Meeting: Project Review Meeting Meeting Date: 10-Feb-20


Meeting Number: PM-05 Meeting Time: 4:00 PM
ESGRM-03
Date of Issue: 12-Feb-20

Labour Camp,Tie up with Hospital & Ambulence,


Agenda: Safety helmet, AOB, Labour & staff toilet at site, Time of Issue: 5:00 PM
Celebration of National Safety day.

SL
Name Agency Code Remarks
No.
1 Mr. Abir Sengupta SPL Estates Private Limited AS

2 Mr. Ayan Basu Mallick SPL Estates Private Limited ABM

3 Mr. Prakash Mitra Simplex Infrastructures Private Limited PM

4 Mr. Arvind Kumar Anand Simplex Infrastructures Private Limited AKA

5 Mr. Biswanath Moulick Simplex Infrastructures Private Limited BM

6 Mr. Dibbendu Das Adhikari Simplex Infrastructures Private Limited DDA

7 Mr. Amit Roy Simplex Infrastructures Private Limited AR

8 Mr. Sanjay Kumar Datta Masters Development Management(India) Pvt. SKD


Ltd.

9 Mr. Pradip Bandyopadhyay Masters Development Management(India) Pvt. PB


Ltd.

10 Mr. Sudip Kumar Ghosh Masters Development Management(India) Pvt. SKG


Ltd.

Details of Minutes described in the next sheet.

Issued On: 12-02-2020 Page 1 of 4


MASTERS

MINUTES OF MEETING
PM - 05
ESGRM - 03 Date : 10-Feb-20
Raised Action
Sr. No. Subject Points/Issues Raised Comments and Decisions Date Remarks
by by
A. ESG Review
1 Labour Licence MDM enquired about labour licence which is due till date. MDM/SP PM mentioned that they are waiting for the signed hard copy of LOI, without SPLEPL To note
LEPL which they are unable to proceed in this issue.
2 Wage Register, Master Roll, During scheduled inspection Wage and Master roll register was SPLEPL / SIL committed that the same will be submitted by 14.02.2020 SIL 14.02.20
not found. MDM

3 Submission of PUC. MDM enquired about PUC of vehicle which is due till date. MDM/SP SIL committed that the same will be submitted by 12.02.2020. SIL 12.02.20
LEPL

4 Display of Minimum Wages MDM mentioned that minimum wages as per Govt. norms is MDM/SP SIL committed that the same will be submitted by 13.02.2020 SIL 13.02.20
not properly displayed by SIL LEPL

5 RTO/ Authorisation MDM enquired about the issue which is due since 25.01.20 ( MDM SIL mentioned that they will be able to submit the Chassis number only by SIL 14.02.20
registration no/ Equipment Ref. MOM ESGRM - 01). 14.02.20.
Chassis no. MDM expressed their disagreement on the commitment of SIL and mentioned
that all the statutory submittals as per RTO has to be submitted by SIL.

6 Fitness certificate of Vehicle MDM enquired about fitness certificate of vehicle as per MDM/SP SIL requested some time for submission of the same. In this regard they will SIL 15.02.20
standard norms , which is due till date. LEPL share a status update on submission of the same by this week.

7 Tax token certificate MDM enquired about tax token certificate of vehicle as per MDM/SP SIL mentioned that this documents might not be required as the vehicles are SIL To note
standard norms . LEPL running only within the project boundaries.
In this context SPLEPL mentioned that if SIL is confident about the legal
parameters of that , then they should confirm the same by writing .
PM mentioned that they will consult with their legal department and update
the status before next meeting.

Issued On: 12-02-2020 Page 2 of 4


MASTERS

Raised Action
Sr. No. Subject Points/Issues Raised Comments and Decisions Date Remarks
by by
8 Dismantling and Re SIL mentioned that they are facing difficulties in dismantling the SIL It is agreed that SIL will provide a alternate location for construction of labour SIL 28.02.20
Construction of existing labour existing labour camp as a gang of labour ( engaged in Grand camp to the labourers already staying in a portion of said labour camp.
camp One) is still there occupying a portion of the labour camp. However SIL committed that dismantling work will be started from 11.02.20
and reconstruction of the labour camp will be completed by 28.02.20.

9 Toilet Facilities MDM enquired about installation of toilet facilities at site as MDM/SP SIL mentioned that only urinal facilities will be arranged by them for labourers. SIL 14.02.20
committed by SIL in last meeting and due since 07.02.20. SD LEPL No latrine facilities will be there for labourers/ workers, but vehicle will be
mentioned that this issue to be resolved on priority basis. available at site for 24hrs for the need as and when necessary . SIL agreed to
set up a bio toilet block for use of SIL/MDM/SPLEPL staff at site. SIL also
agreed to complete the aforementioned toilet set up within 14.02.2020.

10 Sprinkling of water for dust MDM expressed about the dust control by sprinkling of water MDM/SP SIL mentioned that water will be sprinkled to those area which are related to SIL To note
control in the construction and adjacent area should be done regularly. LEPL Sunshine One project only. They are not ready to sprinkle water on Birla
Road.

11 Schedule for Celebration of MDM enquired about the celebration schedule of safety day. MDM/SP SIL committed that they will share the same 07 days prior to the event. SIL 26.02.20
National Safety day. LEPL

12 Fire Mock drill MDM enquired about conducting of Fire mock drill. MDM/SP SIL mentioned that this should be conducted once in three months. The 1st SIL 04.03.20
LEPL one will be conducted during safety week.

13 Hospital Tie up Certificate MDM enquired about Hospital tie up certificate which is due till MDM/SP SIL intimated that they have already applied for that and confirmation on the SIL 12.02.20
date. LEPL same is expected on 12.02.20

14 Health Check up MDM reminded SIL for health check up labours on regular MDM/SP SIL intimate that this should be conducted once in three months. This first SIL To note
basis. LEPL check up will be conducted during safety week.

15 Safety Helmet quality is not up MDM raised the issue that the quality of safety helmets issued MDM SIL agreed to take necessary measures on this on priority basis. SIL Immediate
to the mark. to the labourer/worker by SIL, is not up to the mark. MDM
asked SIL to take immediate action on this.

16 Hard barricading of Steel Yard SD highlighted that hard barricading is not proper in the Steel MDM SIL accepted that agreed to take action on the same on priority basis. SIL Immediate
yard .

17 Steel Scrap Yard MDM enquired about setting up of dia wise steel scrap yard/bin MDM SIL accepted that agreed to prepare dia wise scrap yard/bin on priority basis. SIL Immediate
and asked SIL to take immediate action on this.

18 Back horn of TM MDM mentioned that the TM in operation at site has not MDM PM accepted that and mentioning the same as a matter of great concern SIL Immediate
equipped ith back horn facilities and asked SIL to take Action in assured that necessary measures will be taken on priority basis.
this regard.

Issued On: 12-02-2020 Page 3 of 4


MASTERS

Raised Action
Sr. No. Subject Points/Issues Raised Comments and Decisions Date Remarks
by by
19 Illumination at site MDM mentioned that illumination in 2A block project site is MDM SIL accepted that assured necessary measures on priority basis. SIL Immediate
inadequate and need improvement on priority basis.

20 Gas cylinder test certificate MDM enquired about the statutory submittals of test certificate MDM SIL accepted their delay. They have assured necessary measures on this on SIL Immediate
and consumer registration of gas cylinders. The issue is pending since 25.01.20 ( Ref. priority basis.
certificate of LPG cylinder MOM of ESGRM 01)

21 Signage & Tags MDM mentioned that project name to be clearly printed to all MDM SIL accepted that. SIL Immediate
the Signage's and Tags displayed/ used at site .

22 Pest & Vector Control MDM/ SPLEPL asked SIL to do pest and vector control on MDM/SP SIL accepted committed that agency will be appointed on urgent basis SIL Immediate
regular basis LEPL

Circulation to:
1 All participants

Notes To Recipients:
1 Departments & individuals are expected to implement any action as noted.
2 This minutes record the true understanding of the concern and intended action rising there from. Your agreement that the minutes form a true record of the discussion will be assumed unless adverse comments are received in

Issued On: 12-02-2020 Page 4 of 4