Professional Documents
Culture Documents
YAHYA AKTAŞ, HAKAN OǦUZ, GÜRAY AKSU, DOǦUŞUZUN and MUAMMER SEVER
Tüpras¸ Izmir refinery
T
he basic principle of good absolute necessity and an temperatures. A reduction in
combustion is to fully expensive challenge for refiner- temperature leads to an
oxidise the carbon, hydro- ies to meet environmental improvement in efficiency. Due
gen and sulphur in the fuel, targets according to legal to instrument failures in some
leading to the formation of requirements. In Izmir refinery, furnaces, one can observe unre-
carbon dioxide, water and SOx. we are trying to decrease the alistic low stack temperatures,
Stoichiometric levels of oxygen production of greenhouse gases indicating cold air intake.
should normally be sufficient by making some operational Detecting cold air leaks is also
to complete combustion.1 changes and investments. very important in the operation
Improvement of furnace In order to reduce emissions of furnaces. Sources of leaks
operation is very important to of CO2, CH4 and O3, as well as include:
achieve efficient or continuous energy demand, we undertook • Heater header boxes
production, and safety issues the following tasks: • Peep holes
have always been the priority • Heat integration projects, for • Non-activated burners
for chief engineers in refineries. the significant reduction of • Explosion doors
Generally, for combustion in emissions and for further • Damper leaks
refinery heaters, there are two energy savings • Breakdown of air registers.
main parameters that affect the • Installation of new preheat In practice, excess air is
thermal efficiency of the entire exchangers before the heaters, necessary to achieve complete
combustion process: and online cleaning of heaters combustion. This excess air is
• Lowering the value of the • Optimise the operation of an expressed as a percentage of
oxygen content of the flue gas existing heater. the theoretical amount of air.2
• Lowering the value of the Any excess air, above its theo-
temperature of the flue gas. Detection and diagnostics retical value, causes a loss of
The thermal efficiency of Combustion engineering is an energy in furnaces.
furnaces can be improved by intellectually challenging field Stack gas temperatures are
increasing heat recovery from with plenty of opportunities to usually higher than target
the flue gases. Usually, a 20°C enhance fundamental and prac- temperatures. Excess stack gas
reduction in stack flue gas tical knowledge that will temperatures also lead to heat
temperature corresponds to a ultimately lead to the develop- loss, thus decreasing the effi-
1% gain in efficiency. In addi- ment of new products with ciency of the furnace. One of
tion, a 1% reduction in the total improved performance.3 the most important actions to
oxygen level leads to a 0.5% Most refinery furnaces gener- decrease stack gas tempera-
improvement in efficiency. ally have a large potential for tures is to constantly keep tube
Reducing CO2 emissions is an the reduction of stack gas surfaces clean. This can be
the furnace duty increased by Refractory maintenance cantly lowers the combustion
approximately 20% through should be carried out at specific air outlet temperature at the air
enhanced heat recovery. periods (see Figures 1 and 2) so preheater and thus reduces the
The Combustion Engineering that appropriate action can be thermal efficiency of the
Group at Izmir refinery regu- taken very quickly to reduce furnace. The other negative
larly inspects the furnaces. This heat losses in furnaces. effect of a leakage in an air
group, together with the tech- preheater is that the air outlet
nical control department, has Practice of furnace operation temperature is lower than the
found heavy soot accumula- Furnaces are usually supplied design value, reducing the
tions in the convection bank along with information from furnace’s total efficiency.
and refractory area, indicating the manufacturer on the duty, However, if we only fire fuel
poor combustion leading to corrected log mean tempera- gas or natural gas in the heater,
reduced efficiency. ture difference, percentage soot blowing has no impact on
Some furnaces in the refinery vaporised, desired pressure increasing heat transfer and
have been operating with high drop and materials of heat recovery. Using soot
stack temperatures. We know construction.5 blowers leads to consumption
that these temperatures were Bad combustion through of steam and increases the
not in compliance with the shortage of air to individual amount of oxygen in the stack
manufacturer’s operating data. flames and bad atomisation gas.
This resulted in an inspection cause a non-symmetric flame While the heater is out of
of the convection bank. We (see Figure 3). Some furnaces service, there are some steps
found that some of the tubes in the refinery appear to have that need to be carried out, as
did not have fins, causing poor low stack temperatures. We follows, in terms of control
heat transfer and higher stack can explain this as a leakage in mechanisms. The burner firing
temperatures than the design the air preheaters, which pattern should be mirrored and
values. The simplest action was results in air mixing into the burners should be evenly
needed to resolve this: install hot flue gases. This signifi- spaced along the entire box.
new fin tubes. When the burners are
A furnace’s interior also out of service,
refractory walls have a they should be rotated
much greater surface regularly. The change
area than the surface in burner positions
area of the heat trans- helps to maintain the
fer tubes. Therefore, a integrity of the tubes.
proportionally greater Once per shift the
amount of energy is field operator should
delivered to the walk the furnaces and
furnace’s refractory carry out the follow-
surfaces.4 Figure 3 Non-symmetric burner: top view ing checks:
• Check flames to ensure they otherwise, unexpected hazards during startup and shutdown.
are orange and in stable could occur with severe conse- In order to protect equipment,
condition quences. All equipment operational procedures for
• Make sure combustion is related to shutdowns should be startup and shutdown should
symmetrical tested periodically according to be followed completely, and a
• Check for flame impinge- approved procedures. The aim purge sequence should be
ment on the surfaces of tubes and importance of these tests is carried out to remove fuel from
• Note any burners that are to detect unidentified failures the firebox before a burner is
showing signs of plugging and to reduce the probability ignited.
• Ensure all peep holes and of failure on demand in the
dampers on burners out of instrumented protective func- Safe operation
operation are closed. tion. The quality of these tests The primary consideration is
If a burner is not firing, it is is very important and has a safety for operating personnel
best to remove the oil gun or, if major bearing on probability of and equipment. During shut-
this cannot be done, keep the failure on demand of the down, all fuel inputs to the
atomising steam on to avoid instrumented protective func- furnace, except for pilots, must
fouling of the tips. Burners tion. All test results should be be isolated. Pilots are kept
should be periodically removed analysed and test reports kept alight as a safety precaution so
from service and cleaned or for future inspections. that fuel does not accumulate
repaired. Burners exhibiting long, and lead to an explosion. Low
Online and off-line cleaning non-symmetrical flames process flow through the tubes
of heaters removes all hydro- impinging on the tubes indi- is a good example of “heat
carbon residues, soot and other cates plugging problems. The off” shutdown.
deposits (see Figures 4 and 5). first priority in this instance The very poor condition of
Optimal energy efficiency is should be to calibrate periodi- the furnace refractory has
restored and the equipment’s cally the oxygen analyser; this resulted in high casing temper-
lifetime is extended. Heater is essential for optimum atures and numerous flue gas
tubes should be cleaned and furnace efficiency. If necessary, leaks through the casing. The
repaired; burner atomisers a new analyser should be safety of platforms around the
should be checked for corro- installed. furnace was low because of
sion and erosion; tip hole The main hazard for furnaces flue gas leakages and radiation
drillings and alignment should is gas accumulation in the fire- from the hot furnace casing.
be checked; and the burner box and explosion. Explosion The installation of new refrac-
tip’s position needs to be will occur if a source of igni- tory will result in increased
adjusted. tion is introduced into a firebox thermal efficiency in the
All process shutdown param- containing a flammable furnace, reliability and safety
eters for furnaces must be kept mixture of fuel and air. The will increase, and the mainte-
in operation without bypassing most hazardous periods during nance shutdown period will be
safe operating conditions; the operation of furnaces are reduced.
Figure 6 Percentage of oxygen analyser after installation of Figure 7 Tag plot for total temperature of furnaces
furnace control