Professional Documents
Culture Documents
Details and and comply with the Specifications and Drawings pre -
pared by him.
Once the submission is given to him, the Engineer
Designer’s responsibility
Where construction difficulties, problems or acci-
dents develop on a project, litigation may develop rela-
tive to liability for financial losses. Such litigation some-
times questions whether the material supplied in
accordance with approved shop drawings conforms to
the design concept of the project and complies with the
project specifications and drawings as prepared by the
design engineer. The National Society of Professional
Engineers in 1974 took the following position relative to
the engineer’s responsibility in such a case:
In approving Shop Drawings, catalog data, sched -
ules and samples, the Engineer should indicate that Typical details for tendon anchorage installation at corner
these items conform to the design concept of the Project column of waffle slab structure.
municated by the design drawings and contract docu- by different subcontractors, and that these drawings
ments. The post-tensioning subcontractor normally show two or more items occupying the same space. The
does not have design calculations or other information ultimate responsibility for eliminating such conflicts be-
on the project necessary for complete determination of tween shop drawings is considered to rest with the engi-
s t ru c t u ral adequacy. For these reasons, the post-ten- neer, architect or other agency responsible for construc-
sioning subcontractor as well as the general contractor tion supervision. In most cases details can be rather
must rely on the engineer to determine that the infor- easily adjusted at the shop drawing stage to accommo-
mation submitted on the shop drawings is structurally date all embedded items. When conflicts do arise during
adequate and responsive to the intent of the contract the development of shop drawings, or during construc-
documents. tion, preferential consideration should be given to the
primary structural system which normally includes the
post-tensioning tendons.
The Post-Tensioning Manual shows examples of de-
sign detailing practices for buildings, including typical
one-way slabs and supporting beams, one-way and two-
way joist floors, two-way flat plates, and flat plates with
drop panels. Detailing of beam-column intersections
must be carefully developed to avoid undue congestion
or conflicts between the post-tensioning system and the
main column reinforcement. Also, adequate clearance
must be provided to permit access by stressing equip-
ment. Stressing equipment clearance requirements for
various tendon sizes are provided by suppliers, and a
number of typical details for the different post-tension-
ing systems are available in the Post-Tensioning Manual.
Acknowledgment
Information and illustrations in this article were taken from
Beam-column intersection showing reinforcement location the Post-Tensioning Manual with permission of the publish-
relative to tendon anchorage. Note that bundled bars have er, the Post-Tensioning Institute. The manual is available
been selected to help reduce congestion at this from PTI, 301 W. Osborn, Phoenix, Arizona 85013 or from
intersection. Concrete Construction Publications, Inc., 426 South West-
gate, Addison, Illinois 60101.