Kokoh will submitted RFI for hydotest Tank D-337 on 19 and 20 Jan 2021, after

enlosed punchlist refer to IR number MTS0-00046-IR05

Jo Eng confirm will disucussed internally related justification action for


deviation of dimension tank D-065-05 and requested Kokoh to provide all summarize
dimensional report include drawing markup

Kokoh shall submit drawing modification to JO for deviation of slope/internal


piping N-3

Water certificate for hydrotest in process review by JO

Hydrotest Tank D-337 can be conducted if all requirement/Oou standing document are
finished, (ex : NDE clearence, Dimensional report etc)