Professional Documents
Culture Documents
Subject:-Cross Examination of Sri S RW-5 On 10-11-2020 at 11.30am Through
Subject:-Cross Examination of Sri S RW-5 On 10-11-2020 at 11.30am Through
To,
Sir,
Adverting to the above subject I beg to bring few lines for your kind
considerations and further needful in the matter.
During my cross examination the learned counsel for claimant Sri. Chaitanya .
S. G, insisted me to answer only in two words “Yes” or “No” in respect few of the
question viz question No 8 and 9. As soon as I answered the above questions, I
wanted to elaborate my answer, so that there is confusion in respect of my one word
answer, but the learned counsel for claimant did not heed to my request. At this
juncture, the Govt. pleader also did not come to my help.
Time and again, the learned counsel for claimant was in a hurry to prove that
the estimate was prepared in haste and is faulty as in question No 8, 9, 11, 14, 23
and 37. The learned counsel for claimant frequently repeated these questions as
stated above, in order to get answer as desired by him to suit his case and thereby
prove that the preparation of estimate itself is faulty. However I have replied to all the
questions put forth by the learned counsel for claimant in an appropriate manner.
Further I write a submit as under.
Here it is to be stated that the LBC from 0.00 to 2.00 KMs also runs in deep
B.C. Soil and the work of improvements to this reach is tackled with 30 Cm CNS
layer at bottom and sides and M15 concrete of thickness 10 Cm for bed and 7.5 Cm
for sides as recommended in the sanctioned estimate. This reach of LBC up to 2.00
KM has not developed any cracks (Horizontally or vertically) and the bill for this
reach is also paid to claimant.
It is only beyond 2.00 Km upto 6.00 Kms that the cracks have developed after
the execution of the work, which is due to bad quality of work turned out by the
claimant. This is evident from the quality control report dated 30-06-2013 furnished
by Premier Technical Consultant, who was authorised to conduct quality control tests
for the above work. In the quality control reports, the reasons for the development of
cracks in canal bed and sides as summarised by Premier Technical Consultant are
as under.
1. In the sanctioned estimate, the provision of C.C has been provided 75mm for
side slopes and 100mm for bed. After taking C.C cores by our technical staff,
it is observed that the thickness of CC for bed and sides is not to the required
thickness at some locations. (As stated in Para 1 page-1 of report date-30-06-
2013.
2. In spite of given instructions orally by our field staff during execution, the
gravel casing provided in some reaches, where the cores are taken is less
than the provision made in estimate.(As per Para-2, page-1 of the report date-
30-06-2013 )
3. Due to insufficient curing in the initial stage. (As per item No.2 of Para-3,page-
1 of the report date-30-06-2013)
The above points are to be brought to the notice of the Arbitrator through an
Affidant by the Govt Pleader for his kind considerations. If not the order may prove
detrimental to the interest of the Govt.
As regards the appointment Govt pleaders for this case, it is to be stated that
on the day of my cross examination date 10-11-2020 Sri Basavaraju attended the
case as Govt pleader on behalf of the respondent.
Such being the case the temporary Govt pleaders possesses very little
knowledge about the fact of the case and will not be able to help and advise the Govt
witnesses during cross examination, as the case with me during the cross
examination date 10-11-2020.