Professional Documents
Culture Documents
Railway Lines
The development of high-speed railway lines starts in The electrical supply system of a high-speed railway line
France at the beginning of the 80’s when the line Paris – provides electric power of the desired characteristics (AC,
Lyon was opened [1] (the first section Lyon – St. Florentin single phase, 25 kV) to the trains from the high-voltage
was opened in 1981 and the full line Paris - Lyon was opened network. The main components of the system are the
in 1983). The French developments have been followed by catenary and the substations that feed the catenary from the
other ones in Germany, Italy and Belgium. high-voltage network. Fig. 1 displays a typical configuration
of the system. Each transformer is connected to two phases of
The first Spanish railway line (Madrid – Seville) was the three-phase system. Each section of the line is
opened in 1992. It is approximately 450 km long, the nonstop independently fed by a traction substation. In case that a
trip takes 2:30 hours and the trains travel at a maximum substation is out of service, the adjacent substations
speed of 300 km/h. The technical and economic success of respectively feed the two parts of the corresponding section.
that line has encouraged the Spanish government to start new
High-Voltage Network
projects: Madrid – Barcelona – French border (800 km),
Madrid – Valencia (350 km) and Madrid – Valladolid (200
km). These projects are also supported by the European
Traction Traction Traction
Union under the framework of the Common Transportation substation 1 substation 2 substation 3
C. Solution procedure
High-Voltage network
Fig. 2. Topology of the 1x25kV system.
The problem of designing the electrical supply system of a
Positive phase high-speed railway line is solved iteratively (see Fig. 4). The
starting point consists of determining the electrical
Train consumption scenarios from traffic simulations. Then, values
are assigned to the design variables, the electrical simulations
are performed and the constraints evaluated. If the constraints
are not fulfilled, the user assigns new values to the design
variables. The tool has been designed in such a way that this
Negative phase process can be done easily.
Scenarios generator
Assign value to
High-Voltage network design variables
End
the design variables so the required technical constraints are
Fig. 4. Solving procedure.
fulfilled.
IV. OVERVIEW OF THE SIMULATION TOOL
A. Design variables
The simulation tool consists of computing modules and
The design variables define the configuration of the user-friendly interfaces to handle input and output data. The
system, the size of its components and impose constraints to main computing modules are the traffic simulator and the
external systems. Therefore, three groups of design variables electrical simulator [3].
are set up:
The traffic simulator builds the scenarios of electrical
1) Topological variables: variables which define the system (location and magnitude of the train loads) by
topology of circuits, that is (i) type of feeding system of each simulating the movement of each train. The electrical
sector, (ii) location of each traction substation and connecting simulator determines magnitudes of the high-speed power
bus to the high-voltage network, (iii) location of each switch system for each scenario. In addition to the computation of
and (iv) location of each autotransformer. voltages, currents and power flows, other studies can be
performed such as unbalance introduced in the high-voltage
2) Gauge variables: variables which set the size of every network, step and touch voltages, or induced voltages along
element of the system, such as (i) transformers and parallel lines. The two simulators are uncoupled [4]. In other
autotransformers ratings, (ii) number and type of physical words, the movement of the trains is not affected by the
conductors of the catenary, and (iii) specifications of each steady state of the electrical system (this is possible thanks to
grounding connection. the control capabilities of the power electronic converters of
the trains).
3) External variables: variables of the external systems that
V. TRAFFIC SIMULATOR starting station are the temporal and spatial origins. Once it
has been obtained, the departure timetable is used to compose
The traffic simulator determines, for every time step, the the movement of the trains’ sequence. This is done by
position and the active and reactive power consumption of reproducing the movements with different time and space
every train. This simulation is performed in two steps: firstly, origins as shown in Fig. 5.
the movement of every type of train between two consecutive Train type 1
Station 1 - Station 2
stations is calculated. Secondly, the entire traffic is built up
using the timetable that determines each train departure from
Position (in m)
each station.
Station 3
A. Movement of a train between consecutive stations Time (in s)
Station 2
Position (in m)
Train type 2
The movement of a train between two consecutive stations Station 1 - Station 3
Position (in m)
Station 1
Time (in s)
dv
Fi = Ft − F p − Fc − Fa = M (1)
i dt
Time (in s)
where M is the mass of the train, v is the speed of the train, Fig.5. Procedure to build up the line traffic.
Ft is the traction force of the train, F p is the resistant force
It should be noted that in the adopted model, trains do not
due to the slope of the railway line, Fc is the resistant force interact with other trains. In other words, the timetable must
due to the curvature of the railway line, Fa is the force that reflect overtakes, waiting states, and all necessary behaviors
models the aerodynamic resistance. The traction force is a to allow an efficient exploitation of the railway line.
piece-wise linear function of the speed. The resistance force
due to the slope of the line is proportional to the mass of the VI. ELECTRICAL SIMULATOR
train and the slope of the line. The resistance force due to the
curvature is also proportional to the mass of the train and The electrical simulator contains a set of tools to perform
inverse to the curvature radius. The aerodynamic resistance the studies required to evaluate a design of the electrical
force contains three terms: one constant, other proportional to supply system of a high-speed railway line. The main
the speed and the remaining one proportional to the square of computations are the train voltages, conductor currents and
the speed. transformer power flows. In addition, unbalance introduced
in the high-voltage network, induced voltages along parallel
The solution of equation (1) provides the position, speed lines, and step and touch voltages in the proximity of the
and acceleration of the train. The solution takes into account grounding connections can be determined. An utility to
the speed and acceleration constraints. Once, the movement compute the line parameters of the catenary has also been
of the train has been solved, the active power consumption is added due to the specific features of the catenary as a power
determined as: distribution line [5].
Pm F ⋅v A. Line parameters
Pe = = t (2)
η e, m η e, m
The configuration of the catenary of a high-speed railway
line is shown in Fig. 6. The catenary contains several
where η e,m is the efficiency of the electrical-to-mechanical physical conductors that can be grouped into three groups:
power conversion. positive, negative and ground wires.
Grounded wire positive feeder
The reactive power is determined from the train power Positive phase
negative feeder
Negative phase (in 2x25kV only)
sustainer wire
factor. The train power factor is modeled as a piece-wise
linear function of the speed. Regenerative braking can be return wire
S r = ( Pe + j ⋅ Qe ) ⋅η r (3)
rail
Ztr3 Ztr2
ë 11, g
2
er
er
rm
rm
sfo
sfo
ran
S1 (MVA) Traction
éY22, gg Y22, g ù éV2, g ù éI 2, g ù
tot
tot
substation
ú=ê
Au
Au
Y11, V1, = I1, − Y11, g V1, g (10) E. Induced voltages in parallel lines
Y22, V2, = I 2, (11) Catenary currents also induce voltages in long parallel
lines, like parallel catenaries of conventional railway lines.
The conditions that describe the phase-to-phase unbalance Induced voltages over admissible values can damage such
can be formulated according to equations (12) and (13). lines unless corrective measures are applied. The induced
voltages are computed using the equivalent conductor model
K V1, V1, + K V2 , V2, = Z I1, (12) of the catenary and representing the parallel line by sections
of uniform separation from the catenary (see Fig. 10).
I 2,c = K I ,c I1,c (13)
Vext = M ph − c ⋅ I ph ⋅Lsect (15)
sect ph
where Z , K V1, , K V2 , , y K I , are diagonal matrices. The
nonzero elements of K V1, , K V2 , , y K I , depend on which where M ph −c are the mutual induction coefficients between
phases the load is connected to. If the unbalance conditions the catenary equivalent conductors and the external parallel
and the sequence equations are combined, the solution of conductor, and I ph are the equivalent conductor currents and
linear system (14) provides the direct and the inverse
Lsect is the length of the section.
sequence voltages.
Positive phase
(14) Ineg
connections. The rail currents are very high due to the power Fig. 10. Model to determine induced voltages in a parallel line.
requirement of high-speed trains. Since a fraction of those VII. ILLUSTRATIVE EXAMPLE
currents flows through the grounding connections, non-
admissible voltages may appear near them [8]. The step and The tool will be illustrated with results of the studies of the
touch voltages analysis estimates those voltages to design the Madrid – Barcelona high-speed railway line (Madrid – Lleida
adequate safety measures. section). A traffic scenario corresponding to a Thursday of
March 2015, between 12:00:00 and 15:00:00 will be
The step and touch voltages analysis models the trains as considered. Two Alstom train models have been used. A
equivalent impedances (which are determined using the realistic configuration of the electrical supply system has also
voltage calculated by the load flow analysis and their been assumed.
consumption) and traction substations by their Norton
equivalent (see Fig. 9). Fig. 11 displays the minimum voltages along the catenary.
Positive phase It should be noted that such voltages are always over the
minimum requirement (19 kV).
It Ztrain
Grounding Grounding Grounding
impedance impedance impedance
Neutral
Zg I3 Zg I1 I2 Zg
IX. ACKNOWLEDGEMENT
[1] J. Dupuy, “France superfast train”. IEEE Spectrum, July, 1982, p. 38-43.
[2] R.J. Hill, I.H. Cevik, “On-line simulation of Voltage Regulation in
Autotransformer-Fed AC Electric Railroad Traction Networks”, IEEE
Transactions on Vehicular Technology, Vol 42, No3, Agust 1993
[3] G. Cosulich, T. Ghiara, “MOTORS: a flexible traffic simulator to
investigate tail and metrorail capability”, Computers in Railways, p. 381-390
Fig. 13. Autotransformer loads. [4] B. Melitt, et al., “Simulator for studying operational and power supply
conditions in rapid-transit railways”, Proceedings IEE, Vol 125, Nº4, April
Fig. 14 details the unbalance introduced in the current 1978
Spanish high-voltage network by the single-phase loads due
[5] J. Duncan, A. Kusko, S. M. Peeran, “Train Voltage Analysis for AC
to the section Madrid – Lleida of the Madrid – Barcelona
Railroad Electrification”, IEEE Transactions on Industry Applications, Vol
high-speed railway line. A number of buses exhibit IA-20, NO. 4, July/August 1984
unbalances higher than 2%. It indicates that the network
[6] H.W. Dommel, Electromagnetic Transients Program Reference Manual,
should be reinforced to reduce them. In fact, a program to Vancouver, 1986.
reinforce the Spanish transmission system has been planned
to reduce the unbalance to admissible values, and it will be [7] K.L. Lo, C. Zhang, “Decomposed three-phase power flow solution using
the sequence component frame”, IEE Proceedings-C, Vol 140, No 3, May
ready when the line opens. 1993
[8] S. D. Jacimovic, “Maximum Permissible Values of Step and Touch
Voltages with Special Consideration to Electrical Railroads”. IEEE
Transactions on Industry Applications, Vol. IA-20, No. 4, July/August 1984,
pp. 935-941.
XI. BIOGRAPHY
Fig. 14. Maximum unbalance introduced in the high-voltage network. Luis Rouco obtained his Electrical Engineer and Ph.D. degrees from
Universidad Politécnica de Madrid in 1985 and 1990. He is Associate
VIII. CONCLUSIONS Professor of the School of Engineering of Universidad Pontificia Comillas
and Research Staff of Instituto de Investigación Tecnológica. His areas of
interest are modeling, analysis, simulation and identification of electric
This paper has presented a tool to help in the design of the power systems.
electrical supply system of high-speed railway lines. The
main components of the simulation tool are the traffic Antonio Fernández Cardador obtained his Physics degree in 1991 from the
Universidad Complutense de Madrid. He received the Ph.D. degree from the
simulator and the electrical simulator. The tool has been Universidad Pontificia Comillas in 1997. He is Assistant Professor of the
extensively used by SEMI to design the electrical system of School of Engineering of Universidad Pontificia Comillas and Research
the Madrid – Lleida section of the line Madrid – Barcelona – Staff of Instituto de Investigación Tecnológica. His research interests include
French border. SEMI has been awarded by the Spanish design, management and control of railway systems.
government with the project and the construction works of Agustín Hernández Velilla obtained his Electrical Engineering degree from
the power supplying system of this high-speed line. ICAI (Universidad Pontificia Comillas) in 1965. He is the General Director
of SEMI.