Surface Treatment in Thermal Turbomachines

Customized Coating Solutions


Prolong Service Life

PETER VAN NEERVEN Turbomachines need to operate at very high


GARY LOGAN temperatures and sometimes with corrosive
MATT LAU and abrasive fluids. There are no materials
SULZER TURBO SERVICES available which can withstand the
temperatures in the hot section of a modern
gas turbine and still provide sufficient strength
and lifetime. Complex cooling designs and
thermal-barrier coatings can reduce the actual
metal temperature to a level at which modern
superalloys are strong enough. Other coatings
in turbomachines protect surfaces from
oxidation, corrosion, and erosion or reduce
seal or tip clearance. When refurbishing
rotating equipment, Sulzer Turbo Services
applies adapted coating solutions depending
on fuel and operation mode.

16 SULZER TECHNICAL REVIEW 4/2007 4223


16-19_west_ed.qxd 1.11.2007 12:10 Uhr Seite 2

In a turbomachine, tempera- ing to a deterioration of material


Substrate Bond Top Combustion
ture and velocity as well as properties. Two different modes of coat coat gas
Turbine
the moisture content of the fluid corrosion can be distinguished. operating temperature

Temperature
vary both along the flow path Hot corrosion (type 1 corrosion)
through the machine and depend- takes place at temperatures be- Substrate
melting temperature
ing on the operating conditions. tween 800 and 900 °C. It attacks
Consequently, the material is sub- the entire surface and develops
ject to a range of wear mecha- along the grain boundaries.
Distance
nisms, including corrosion, oxida- Type 2 corrosion mostly forms
tion, and erosion. Heat can alter local spots with heavy attack 2 Schematic coating structure and temperature gradient
the structure of the blade material and builds distinct layers of ox- (blue line) of a thermal-barrier coating as a function of
distance.
(thermal fatigue) and deteriorate ide and metal
its mechanical properties, e. g., Erosion as defined in materials sci-
strength. Different types of coating ence is the damaging of surfaces
protect the equipment from the by repetitive, localized mechanical or low-pressure plasma spraying
various types of attack (Fig. 1). attack, e.g., by abrasive particles. (LPPS).
The purpose of a thermal-barrier
Oxidation, Corrosion, and Protection from coating (TBC) is to enhance the
Erosion Resistance High Temperatures longevity of coated parts by reduc-
During oxidation, metal forms a In modern turbines, mostly a com- ing metal temperatures. In addi-
metal-oxide layer on the surface. bination of techniques is used to tion, these ceramic coatings are
In general, this oxide layer protects create the optimal protection from used for clearance-control applica-
the underlying material. Therefore different types of attack. tions in the high-temperature
the oxidation process will slow Oxidation and corrosion resistant regime.
down as the thickness of the oxide coatings are usually aluminides, TBC based on zirconia are pro-
layer increases. The intentional produced by chemical vapor dep- duced normally by thermal-spray
formation of oxides can provide a osition (CVD) processes as well as techniques or electron-beam phys-
protective layer preventing further coatings produced by thermal- ical vapor deposition. The thermal
atmospheric attack. spray processes or combined tech- conductivity of zirconia used in a
Corrosion is a combined surface niques, e.g, MCrAlY applied by TBC is low, about 1 W/m·K; that
attack of oxygen and sulfur lead- high-velocity oxygen-fuel (HVOF) of, e. g., copper is 3000 times

1 Coatings increase efficiency and extend the service life of modern gas turbines. When repairing a gas turbine, Sulzer
Turbo Services engineers chose tailor-made coating solutions. The right selection can help improve performance.

Main turbine parts Applied coatings


a Air intake 1 Babbitt coatings 5 Shroud blocks:
high-temperature abradables
b Compressor 2 Compressor coatings
6 Buckets and nozzles:
c Burner, combustion liner, 3 Burner and combustion liner: hard facing oxidation coatings, TBC, tip sealing
transition piece (combustion vibrations) and TBC
7 Labyrinth seals: abradables
d Turbine cooling air 4 Transition piece: hard facing and TBC
e Exhaust
f Bearings 5 6
3
g Turbine section
c
4
a e
2

b 7 1
g
f
1
f

SULZER TECHNICAL REVIEW 4/2007 17


16-19_west_ed.qxd 1.11.2007 12:10 Uhr Seite 3

greater. Sulzer Turbo Services ap- Modern Coating Technology Environment-Friendly Process
plies a 2-layer coating system The basic production techniques Applications include protection
(Fig. 2). It consists of a bond coat for coatings are thermal spraying from wear, high temperatures, or
and a top coat. The bond coat pro- and physical and chemical vapor chemical attack, as well as envi-
vides good adhesion between the deposition (PVD and CVD). ronment-friendly use for corrosion
metal substrate and the ceramic Thermal spraying is an industrial protection as a substitution for
top coat. It acts as a heat shield, in- coating process consisting of a heat hard chromium. Coatings can be
sulating the substrate alloy and source and a material. The process metallic, ceramic, or any combina-
therefore allowing higher operat- involves heating a material, in tion desired to meet a broad range
ing temperatures or reductions in powder or wire form, to a molten of physical criteria.
cooling requirements or both. or semi-molten state. The material Diffusion coating is a process in
Erosion resistant coatings are is propelled using a stream of gas which a base metal or alloy com-
made from hard carbides and are or compressed air towards the ma- ponent is either coated with anoth-
mainly produced by thermal- terial to be coated, or substrate, er metal or alloy and is heated to a
spray processes. creating a new surface structure as process specific temperature with-
it impacts. The coating materials in a closed environment. The coat-
Clearance Control can be melted using several differ- ing is then diffused into the sur-
Besides their thermal-barrier prop- ent processes, including fuel com- face of the component by exposure
erties, zirconia-ceramic materials bustion, plasma spray, and elec- to a gaseous medium. Diffusion
are also used for clearance-control tric-arc delivery systems. The coatings provide superior oxida-
applications in the high-tempera- process can take place under stan- tion, corrosion and erosion resist-
ture regime. Tighter clearance con- dard atmospheric conditions or in ance for applications as internal
trol leads to improved efficiency of a special, highly controlled atmos- cavities and are widely used as
the turbine. Clearance-control phere. standard oxidation protection for
coatings, or abradable coatings, The speed of the molten material external surfaces.
function by permitting a rotating and the atmosphere under which
part (such as a blade) to cut a path the process is carried out influence Case Study 1:
in a sealing abradable layer with the properties, e. g., density or Operating Costs Reduced
minimum clearance (Fig. 3). Many hardness, of the coating. Sulzer The need for smooth, corrosion re-
advanced gas turbines utilize a Turbo Services applies LPPS, sistant coatings for gas turbine
thick ceramic coating to impart atmospheric plasma spraying compressor blades was recognized
both thermal-barrier and abrad- (APS), or HVOF spraying depend- some time ago. Although the base
ability properties. ing on the requirements. alloys have good corrosion resist-
ance and a smooth surface finish
when first installed, these proper-
3 Inner shroud of a gas turbine freshly coated with an abradable coating (left). The
ties can deteriorate quickly once in
picture after 18 000 operating hours shows the abradibility of the coating system.
service. Sulzer Turbo Services has
developed various compressor
coatings. The crack-gas compres-
sors in the ethylene unit of a glob-
al chemical company required
regular shutdown and cleaning.
Sulzer Turbo Services applied anti-
fouling coatings to the compressor
rotors and diaphragms, complete-
Stage 1 Stage 1
shroud tile shroud tile ly eliminating the need for off-line
with product with rub washing, providing an annual sav-
build up from stage
1 bucket ing of over USD 1 million to the
client. This cost reduction is due to

18 SULZER TECHNICAL REVIEW 4/2007


16-19_west_ed.qxd 1.11.2007 12:10 Uhr Seite 4

improved availability and the fact blades, they were considered for
that no more washing fluid is nec- replacement. However, due to
essary. The customer chose Sulzer budget and time constraints, the
Turbo Services exclusively, be- customer wanted to reuse the
cause the company could guaran- blades applying the quickest pos-
tee quick response time during the sible repair option. Sulzer Turbo
tightly scheduled outage. Services restored the blades by
dressing the erosion area and ap-
Case Studies 2 and 3: plying chrome-carbide coating us-
Service Life Extended ing the HVOF method (Fig. 5). The
For the gas turbines of one cus- journal bearings were also refur-
tomer, Sulzer Turbo Services coats bished by HVOF coating. The coat- 5 Manual coating of steam-turbine blades.
the transition pieces exclusively, ing process was applied to both
because the client can now reuse journals first and the blades of the The newest generation of turbine
them without any need for repair last 2 stages afterwards. After com- parts is challenging for repair com-
after running an operating cycle of pleting, the rotor was shipped panies, this is because of the many
8000–12 000 hours (Fig. 4). Before, back to the customer for installa- small cooling holes (very often
other vendors had coated the tion and immediate return to op- more than 500 in a single part!).
parts, and after one cycle, the tran- eration. The repair requires new coating
sition pieces had to be taken from solutions since conventional plas-
the turbine, the coating that was Adapted Coatings ma-spaying processes would close
left had to be completely removed Sulzer Turbo Services offers a vari- up many of small holes when
and the transition pieces had to ety of coatings to extend the life of spraying. Sulzer Turbo Services
undergo weld repair before being critical turbomachinery, adapted to and Sulzer Metco put a lot of much
recoated. the specifics of the respective ma- effort into new techniques for im-
In 2005, Sulzer Turbo Services re- chine and its operation modes. proved coatings but also in im-
ceived one unit of a 25-MW steam These coatings are designed to proved coating application tech-
turbine from an Indonesian com- keep machinery running longer niques to keep the holes open dur-
pany. The last-stage blades of the and in many cases more efficiently. ing spraying.
turbine had suffered from severe In advanced gas turbines, which The combination of the broad ex-
erosion on the leading edges. operate at temperatures higher perience of Sulzer Turbo Services
Sleeve rubbing on both journal than the melting points of the in refurbishing turbomachinery
bearings was also found. Observ- newest alloys, the cooling and and the coating expertise of Sulzer
ing the damage on the last stage coatings determine the lifetime. Metco makes sure that the clients’
processes are back online as fast as
4 Coating the inner diameter of these transition ducts increased
possible after a shutdown.
their service life and reduced the need for weld repair.

Contact
Sulzer Hickham Inc. Sulzer Elbar B.V.
Gary Logan Peter van Neerven
11518 Old La Porte Road Spikweien 36
La Porte, TX 77571 5943 AD Lomm
USA The Netherlands
Phone +1 713 567 28 97 Phone +31 77 473 8659
Fax +1 713 567 28 31 Fax +31 77 473 2785
gary.logan@sulzer.com peter.vanneerven@sulzer.com

SULZER TECHNICAL REVIEW 4/2007 19

You might also like