Re-planned/Delayed
Planned
Criteria Time frame
Writing of quality manual
2 weeks
Writing of procedures
Training of CFL team on understanding and importance of ISO 17025
4 weeks
Implementation of procedures with internal team
Submission of application form to MAURITAS including quality manual
Review of QM by MAURITAS 3 weeks
Pre-assessment by MAURITAS
Feedback from MAURITAS on pre-assessment and corrective actions 1 week
Initial Assessment 3 days
Corrective actions proposal and Closure of NCS 3 weeks
Approval by MAURITAS committee
1month
Grant of Accreditation
March April May June July August September October November December January February March
CFL Lab ISO 17025 Implementation Roadmap
Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks Weeks
S/N No. Criteria 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 1st 2nd 3rd 4th 5th 1st 2nd 3rd 4th 5th
1 Training on M&S test methods (theory)
10 Writing of procedures
14 Review of QM by MAURITAS
15 Pre-assessment by MAURITAS
17 Initial Assessment
20 Grant of Accreditation