Professional Documents
Culture Documents
Ex.6.8 We would expect to penalized for one day past the 15 day deadline.
Ex.6.12 The project is expected to take 18 days. The project is not very sensitive with one dominant critical path.
Activities B, D, E, G, H and J all have total slack of 9. Activities B, D, E, and G have zero free slack. Activ
e dominant critical path.
ave zero free slack. Activities H and J have 9 days of free slack.
CHAPTER 8 Scheduling Resources & Costs
Ex.8.1
Ex.8.2
Resource constraints extend the project duration from 12 days to 14 days and Activity 2
which was part of the original critical path is no longer critical path. All other activities are
critical which illustrates the key point that resource constraints tend to increase the
sensitivity of project networks.
ays and Activity 2
other activities are
o increase the
CHAPTER 9 Reducing Project Duration
2 Reduce activity A one time unit (from CP, and least cost activity)
A-B-E-G 2+6+8+6 22
A-C-F-G 2+10+5+6 23
CP A-D-F-G 2+11+5+6 24
Cost 470
3 Reduce activity D one time unit (from CP, and least cost activity)
A-B-E-G 2+6+8+6 22
CP A-C-F-G 2+10+5+6 23
CP A-D-F-G 2+10+5+6 23
Cost 495
4 Reduce activity F one time unit (from CP, and least cost activity)
CP A-B-E-G 2+6+8+6 22
CP A-C-F-G 2+10+4+6 22
CP A-D-F-G 2+10+4+6 22
Cost 525
5 Reduce activity C, D, E one time unit (from CP, from each path)
CP A-B-E-G 2+6+7+6 21
CP A-C-F-G 2+9+4+6 21
CP A-D-F-G 2+9+4+6 21
Cost 610
Ex.9.2
CHAPTER 13 Progress and Performance Measurement and Evaluation
Ex.13.1
CV = EV – AC = 2,100 – 2,000 = 100
SV = EV – PV = 2,100 – 2,400 = -300
Ex.13.2
CV = EV – AC = 600 – 650 = -50
SV = EV – PV = 600 – 560 = 40
CPI = EV / AC = 600 / 650 = 0.92 Over Cost
Ahead of
SPI = EV / PV = 600 / 560 = 1.07
Schedule
Ex.13.3
End of Period 4
Actual % EV AC PV CV SV
Task
Complete $ $ $ $ $
A Finished 400 300 400 100 0
B 50% 1200 1000 800 200 400
C 33% 500 500 600 0 -100
D 0% 0 0 0 0 0
E 0% 0 0 0 0 0
Cumulative Totals $2100 $1800 $1800 $+300 $+300
The project appears to be doing nicely. In both periods 4 and 8 the cost variance is positive—+$300 and
The schedule variance is also positive—+$300 and +$400 for period 4 and period 8. Since Task D is al
Note: Completion of the answer sheet requires constant reference to the baseline figure.
s not started
25% complete
e is positive—+$300 and +$400, respectively. This suggests a pattern of good cost variance that is under budget.
od 8. Since Task D is already 25% complete, Task B must have been completed at least one period early.
under budget.