matrix discussion and agreement GPG-Indo
Page 2 of 2