SUMMARY Budget MD Used MD Used MD % Progress %

Floor #7 87 64 74% 61% Marriott Gulf Renovation Project Day B4 Yesterday 30-Aug-20
Floor #8 87 41 47% 53% Yesterday 31-Aug-20
Floor #9 87 40 46% 40%
Blue Building Electrical Installation Today 01-Sep-20
Floor #10 87 30 34% 35% Pending 1st Fix Works (floors 7 to 11) Incharge Amal
Floor #11 87 0 0% 0%
Total 435 175 40.2% 37.8% 6 9 0 10 13 0 0 0 0 0 0 0 0 0 0
Floor #7 Budget MD Used MD Status Progress % 8 Aug - 25 Aug 26 Aug 27 Aug 28 Aug 29 Aug 30 Aug 31 Aug 1 Sep 2 Sep 3 Sep 4 Sep 5 Sep 6 Sep 7 Sep 8 Sep 9 Sep
Facade Light 33 31 Blocked 89% 30 1
Cable Tray 15 9 30% 6 3
Fire Damper 6 7 Ongoing 89% 6 1
Staircase#1 3 3 Complete 100% 3
Staircase#2 3 0 Blocked
Fire/Light Cnx 12 14 90% 12 2
IT Room 6 0
Elec. Room 9 0 Blocked
Total MD 87 64 61% 57 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0
Floor #8 Budget MD Used MD Status Progress % 8 Aug - 25 Aug 26 Aug 27 Aug 28 Aug 29 Aug 30 Aug 31 Aug 1 Sep 2 Sep 3 Sep 4 Sep 5 Sep 6 Sep 7 Sep 8 Sep 9 Sep
Facade Light 33 26 Blocked 85% 26
Cable Tray 15 0
Fire Damper 6 4 Ongoing 80% 2 2
Staircase#1 3 3 Complete 100% 3
Staircase#2 3 0 Blocked
Fire/Light Cnx 12 8 Ongoing 85% 4 4
IT Room 6 0 Blocked
Elec. Room 9 0 Blocked
Total MD 87 41 53% 31 2 4 0 4 0 0 0 0 0 0 0 0 0 0 0
Floor #9 Budget MD Used MD Status Progress % 8 Aug - 25 Aug 26 Aug 27 Aug 28 Aug 29 Aug 30 Aug 31 Aug 1 Sep 2 Sep 3 Sep 4 Sep 5 Sep 6 Sep 7 Sep 8 Sep 9 Sep
Facade Light 33 29 Ongoing 80% 25 2 2
Cable Tray 15 0
Fire Damper 6 4 Ongoing 50% 2 2
Staircase#1 3 3 Complete 100% 3
Staircase#2 3 0 Blocked
Fire/Light Cnx 12 4 20% 4
IT Room 6 0 Blocked
Elec. Room 9 0 Blocked
Total MD 87 40 40% 28 4 2 0 2 4 0 0 0 0 0 0 0 0 0 0
Floor #10 Budget MD Used MD Status Progress % 8 Aug - 25 Aug 26 Aug 27 Aug 28 Aug 29 Aug 30 Aug 31 Aug 1 Sep 2 Sep 3 Sep 4 Sep 5 Sep 6 Sep 7 Sep 8 Sep 9 Sep
Facade Light 33 24 Ongoing 75% 18 3 2 1
Cable Tray 15 0
Fire Damper 6 3 Ongoing 50% 2 1
Staircase#1 3 3 Complete 100% 3
Staircase#2 3 0 Blocked
Fire/Light Cnx 12 0
IT Room 6 0 Blocked
Elec. Room 9 0 Blocked
Total MD 87 30 35% 21 0 3 0 4 2 0 0 0 0 0 0 0 0 0 0
Floor #11 Budget MD Used MD Status Progress % 8 Aug - 25 Aug 26 Aug 27 Aug 28 Aug 29 Aug 30 Aug 31 Aug 1 Sep 2 Sep 3 Sep 4 Sep 5 Sep 6 Sep 7 Sep 8 Sep 9 Sep
Facade Light 33 0
Cable Tray 15 0
Fire Damper 6 0
Staircase#1 3 0
Staircase#2 3 0 Blocked
Fire/Light Cnx 12 0 Blocked
IT Room 6 0 Blocked
Elec. Room 9 0 Blocked
Total MD 87 0 0% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0