You are on page 1of 8

Grounding System Design Optimization on

275 KV Betung Substation Based on IEEE


Standard 80-2000
1.a.
Ishak Kasim, 1.b.Syamsir Abduh, 1.c. Nur Fitryah
1
Electrical Engineering Department, Industrial Technology Faculty
Trisakti University
Jakarta, Indonesia
a
ishak@trisakti.ac.id, bsyamsir@trisakti.ac.id, cfitryahnur@gmail.com

Abstract—The demand of electricity transmission safe and reliable, such Substation should have
toward regions for society, industrial and other grounding system [2]. Grounding system plays
needs are increasing hence, making electricity important role in a Substation operation.
transmission and distribution increased as well. Grounding system provides connected neutral
The increase in electricity transmission and
point system, equipment, and support for
distribution requires addition of Substation
construction. Substation constructions are crucial structure into the earth. Grounding system
for economic growth in Indonesia. This research ensures safety for every one that work inside
aims to design two models of grounding system, to Substation. Grounding system also eases
determine permissible touch voltages and interference finding into the earth and helps
permissible step voltages, and to simulate both controlling and protecting system [1].
designs using CYMGrd Software, whereby both Grounding system has crucial roles a
designs were compared to obtain optimal Substation, amongst them are to ensure people
grounding system at 275 KV Betung Substation. or animal nearby grounded facilities not
With touch voltages and step voltages values of
affected by hazard from electric shock and to
1387.97 V and 364.6 KV in first model, and touch
voltages and step voltages of 1247.2 V and 112.39 provide means to carry electric currents into the
V in second model, both model did not exceed earth under normal and fault conditions without
permissible touch voltages of 1409.58 V and exceeding any operating and equipment limits
permissible step voltages of 5050.1 V. Final result or adversely affecting continuity of service [3].
of this research showed that second design model With this crucial role of grounding
was more optimal compared with the first design system, we conducted grounding system design
model. optimization on 275 KV Betung Substation
Project which aims to design two models of
Keywords—Substation; grounding system; CYMGrd
grounding system by determining permissible
software; touch voltage and step voltage; IEEE 80-
2000 Standard. touch voltages and permissible step voltages on
275 Betung KV Substation, and simulating both
design models with CYMGrd Software.
I. INTRODUCTION Afterwards, both designs were compared to
Substation is an integrated part of obtain optimal design. Grounding system design
electricity distribution and transmission. In on 275 KV Betung Substation discussed in this
which certain power system centered in a place paper is grounding on equipment, and such
containing transmission and distribution, design carried out only on outdoor side which is
distribution tools, transformer, and safety tools simulated using CYMGrd Software.
and control tools. The success of a power
system operation depends on efficient and
II. RESEARCH METHOD
satisfying performance of a Substation.
Therefore, Substation could be said as core of a A. Design Flowchart
power system [1]. Safety and reliability are the Fig. 1. shows design flowchart on how to
two main matters in operation and design of an design grounding system according to IEEE
electricity power system, including in Standard 80-2000:
Substation design. To ensure that Substation is

978-602-50431-1-6/17/$31.00 ©2017 IEEE 400 2017 15th Intl. Conf. QiR: Intl. Symp. Elec. and Com. Eng

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
Fig.1. Design Flowchart According to IEEE 80-2000 [3]

B. Determining Grid Conductor Size C. Touch Voltages and Step Voltages


Equation used to determine grid Someone’s safety depends on critical
conductor size is the following [3]: amount prevention from shock energy being
absorbed before the fault is cleared and the
(1) system de-energized. Maximum driving voltage
of any accidental circuit should not exceed the
determined limits below.
In which Permissible step voltages for 50 kg body
I rms current in kA weight [3]
Amm2 conductor cross section in mm2
Tm maximum allowable temperature in oC (2)
Ta the ambient temperature in oC
Tr reference temperature for material Permissible touch voltages for 50 kg
constant in oC body weight [3]
Įo thermal coefficient of resistivity at 0oC
o
in 1/ C
Įr thermal coefficient of resistivity at Tr (3)
reference temperature in 1/oC
ȡr resistivity from ground conductor at Tr In which :
reference temperature in μȍ-cm Estep step voltages in V
Ko 1/Įo or (1/Įo) - Tr in oC Etouch touch voltages in V
tc duration of current in s Cs surface layer derating factor,
TCAP thermal capacity per unit volume in in which Cs is
J/(cm3. oC)
(4)

401

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
If protective surface layer is not used, then Cs = 1 and ȡs=ȡ.
ȡs earth surface resistivity in tf fault duration in s
ȍ.m Ta dc time offset constant in s
ts duration of shock current in Ig symmetrical grid current in A, in which
seconds. Ig is [4]

D. Determining Grid Maximum Current (7)


Grid maximum current is current
maximum value from grounding grid design
that could be calculated using the following In which
equation [3] RE grounding grid resistance in ȍ
IEtot total current through earth at the short-
(5) circuit location F
Zp driving point impedance in ȍ
In which Zp, IEtot, and r description discussed below
IG maximum grid current in A
Df decrement factor in s with

Fault Current Flowing Through The
Earthing Grid
(6) According to IEC 60909-3, short circuit
phase into the ground are mostly occur on
unbalance short circuit.
In which:
Fig. 2 shows that transformer of (9)
substation B with feeders coming in from
adjacent substation A and C. In which equal In which,
to three times of zero sequence current that flow IEtot total current through earth at the short-
into short-circuit location F [4]: circuit location F in kA
r reduction factor from overhead line
(8) (OHL)
I(0) short-circuit current of zero sequence
Total current through earth at the short- Driving point impedance from Substation is
circuit location F on Substation which
connected to the other Substation is:

IWA IWC Earth Wire

3I(0)A 3I(0)B
3I(0)C

I”k
3I(0)B

B C
A

ZEB
ZEA ZEC
UEB

IEA IEB IEC

IA 31(0)A IC 31(0)C Reference Earth


IEC 223303

Fig. 2. Partial Short-Circuit Current on Short Circuit Phase into the Ground on Substation B [4]

402

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
(10) with

In which, in which
ZP driving point impedance in ȍ resistance per unit length from earth
ZW earth wire impedance between two wires
towers, where ZW [4] rWW equivalent earth wire radius
rW earth wire radius
(11) for 1 earth wire: rWW = rW
for 2 earth wires:
• Reduction Factor for Overhead Line v total earth wire
(OHL) dWL geometric mean distance between earth
The following equation used to calculate wire and phase conductor L1, L2, and
reduction factor for OHL [4] L3
Ȧ angular frequency: Ȧ = 2ʌf
(12) permeability in the air:

relative permeability from earth wire


In which
ȡ ground resistivity
earth wire impedance per unit length
with
III. RESULT
(13) Table 1 shows calculation needed
before designing grounding system. With grid
mutual impedance per unit length installation, deep 0.8 m beneath the surface,
between earth wire and parallel phase mesh grid size was 10 × 10 m, and 0.2 m gravel
conductors with the same return grounding surface installed on Substation. Table 2 shows
grid form of both design model.
(14)

TABLE I. CALCULATION NEEDED BEFORE DESIGNING GROUNDING SYSTEM

No. Calculation Result Equation

1. a. Burried conductor (Amm2) 70.96 mm2 1


b. Down lead from apparatus (Amm2) 141.92 mm2
2. (į) 1446.73 m -
3. Earth wire impedance per unit length (Z’W) 1.139 + j 1.174 ȍ/km 13
4. Earth wire impedance between two towers (ZW) 0.573 ȍ 11
5. Driving point impedance (Zp) 2.70 ȍ 10
6. Mutual impedance per unit length between earth wire and parallel phase 0.05 + j 0.30 ȍ/km 14
conductor (Z’WL)
7. Reduction factor (r) 0.85 ȍ 12
8. Total current through earth at the short-circuit location F (IEtot) 34.14 kA 9
9. Symmetrical grid current (Ig) 13.23 kA 7
10. Decrement factor (Df) 1.044 6
11. Maximum grid current (IG) 13.81 kA 5
12. Derating factor (Cs) 0.8251 4
13. Permissible touch voltage (Etouch) 1409.58 V 3
14. Permissible step voltage (Estep) 5050.10 V 2

403

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
TABLE 2. FIGURE OF BOTH DESIGN MODEL

Model 1

Model 2

In first design model, Bare Copper 276 rods were used. Table 3 shows potential
Conductor (BCC) used were 5,334.35 m and 12 contour simulation result on both design model
rods were used. Meanwhile on the second
design model, 5,089.49 m BCC were used and

404

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
TABLE 3. CONTOUR SIMULATION RESULT ON BOTH DESIGN MODEL

Model 1

Model 2

Table 4 shows potential profile simulation


result on both design model.

405

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
TABLE 4. POTENTIAL PROFILE SIMULATION RESULT ON BOTH DESIGN MODEL

Model 1

Model 2

In the first model, highest touch Table 5 shows optimization from


voltages and step voltages value were 1,387.97 grounding design on 275 KV Betung
V and 364.6 V respectively, meanwhile in the Substation.
second model the values were 1,247.2 V and
112.39 V for highest touch voltages and step
voltages respectively.

406

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.
TABLE 5. OPTIMALIZATION OF BOTH GROUNDING SYSTEM DESIGN OF 275 KV BETUNG
SUBSTATION

Parameter Model 1 Model 2

Permissible Etouch 1409.58 V

Permissible Estep 5050.1 V

Etouch actual 1387.97 V 1247.2 V


Technical
Estep actual 364.6 V 112.39 V

Rg 0.588699 ȍ 0.530937 ȍ

GPR 8313.33 V 7969.95 V

Total BCC Length 5,334.35 m 5,089.49 m

Economical Total Rod 12 pcs 276 pcs

Total Price* (IDR) Rp 4,561,053,777.78 Rp 3,810,225,872.65

IV. CONCLUSION
1. There were two grounding design models ACKNOWLEDGMENT
simulated in this research of grounding Researcher would like to thank source person
system design optimization on 275 kV and all supporting parties in data collection and
Betung Substation. First model used 12 processing in this research. Eventually,
rods and 5,334.5 m BCC. Meanwhile researcher hope that Allah SWT would grant
second model made with more rods, 276 His grace and blessing for all parties supporting
rods and grounding BCC was made the completion of this article.
loose, 5,089.49 m
2. In first model, Etouch actual and Estep
actual was 1,387.97 V and 364.6 V REFERENCES
respectively. Meanwhile on the second [1] K. A. Vyas; J. G. Jamnani, “Optimal Design
model, Etouch actual and Estep actual were of Grounding System for HV/EHV
1,247.2 V and 112.39 V respectively. On Substations in Two Layered Soil”,
permissible Etouch and Estep and manually International Journal of Emerging
calculated, permissible Etouch and Estep Technology and Advanced Engineering,
value was 1,409.58 V and 5,050.1 V Gujarat, 2012, pp. 383 – 392, Vol. 2 (5).
respectively. These showed that both
[2] M. A. Adelian, “Improvement of Substation
design model had complied with the
Earthing”, International Journal of
permissible Etouch and Estep or both design
Engineering and Advanced Technology,
was safe.
3. Upon the comparison of both design, 2014, pp. 100 – 104, Vol. 3 (4).
economically it was predicted that cost [3] IEEE Guide for Safety in AC Substation
needed to construct second grounding Grounding, IEEE Standard 80-2000, 2000.
system design model on 275 kV Betung
Substation was Rp 3,810,225,872.65, [4] S. Ishak, “Module Earthing Calculation Note
cheaper than cost estimation for first Using Excel Spread Sheet and CYMGrd
grounding system design model of Rp Software”, Jakarta : -, 2014, Chapter 2
4,561,053,777.78.

407

Authorized licensed use limited to: Universidad Antonio Narino. Downloaded on May 30,2020 at 17:57:48 UTC from IEEE Xplore. Restrictions apply.

You might also like