CONSTRUCTION METHOD
STATEMENT
PILE MATERIAL RECEIVAL
CONSTRUCTION OF A
DOMESTIC WASTEWATER
TREATMENT PLANT AND
PUMPING STATION - PACKAGE
A2
PROJECT NO.: 2914
MMS ID: HSEQ-QA-TEM004-GEN-2914
PROJECT REVISION 0 – 2608 JULY SEPTEMBER 2020
COMMERCIAL-IN-CONFIDENCE
DOCUMENT NO : HSEQ-QA-CMS0016-CIV-2914
Revision History
This document remains the property of MDI-PP JV. Its contents are confidential and shall not be reproduced, destroyed or given
away without the express, written permission of MDI-PP JV. The electronic version of this document in MMS Database on
designated server(s) is the Master Copy and is a controlled document. Unless specifically noted thereon, other copies of this
document are uncontrolled.
TABLE OF CONTENT
1 GENERAL.................................................................................................................3
1.1 Objective............................................................................................................3
1.2 Definition............................................................................................................3
1.3 Scope of Works..................................................................................................3
2 JOB RESPONSIBILITY............................................................................................3
2.1 Site Manager......................................................................................................3
2.2 Civil Engineer.....................................................................................................4
2.3 Civil Supervisor..................................................................................................4
2.4 HSE Officer........................................................................................................5
2.5 QC Inspector......................................................................................................5
2.6 Lift Engineer.......................................................................................................6
2.7 Crane Lifting Supervisor....................................................................................6
3 PROCEDURE...........................................................................................................8
3.1 Flowchart............................................................................................................8
3.2 Safety Preparation.............................................................................................8
3.3 Preparation.........................................................................................................9
3.4 Site Preparation and Access...........................................................................10
3.5 Material Receival Inspection............................................................................14
3.6 Crane Positioning and Lifting...........................................................................14
3.7 Material Stockpile.............................................................................................17
4 ACTIVITY SCHEDULE / MILESTONES................................................................20
5 CONSTRUCTION RESOURCES...........................................................................20
5.1 Personnel & Training Requirements................................................................20
5.2 Subcontractors & Suppliers.............................................................................21
5.3 Plant & Equipment...........................................................................................22
5.4 Material............................................................................................................22
6 INSPECTION & TESTING......................................................................................23
7 OHS&E HAZARD IDENTIFICATION, RISK ASSESSMENT & CONTROL ...........23
8 HAZARDOUS MATERIAL / SUBSTANCES..........................................................25
9 HSE TASK ANALYSIS AND JOB SAFETY ANALYSIS........................................26
10 SAFETY PRECAUTION & PROGRAM..............................................................26
11 QUALITY MANAGEMENT..................................................................................27
11.1 Quality Assurance........................................................................................27
11.2 Quality Control..............................................................................................27
12 REVIEW & APPROVAL......................................................................................28
Page 2 of 47 HSEQ-QA-CMS0016-CIV-2914 Rev: 00
Palembang City Sewerage Project
Construction Method Statement for Pile Material Receival
1 GENERAL
1.1 Objective
This method describes the general procedure of pile material receival work. This
method statement is carried out to ensure the work executed safely and effectively.
Metode ini menjelaskan tentang prosedur umum pelaksanaan pekerjaan penerimaan
material pancang. Metode kerja ini dibuat untuk memastikan pekerjaan berlangsung
dengan aman dan efektif.
1.2 Definition
Table 1. Project Definition
2 JOB RESPONSIBILITY
2.5 QC Inspector
• Coordinating Work Inspection Request
• Conducting inspection of work in accordance with the stages mentioned in the ITP
and ensure the results of the work are made and stored properly
• Make Preparing a report of deviations that occur [NCR] and follow up
• Create Preparing a working quality report (RFI, ITP, ITR and Documentation)
• Mengkoordinir Permintaan Inspeksi Pekerjaan (WIR)
• Melaksanakan pemeriksaan hasil kerja sesuai dengan tahap-tahap yang tersebut
dalam ITP dan memastikan hasil pekerjaan dibuat dan disimpan dengan baik
• Membuat laporan penyimpangan-penyimpangan yang terjadi [NCR] dan
menindaklanjutinya
• Membuat laporan kualitas kerja (RFI, ITP, ITR dan Dokumentasi)
• Ditunjuk oleh manajer proyek atau manajer konstruksi dan memiliki pengalaman
dan kualifikasi yang diperlukan di bidang crane dan pengangkatan.
• Libatkan insinyur pihak ketiga dan / atau arsitek angkatan laut untuk memberikan
masukan untuk lift yang relevan.
• Buat perhitungan beban.
• Hadir untuk semua pertemuan sebelum pengangkatan lift kritis dan hadir selama
pengangkatan kritis.
3 PROCEDURE
3.1 Flowchart
Start
Work Permit
CEP Preparation
CMS Persiapan
JSEA
Material Approval
Manufacturing Procedure Preparation for Site Access and Storage
Specification Persiapan akses ke Lokasi dan Penyimpanan
Material Receival
Material Handling Document
Equipment & Manpower Material & Equipment Mobilization
Mobilization Mobilisasi Material & Alat
Material Storage
Penyimpanan Material
Finish
Figure 12 - Flowchart
Figure 1. Flowchart
a. Install the safety equipment as described on JSEA and ensure all personnel use
their PPE according to their requirement.
3.3 Preparation
c. The location of the stockpile can be seen in the Figure 15 layout below. The
location of stockpile might be adjusted based on the future site condition and
work.
Lokasi stockpile pancang dapat dilihat pada layout gambar dibawah. Lokasi
penyimpanan pipa mungkin bisa berubah tergantung kondisi lapangan dan
pekerjaan kedepan.
Steel Pipe
Pile Stockpile
Pada pengiriman pertama, truck trailer yang membawa tiang pancang akan
memasuki area stockpile di site melalui area gui pada bagian selatan pada lokasi
site sebagaimana ditunjukkan di Figure 16 di bawah ini.
Entrance area
from GUI (South
side of the site
location).
b. Random sampling was checked, namely measuring plate thickness, pipe length,
pipe diameter and pipe straightness.
Dilakukan pengecekan secara sampling acak, yaitu pengukuran ketebalan plat,
panjang pipa, diameter pipa dan kelurusan pipa.
c. The results of the inspections are recorded and for pipes that have a defect, will
be marked and placed in a separate stockpile for repair.
Hasil pengecekan di catat dan untuk pipa yang memiliki cacat, akan di tandai dan
ditempatkan pada stockpile terpisah untuk perbaiki.
Exclusion Zone
a. The surface to be used for pipe piling must be flat and free from protrusions.
Permukaan yang akan dipakai untuk penumpukan pipa harus datar dan bebas
dari tonjolan.
b. The bearing strips shall be levelled to provide uniform load distribution.
Strip bantalan harus diratakan untuk memberikan distribusi beban seragam.
c. Pipes can be stored only in stable soil.
Pipa dapat disimpan hanya di tanah yang stabil.
d. The ground surface for stockpiles must be free from puddle and avoid rain runoff
scouring out under timber supports.
Permukaan tanah untuk penumpukan pipa harus bebas dari genangan air dan
hindari limpasan hujan yang mengalir di bawah penyangga kayu.
e. Every six (6) meters of pipe length shall be provided with dunnage or sandbags to
avoid pipe bending. The size of the dunnage wood is 10 x 12 (HxW) cm.
Setiap enam (6) meter dari panjang pipa harus disediakan dunnage atau karung
pasir untuk menghindari lenturan pipa. Ukuran kayu dunnage adalah 10 x 12
(HxW) cm.
f. For coated pipes, the subsequent heaps of pipes should be separated from each
other by wooden pads (stopper) or sandbags.
Untuk pipa yang dilapisi, penumpukan berikutnya pipa harus dipisahkan dari satu
sama lain dengan bantalan kayu (stopper) atau kantong pasir.
g. The number of stacks (levels) is referenced in the following table according to the
product handling by the manufacturer (KHI).
Jumlah tumpukan (tingkatan) direferensikan pada table berikut sesuai dengan
produk handling dari manufacturer (KHI).
Steel Pipe
Pile
Stockpile
Entrance area
from GUI (South
side of the site
location).
o. The steel pipe pile is attached to the sling according to the lifting plan, as shown in
the Figure 19 and Figure 20 below.
Steel pipe pile dikaitkan ke sling sesuai dengan lifting plan sebagaimana di
tunjukkan pada Figure 19 dan Figure 20 di bawah ini.
4577
0,457 m
p. The swing crane radius to be able to reach the piling material from the trailer truck
to the stockpile can be seen in the Figure 21 image below.
Radius swing crane untuk dapat menjangkau material pancang dari truck trailer
menuju stockpile dapat dilihat pada Figure 21gambar di bawah ini.
q. pile material is lifted from the trailer and placed in the stockpile.
material pancang diangkat dari trailer dan ditempatkan di stockpile.
Hasil pengecekan di catat dan untuk pipa yang tidak masukmemiliki cacat, akan
di tandai dan ditempatkan pada stockpile terpisah untuk ditindaklanjutiperbaiki.
g. The surface to be used for pipe piling must be flat and free from protrusions.
Permukaan yang akan dipakai untuk penumpukan pipa harus datar dan bebas
dari tonjolan.
h. The bearing strips shall be levelled to provide uniform load distribution.
Strip bantalan harus diratakan untuk memberikan distribusi beban seragam.
i. Pipes can be stored only in stable, dry soil.
Pipa dapat disimpan hanya di tanah yang stabil dan kering.
j. The ground surface for pipe pilingstockpiles must be free from stagnant
waterpuddle.
Permukaan tanah untuk penumpukan pipa harus bebas dari genangan air.
k. Every six (6) meters of pipe length shall be provided with dunnage or sandbags to
avoid pipe bending. The size of the dunnage wood is 10 x 12 (HxW) cm.
Setiap enam (6) meter dari panjang pipa harus disediakan dunnage atau karung
pasir untuk menghindari lenturan pipa. Ukuran kayu dunnage adalah 10 x 12
(HxW) cm.
l. For coated pipes, the subsequent heaps of pipes should be separated from each
other by wooden pads (stopper) or sandbags.
Untuk pipa yang dilapisi, penumpukan berikutnya pipa harus dipisahkan dari satu
sama lain dengan bantalan kayu (stopper) atau kantong pasir.
m. The number of stacks (levels) is referenced in the following table according to the
product handling by the manufacturer (KHI).
Jumlah tumpukan (tingkatan) direferensikan pada table berikut sesuai dengan
produk handling dari manufacturer (KHI).
Table 2. Pipe Stacking
Estimated Commencement
Estimated Completion Date Duration (Day)
Date
October 2020 December 2020 -
5 CONSTRUCTION RESOURCES
Subcontractors & suppliers for the works will bethat are involved are divided into
scope of works, name of subcontractor/suppliers, contact person and contact details.
Subkontraktor & pemasok untuk pekerjaan yang akan dilibatkan terbagi dalam
lingkup pekerjaan, nama subkontraktor / pemasok, contact person dan detail
kontak.
Plant and equipment associated with the works will be in good working order and
have the capacity to safely and efficiently do the work required. The type, size and
number of machines used will depend on the quantity of material, scheduling and
access restrictions. Necessary plant inspections and operator competency
assessments will be undertaken as part of the Project Safety Management Plan.
Plant dan peralatan yang terkait dengan pekerjaan akan berfungsi dengan baik dan
memiliki kapasitas untuk melakukan pekerjaan yang diperlukan dengan aman dan
efisien. Jenis, ukuran dan jumlah mesin yang digunakan akan tergantung pada
jumlah material, penjadwalan dan pembatasan akses. Inspeksi instalasi yang
diperlukan dan penilaian kompetensi operator akan dilakukan sebagai bagian dari
Rencana Manajemen Keselamatan Proyek.
Table 6. Plant & Equipment
5.4 Material
Materials incorporated into the works will be compliant with the IFC drawings,
technical specifications, relevant standards and manufacturer’s instructions.
Material yang dimasukkan ke dalam pekerjaan akan sesuai dengan gambar IFC,
spesifikasi teknis, standar yang relevan, dan instruksi pabrik.
Table 7. Material
Person or
organisation
ITP Number Title / scope
responsible for
preparation
Hazard identification, risk assessment and control will be principally managed and
documented through the use of the HSE Risk Register (HSEQ-HS-TEM003-GEN-
ALL). Relevant SWI’s, SOPs and EPIs will be implemented and followed. JSEA /
SWMS’s will be prepared to cover specific risks associated with the works.
Development and implementation of the JSEA / SWMS and the associated
documentation (SWI’s; SOP’s; EPIs; etc...) will be undertaken with the personnel
involved in the works. These documents can then be viewed by the Client’s
representative prior to work commencement.
All personnel will complete the project site induction before being allowed access to
the works. Operator competency will be recorded, and plant inspections will be
undertaken prior to any activity commencing. Daily start start-up meetings will be
conducted and documented by Supervisors to ensure all safety measures are in
place for the day’s activities. OHS&E hazard identification, risk assessment &
control that will be involved are divided into JSEA, development responsibility (role)
and due by.
Identifikasi bahaya, penilaian dan pengendalian risiko pada prinsipnya akan dikelola
dan didokumentasikan melalui penggunaan HSE Risk Register (HSEQ-HS-
TEM003-GEN-ALL). SWI, SOP, dan EPI yang relevan akan diterapkan dan diikuti.
JSEA / SWMS akan disiapkan untuk menanggung risiko spesifik yang terkait
dengan pekerjaan.
Pengembangan dan implementasi JSEA / SWMS dan dokumentasi terkait (SWI;
SOP; EPI; dll ...) akan dilakukan dengan personel yang terlibat dalam pekerjaan.
Dokumen-dokumen ini kemudian dapat dilihat oleh perwakilan Klien sebelum
pekerjaan dimulai.
Semua personel akan menyelesaikan induksi lokasi proyek sebelum diizinkan
mengakses pekerjaan. Kompetensi operator akan dicatat dan inspeksi pabrik akan
dilakukan sebelum aktivitas dimulai. Pertemuan awal harian akan dilakukan dan
didokumentasikan oleh Supervisor untuk memastikan semua tindakan keamanan
tersedia untuk aktivitas hari itu. Identifikasi bahaya OHS & E, penilaian &
pengendalian risiko yang akan dilibatkan dibagi menjadi BEJ, tanggung jawab
pengembangan (peran) dan masa berlaku.
Development
JSEA/SWMS Title / Activity description
Responsibility Due By
(What)
(Role)
012/MDI-PP/JSEA/IX/2020 Pekerjaan
Site Manager 24/09/2020
Penerimaan Material Pancang
REF-HSEQ-HS-SWI012-GEN-IND-
Lifting and Slinging
2914
REF-HSEQ-HS-SWI015-GEN-IND-
Operating Cranes
2914
Management of Loading, Unloading &
HSEQ-HS-SWI140-GEN-ALL
Deliveries
Crane and Lifting Operations HSEQ-HS-SOP001-GEN-2914
Table 1920 - Required SWI for Activities / Tasks
Table 11. Environmental Aspects Identification, Risk Assessment & Controls
Implementation
Aspect
Control (How) Responsibility
(What)
(Role/Subcontractor)
N/A N/A
The HSE and Engineering to identified identify the following risks / hazards
associated with this work and a set Job Safety & Environment Analysis (JSEA) /
Hazard Identification, Risk Assessment to be prepared as per actual condition for
each risk / hazard.
HSE dan Teknik untuk mengidentifikasi risiko / bahaya berikut yang terkait dengan
pekerjaan ini dan harus membuat format analisa keselamatan kerja & lingkungan
(JSEA) / identifikasi bahaya dan pengendalian resiko agar disiapkan sesuai dengan
kondisi nyata untuk setiap resiko/bahaya.
The purpose of the safety requirement is intend intended to guide the concerned
personal such as Site Manager, Civil Supervisor, Operator, and Worker or employees
in managing HSE during sheet pile installationsteel pipes receival and other general
HSE activities.
Tujuan dari persyaratan keselamatan ini adalah untuk membimbing orang yang
bersangkutan seperti Site Manager, Supervisor, Operator, dan Pekerja atau
karyawan dalam mengelola HSE Keselamatan Kerja selama pemasangan sheet
pilepenerimaan pipa pancang dan kegiatan HSE lainnya.
a. Key personnel at site shall provide PTW and approved job safety & environment
analysis (JSEA), and ensure all team involved working at the area on fit health for
work condition on daily basicbasis, if the worker not in fit condition immediately shall
goes to the clinic and take a rest base on the recommendation.
Personil utama di lapangan harus menyediakan PTW dan analisis keselamatan
kerja & lingkungan yang disetujui (JSEA), serta memastikan semua tim yang
terlibat bekerja di area pekerjaan dalam kondisi sehat yang sesuai dengan kondisi
kerja sehari-hari, jika pekerja tidak dalam kondisi sehat harus segera pergi ke klinik
dan mengambil istirahat berdasarkan rekomendasi.
b. Prior to starting the work, all workers involved are to be recorded, briefed, fully
complied with mandatory PPE.
Sebelum memulai pekerjaan, semua pekerja yang terlibat harus dicatat, dibriefing,
dan sepenuhnya mematuhi PPE wajib.
c. Toolbox meeting prior to starting the work is mandatory for workers involved.
Toolbox meeting sebelum pekerjaan dimulai wajib bagi semua pekerja yang
terlibat.
11 QUALITY MANAGEMENT
a. Ensure the work is performed in accordance with the approved work methods.
Pastikan pekerjaan dilakukan sesuai dengan metode kerja yang disetujui.
b. The working method should be known by everyone involved in the job.
Metode kerja harus diketahui oleh semua orang yang terlibat dalam pekerjaan.
c. Providing an Inspection Test Plan (ITP) and ensuring the internal checks of
preparatory work have been fulfilled before the work is carried out.
Memberikan Rencana Uji Inspeksi (Inspection Test Plan / ITP) dan memastikan
pemeriksaan internal pekerjaan persiapan telah dilakukan sebelum pekerjaan
dilaksanakan.
d. Identify all materials, tools, procedures, resources and management in order to
achieve good work.
Identifikasi semua bahan, peralatan, prosedur, sumber daya dan manajemen agar
bisa mencapai hasil yang baik.
Prior to commencement of work covered by the CMS, arrange a briefing with the
delivery team. Areas to be covered should include :
Sebelum memulai pekerjaan yang dicakup oleh CMS, atur pengarahan dengan tim
yang dituju. Area yang akan dicakup harus mencakup:
This information will assist supervisors and their teams to develop any JSEAs required to
complete the work.
Informasi ini akan membantu supervisor dan timnya untuk mengembangkan JSEA yang
diperlukan untuk menyelesaikan pekerjaan.