Government Of Goa

Office Of The Executive Engineer


Works Division XV(NH),PWD,
Ponda-Goa.

SUB: Strengthening of NH-566 from Km. 0.00 to Km. 4.00 (Dhavali


bypass) on EPC Mode in the State of Goa under NH(O) Annual Plan
2023-24.

Reply to pre- bid Queries

Queries Reply
1 No, period of completion
will be remain same as in
Request to modify its completion period : 15 NIT.
months incl. Monsoon period as monsoon
period affects the worksfor 4 to 6 months

2 As per MORTH Formats in other Tender this The following may be


clause is as follows: considered and will form part
of Bid Document:
The EPC Contractor shall within 30 days of The EPC Contractor shall within
appointed date mobilise on site following:
30 days of appointed date
1.Batch Mix plant mobilise on site the following –
2.Hot Mix Paver Finisher with electronic (i) Batch mix plant
sensor
In case of failure to mobilise the above (ii) Hot-mix paver finisher
equipment at site within 30 days from date of with electronic sensor
LoA, the Agreement shall be terminated after a In case of failure to mobilise
notice period of 10 days in this regard, and the the above equipment at site
performance security shall be forfeited within 30 days from date of
LoA, the Agreement shall be
terminated after a notice
Kindly include the same for the clarity as period of 10 days in this regard,
follows. The EPC Contractor shall within 30 and the performance security
days of appointed date mobilise owned Plant shall be forfeited.
and machinery on site as following:
1.Batch Mix plant for hot mix, capcity 120TPH
withinn the radius of 60 km
2.Hot Mix Paver Finisher with electronic
sensor with minimum width of 8.5 metre
3.Tandem Roller
4. Pneumatic roller
3 In the table of Strengthning in builtup area TCS is May contact office for the
not provided same

Kindly provide cross sections.


4 In the table of Typical cross sections of.the project May contact office for the
highway in the 5 th column of table is mentioned as same
TCS attached
Kindly provide cross sections.

5 Quantity is not mentioned in


As per Schedule B - Pg.184 Clause 12 It is Schedule –C since the item
mentioned as the thrie beam metal crash barrier of installation of thrie beam
shall be provided of min length 1.05 km crash barrier is not
considered in estimate.
Wheras in Schedule C point no.2b ii)
however, the damaged crash
The Minimum length of____km Thrie beam barriers shall be repaired/
metal (single beam sided ) crash barrier and replaced as per site condition
shall be provided as per schedule D and for by the executing agency.
safety of traffic and users Schedule B- clause 12 (Page
184) min. length 1.05 Km.
Quantity is not mentioned in schedule C Kindly may be considered as N.A.
Clarify

SD/-
EEXV(NH), PWD Ponda