You are on page 1of 16

An interpretation of ground movements recorded during construction ofbthe

Donkin-Morien tunnel

DJAppolonia Consulting Engineers, S.p.A., Genoa, Italy


P. K . KAISER
Geomechanics Research Centre, Laurentian University, Sudbury, Ont., Canada P3E 2C6
AND
N. R. MORGENSTERN
Department of Civil Engineering, University of Alberta, Edmonton, Alta., Canada T6G 2G7
Received August 8, 1990
Accepted December 27, 1990
A tunnel excavated by a tunnel boring machine was monitored extensively by means of extensometers installed near
the tunnel face. Consequently, the three-dimensional state existing at the time of installation must be considered for
the interpretation of the monitoring data. Results from three-dimensional finite element simulations are used to back-
calculate rock mass strength and deformation properties. The purpose of this study was to establish and test various
approaches of back-analysis. Results are compared with field and laboratory measurements. On the basis of these analyses,
the paper provides guidance on how field data can be used for back-analysis purposes even when the ground behaves
in a nonelastic manner.
Key words: tunnelling, monitoring, tunnel boring, back-analysis, nonlinearity.
:.
Un tunnel percC au moyen d'un appareil tunnelier a CtC instrument6 de faqon ClaborCe au moyen d'extensombtres
installis prbs de la face du tunnel. En consequence, 1'Ctat tridimensionnel prCvalant au moment de l'installation doit
Ctre pris en consideration lors de l'interprktation des donnCes de mesure. Les risultats d'une simulation tridimension-
nelle en ClCments finis sont utilises pour calculer a rebours les propriCtCs de resistance et de deformation du massif
rocheux. Le but de la prCsente Ctude etait d'etablir et de verifier diffkrentes approcheg d'analyse a rebours. Les rksultats
sont comparCs avec les mesures en laboratoire et en chantier. Sur la base de ces analyses, l'article fournit des indica-
tions sur la f a ~ o nd'utiliser les donnees de chantier pour les fins de l'analyse rebours m&melorsque le sol se comporte
dans un etat non-Clastique.
Mots clks : percement de tunnel, mesure, forage de tunnel, analyse a rebours, non-1inCaritC.
[Traduit par la redaction]

Can. Geotech. .I.28, 239-254 (1991)

1. Introduction Over the past decade, much effort has been expended to
The mine access tunnels for the Donkin-Morien coal mine develop methods to back-analyze ground properties from
in Cape Breton Island, Nova Scotia, Canada, comprise a . monitoring data and numerical computations (e.g., Gioda
tunnel excavated by drilling and blasting (tunnel No. 3) as and Maier 1980; Sakurai and Takeuchi 1983). However,
well as a TBM-driven circular tunnel (tunnel No. 2) that was there is still only a limited rational framework for tunnel
built between January 3 and December 21, 1984. Excavation monitoring and data interpretation.
proceeded northward from the portal on Cape Perce to inter- A series of guidelines for tunnel monitoring have been
sect the harbour coal seam about 3.5 km offshore. The tun- provided by Pelli et al. (1990), based on extensive three-
nel was driven to a maximum depth of 200 m below the dimensional finite element simulations, and by Kaiser (1991).
seabed in layered sedimentary rock of Carboniferous age, These include recommendations on the number of instru-
dipping 10" toward the north. A relatively extensive ments in an optimal array, anchor point spacing, orientation
instrumentation program, funded by CANMET (Canadian relative to principal stress axes, and location of initial read-
Centre for Mineral and Energy Technology), was under- ing as well as frequency of recording. In the same study,
taken t o document the tunnel performance. some indications on how field measurements can be used
In this paper, some of the monitoring data collected dur- in the back-analysis process to determine rock mass prop-
ing the excavation of the TBM-driven tunnel are analyzed. erties were given.
The purpose is to demonstrate how field measurements col- The findings of the numerical investigation are applied
lected during tunnel construction can be used t o back- in the following to some data from the Donkin-Morien tun-
analyze the mechanical properties of the rock mass to update nel and it is demonstrated how various methods of data
design parameters and t o assist on-going monitoring based interpretation can be used and implemented in tunnelling
decision making. practice.
In present tunnelling practice, measurements collected
during tunnel excavation are generally used for empirical 2. Project description
assessment of the tunnel performance and are largely based A longitudinal section of the Donkin-Morien tunnel No. 2
on the observation of displacement magnitudes and rates is shown in Fig. 1. The tunnel was driven with a 7.6 m diam-
of deformation (Bieniawski 1984). eter full-face, shielded LOVAT M-300 TBM (Marsh et al.
Prin~edin Canada / Imprime au Canada
CAN. GEOTECH J. VOL. 28, 1991 , r \ i

Chainage: Om 1300m . 3580m

Atlantic Ocean Harbour Coal S e a m

portal Sandstone Unit L~unnel

500
Scale, m
FIG. 1. Longitudinal section through tunnel No. 2 (after Yuen et al. 1987).

TABLE
1. Parameters obtained by laboratory and field testing (summarized from Yuen
et al. 1985)

Laboratory tests

0, (MPa) E (GPa)
Field tests,
Rock type Range Mean Range Mean E (GPa)

Sandstone 45-145 94 14-44 34 8-28


Interbedded
sandstone-siltstone 48-153 121 6.6-22 17.6 -
Siltstone 14-69 54 4.5-25 11.3 j b -
Interbedded
siltstone-mudstone 15-63 36 4-15 9 -
Mudstone 31-42 37 8.8-15 11.5 -
NOTE: u,, uniaxial compressive strength; E, deformation modulus.

1986) in a 30 m thick unit of competent sandstone up to as high as 28 GPa, whereas further from the wall an almost
chainage 1300 m. The remainder was excavated in weaker constant modulus of about 10 GPa was obtained.
mixed sediments consisting of sandstone, siltstone, and The data relevant to the present discussion are sum-
mudstone. marized in Table 1. A Poisson's ratio of 0.25 (mean value)
2. I Support was measured for the sandstone. The laboratory testing pro-
The support was designed for the purpose of sustaining gram revealed relatively high uniaxial compressive strength
the thrust load from the TBM as well as gravity loading for the (portal) sandstone and for the interbedded sandstone-
siltstone. The siltstone, the interbedded siltstone-mudstone,
owing to loose rock at the tunnel crown (Yuen et al. 1987).
and the mudstone were much weaker. In the field, loosening
It is composed of steel ribs (W150 x 23), spaced at 1-1.5 m
at the tunnel crown was observed in the mixed sediment sec-
along the entire length of the tunnel, connected by longitudi-
tions. In terms of deformability, the sandstone was found
nal thrust blocks. Wire mesh was also installed above the
to be more than three times stiffer than the siltstone, inter-
springline to provide support to any loosened rock fragments
bedded siltstone-mudstone, and mudstone. The in situ
for safety during tunnel drivage. The support rings were
dilatometer tests performed in the sandstone unit yielded
expanded behind the tail of the TBM at one diameter from
the tunnel face. Since the liner is very flexible and placed lower Young's moduli than the values obtained in the labo-
far from the tunnel face, its effect on the deformational ratory. This difference was expected, because the rock defor-
behaviour of the ground was neglected in this study. The mability is known to increase as the volume of the rock
field measurements confirm the appropriateness of this tested increases. These results are in agreement with Heuze
assumption. Significant loads were only detected in those (1980) who found that the elastic moduli measured in the
sections where loosening occurred at the tunnel crown and laboratory are two to three times larger than those in situ.
caused gravity loading ( ~ u e net al. 1985).
2.3 In situ stresses
2.2 Rock properties An in situ stress measurement program was conducted in
Laboratory and field tests provided length and deforma- the parallel tunnel by means of two overcoring techniques,
tion properties for the various rock types. The field testing using the CSIRO hollow inclusion cells and the USBM defor-
program included in situ modulus measurements (by means mation gauges. Because of technical problems (Yuen et al.
of the Colorado School of Mines dilatometer) in a horizon- 1985) the horizontal, radial stress at the springline was
tal, 42 m long borehole drilled in the sandstone from a measured at only two locations. One was relatively close to
parallel tunnel (tunnel No. 3). Within one radius from the the tunnel wall and, hence, affected by the excavation. More
tunnel wall, a stiff zone was detected with modulus values extensive and accurate stress measurements would have been
PELLI ET AL. \
, ,

FIG. 2. Section through tunnel with radius a = 3.8 m and horii:ontal extensometer placed at chainage 800 m (modified from Yuen
et al. 1985). Scale 1:400.

very beneficial to the back-analysis process. A vertical,


minor principal stress consistent with the tunnel depth
(u, = 5 MPa) and a moderately high horizontal stress Field Data
(KO = uh/uv = 2) were interpreted. In agreement with the \, E l a s t i c i t y Theory

measured KOvalue, extensive stress-induced loosening was


observed at the tunnel crown in the mixed sediment section.
2.4 Monitoring program
The instrumentation program included strain gauges and
pressure cells on the supports as well as radial multipoint
extensometers installed at various distances from the tunnel
face. Only the latter will be discussed in the following
sections.
One multipoint extensometer was placed at each instru-
mented section (partly because of limited accessibility to the
excavation front of the shielded TBM). Whereas this helps
to detect variability, it renders a quantitative back-analysis
of the monitoring data difficult. At the invert, instruments
could only be placed one diameter from the excavation front Radial Distance ( r-a ), (rn)
immediately behind the tail of the machine. FIG. 3. Comparison between relative radial displacements mea-
sured in the field (chainage 800 m; total values) and calculated by
2.5 Extensometer locations the finite element method (radial distance (r - a ) is measured from
In the sandstone, at chainage 800 m, a rigid probe multi- the tunnel wall).
point extensometer was located in a horizontal borehole,
driven from the parallel tunnel No. 3 (Fig. 2). It provided
the only record of displacements ahead of the tunnel face analyzed. The effect of nonlinear ground behaviour is also
and in the direction of the major principal stress. These evaluated.
extensometer data are used in this paper to back-analyze the At chainage 800 m, the tunnel is contained in a thick sand-
elastic modulus of the sandstone rock mass. stone layer. The instrument was placed far ahead of the tun-
Several extensometers were placed at the tunnel crown, nel face and the complete development of deformations
in the mixed sediment section, to detect the loosening pro- could be monitored as the tunnel advanced.
cess. The data collected from these extensometers are used Two different methods of interpretation are presented.
to back-analyze the strength and the elastic modulus of the The first approach is based on the total relative displace-
mixed sediments. ments, obtained far behind the tunnel face, without con-
Monitoring data collected by instruments in the direction sidering intermediate deformation stages. In principle this
of the major and minor initial stresses are discussed sepa- method can be applied in the context of a conventional two-
rately. This is appropriate because only one extensometer dimensional approach, as it does not require a detailed
record is available for each instrumented section and dif- knowledge of the three-dimensional strain field. However,
ferent rock types generally characterize the springline (sand- as will be demonstrated, a three-dimensional perspective is
stone) and the crown (mixed sediments). necessary to explain certain phenomena that may affect the
measurements and could be relevant for an effective data
interpretation. The second approach consists of analyzing
3. Interpretation of radial displacement records in the the shape of the radial displacement curves and involves a
direction of the major principal stress sound knowledge of the near face deformation field. The
Multipoint radial extensometer and convergence measure- results obtained from these two approaches will be
ments collected at the tunnel springline (i.e., in direction of compared.
the major principal stress for KO > 1) can provide, if inter-
preted correctly, a considerable amount of information on 3.1 Effects of a compression zone on data interpretation
the rock mass properties. In this section, the monitoring data The ultimate radial displacements measured by the exten-
collected by means of the multipoint extensometer placed someter at chainage 800 m are plotted in Fig. 3 (solid line).
horizontally at chainage 800 m (Fig. 2) are discussed and Between 1.5 and 3.0 m from the tunnel wall a compression
the elastic properties of the sandstone rock mass are back- zone is found. Its effects on data interpretation have to be
CAN. GEOTECH. J. VOL. 28, 1991
1 \

S t i f f Zone

4
\

--

r
Cornpress~ve
W ~ t h o u tS t ~ f f

Ur Ur Ur
-- -- - ---

MxSflff Rrng Elements Near Wall

FIG.4. Schematic diagram for the explanation of the effect of


the radial compressive zone. I I I I I I I I I I
I 3 7 10
Radial Distance ( r-a ), ( rn)
explained before the back-analysis process can be carried
out. FIG. 5. Relative radial displacement profiles with and without
zone of stiff rock (finite element analyses; radial distance (r - a)
A possible explanation of this phenomenon is shown is measured from the tunnel wall). "
schematically in Fig. 4 where the effect of a thin stiff zone
on the radial displacements around the tunnel is illustrated.
Such a zone could be caused by a natural inhomogeneity order of 10-30 times would generate a similar response. This
or differential rock damage owing to construction. Modulus is supported by FE analyses of lined tunnels, where com-
measurements conducted in situ (section 2.2) confirmed the pression zones owing to stress concentration at the leading
presence of a stiffer zone in the proximity of the tunnel wall, edge of a thin concrete ring were detected (Pelli 1987).
although the stiffness ratio did not exceed three and the con- The most reliable data are thus provided by the measure-
tinuity of the stiffer ring around the tunnel could not be ments taken at least a few metres awav from the excavation.
verified. Back-analysis of an elastic modulus based on these data will
Various alternative causes for the radial compression zone likely result in an upper bound value, because the magnitude
were explored, both in terms of rock constitutive relation- of the displacement profile affected by a stiff ring is lower
ships and local rock damage. Two-dimensional finite ele- than that for a homogeneous rock mass. On the other hand,
ment analyses were carried out utilizing elastoplastic strain it can be observed from Fig. 5 that the differential displace-
weakening models with nonassociated flow rule and by ment between anchors located at various distances from the
simulating local damage in proximity of the tunnel wall. It tunnel wall (i.e., the slope of the curves in Fig. 5) are not
was found that nonlinear stress behaviour and local damage greatly influenced by the compression zone, provided that
could not explain the development of a radial suppression the selected anchors are far from the excavation wall.
zone in the direction of the major principal stress. On the
other hand, differential rock damage along the tunnel axis 3.2 Back-analysis of rock mass modulus from total radial
may be expected to play some role by enhancing stiffness displacements
differences. Based on three finite element analyses conducted for linear
After excavation, the stiff ring with a higher modulus than elastic, nonlinear elastic (hyperbolic), and elastoplastic con-
the adjacent rock mass causes a localized constraining effect stitutive relationships, it has been shown (Fig. 16a, Pelli
that limits the radial displacements. This effect is concen- et al. 1990) that, for KO > 1, the radial displacement pro-
trated near the wall of the tunnel and vanishes far from it. files obtained at the tunnel springline and far behind the tun-
To qualitatively substantiate this hypothesis a three- nel face are not much affected by the constitutive relation-
dimensional finite element analysis was carried out, where ship characterizing the ground behaviour. The difference in
the conditions described in Fig. 4 were modelled. Note that shape of the corresponding profiles is minor, as the effect
a conventional two-dimensional approach cannot provide of nonlinearity is mostly concentrated near the tunnel crown
an explanation. The results of the analysis are presented in and invert (i.e., in the minor principal stress direction).
Fig. 5 and show that a stiff ring reduces the radial displace- The elastic modulus of the rock mass can then be back-
ment at any distance from the tunnel wall. Most interesting analyzed by comparing the radial displacement profile
is the shape of the simulated displacement profile resembling detected in the field, with the displacements calculated by
the field measurements (Fig. 3). This observation is impor- means of the elasticity theory. In Fig. 3, the recorded dis-
tant for the interpretation of the monitoring data as its placements at chainage 800 m (solid line) are compared with
influence, if not considered properly, may lead to an under- the theoretical displacement profiles (broken lines) calculated
estimation of the deformability of the ground. Although a for E = 10 and 6 GPa (without compression zone simula-
very high modulus difference was adopted for the FE anal- tion). To allow this comparison, the calculated values have
ysis (1000 times higher modulus in 1.3 m long and 0.4 m been obtained assuming a datum 42 m away from the wall
thick stiff rock ring) to provide clear evidence of the com- of the tunnel (location of the deepest anchor). It was
pression zone effects, a much lower modulus contrast in the observed earlier (Fig. 5) that the stiff zone causes a decrease
PELLI ET AL. j

\,

FIG. 6. Radial displacement profile measured at 3 m from the FIG. 7. Radial displacement profiles measured at 7 m from the
tunnel wall fitted by FEM (E = 10 GPa; chainage 800 m). tunnel wall fitted by FEM (E = 7.5 GPa; chainage 800 m).

1
I
I
of the movement away from the excavation' For this calculated by interpretation of the radial displacement pro-
reason the calculated displacement (without stiff zone) files from chainage 800 m.
should be significantlylarger than the measured values (with In a previous study (Pelli et 1990), three-dimensional
stiff zone) and the solution with = GPa represents an numerical analyseswere conducted to investigatethe depend-
upper bound for the rock mass because it
ence of the convergence curve shape on various constitutive
provides a profile just slightly above the field data. relationships for the rock mass. Three convergence curves
A better estimate Of the rock mass can be were obtained at the springline for a tunnel in linear elastic,
obtained by considering relative displacements far from the hyperbolic, and elastoplastic rock. It was observed that the
tunnel wall where the influence of a stiff zone is less domi- curves are virtually identical up to about 0.2 radii behind
nant. The differences between the displacements measured the tunnel face and very similar up to 0.45 radii behind the
at 7 and 21 m from the wall, in Fig. 3, were con-
face as long as the elastic moduli (initial elastic modulus for
sidered for comparison with the elastic body. The relative the hyperbolic case) are Major differences only
at the anchor set can be matched with occurred relatively far behind the excavation front, where
= GPa' A 'Ornewhat higher Of = GPa high deviatoric stresses develop. This observation led to the
was obtained from the relative displacements of anchors at conclusion that, for cases where moderately nonlinear
3-21 from the but it is
(Au,(3-2~))9 behaviour is exhibited by the rock mass, the shape of the
that this modulus is not representative of the average rock initial part of the radial displacement curves can reveal the
mass deformability because of the aforementioned compres- magnitude of the elastic modulus of the rock independent
sion zone. The deformability back-analyzed by means of the of the ultimate rock mass behaviour.
displacement data interpretation is two times larger than the The radial displacement profile, measured at from
deformability determined by field pressuremeter tests. This the tunnel wall, is in Fig. 6 with a curve calculated
is expected because a much larger volume of rock is affected for the same location by a three-dimensional finite element
by the tunnel excavation than by the dilatometer. For tunnel analysis. An elastic modulus of GPa and a stress ratio
design purposes, however, the difference between these of K, = 2 were selected. The calculated curve matches the
moduli is not significant. field data well up to point A where the two profiles diverge
Unfortunately, this kind of back-analysis procedure, towards different final displacement values.
including the total displacements ahead of the tunnel face, The difference in radial displacements,detected far behind
can seldom be applied for deep tunnels because radial the face, is only in part a reflection of the difference in total
displacements are often not available. radial movement (including dis~lacementsahead of the
3.3 Back-analysis of rock mass modulus from radial face). It is also due to the fact that a considerable difference
displacement curves behind the tunnel face between the measured and predicted displacement at the face
1 The elastic modulus of the rock mass can also be back- was observed. In fact, smaller radial displacements than
CAN. GEOTECH. J. VOL. 28, 1991

FIG. 8. Radial displacement profiles measured at 3 m from the FIG.9. Radial displaceme~t'profilesmeasured at 7 m from the
tunnel wall fitted with FEM (E = 10 GPa; chainage 800 m; datum tunnel wall fitted by FEM (E = 5.75 GPa; chainage 800 m; datum
at 21 m from the tunnel wall). at 21 m from the tunnel wall).

predicted were measured at the tunnel face (see Au in insert with calculated curves in Figs. 8 and 9 for Au,0-21) and
of Fig. 6), perhaps owing to a local inhomogeneity in the Au,(~-~I), respectively. In this manner, the measurements
tunnel face (Pelli 1987). To compare the final displacements become independent of the datum. For the measurements
measured at the tunnel face with those computed, the final at 3 m from the wall, the same result as found previously,
displacement at the face must be adjusted as shown in Fig. 6 i.e., E = 10 GPa, is obtained. The rather high value
(insert) to account for the different trends ahead of the face. observed at this location can again be justified by the effect
The C line was obtained by adding to the calculated ultimate of the compressive zone detected near the wall of the tunnel.
radial movement the difference between the calculated and The relative displacements between 7 and 21 m from the
the measured displacements at the tunnel face (Au in insert tunnel wall, presented in Fig. 9, can be fitted by assuming
of Fig. 6). Note, however, that this correction can only be E = 5.75 GPa. These observations are consistent with the
applied if the movement ahead of the face of the tunnel is conclusions based on the analysis of the total radial displace-
measured. On the other hand, no correction should be ments. The modulus back-calculated at 7 m from the wall
applied to the computed displacement profile if a back- is considered to be most representative. For this reason, a
analysis based on matching the near face portion of the curve mass modulus between 5 and 6 GPa is most appropriate for
is performed, as the initial part of the curve, fitted by the the sandstone. A certain amount of nonelastic deformation
numerical results, is assumed to be independent of the occurred behind the tunnel face as indicated on Figs. 8 and 9
displacement at the face. This assumption was proven to (also observed in Figs. 6 and 7).
be correct by Pelli (1987), at least at the tunnel springline No attempts were made to fit the full radial displacement
and for KO = 2. curve by results from finite element analyses with an elastic
The same fitting procedure was then applied to the curve rock model because only the initial portion of the curve (near
at 7 m from the tunnel wall shown in Fig. 7. For this case the face) reflects the elastic properties of the medium. The
a modulus of 7.5 GPa is needed to match the initial part displacements far behind the face are affected by yielding,
of the curve. Consistent with earlier observations, a lower initial stresses, and other factors influencing the displace-
elastic modulus was found by considering measurements ments ahead of the tunnel face (Pelli et al. 1990).
taken far from the wall of the tunnel (and far from the com- Although the two interpretations lead to similar results
pressive zone). These results, however, are not in agreement for the Donkin-Morien tunnel, the authors are more confi-
with the analysis of the total displacements, leading to the dent in the second approach using the gradient of the dis-
conclusion that the elastic modulus of the rock mass should placement profile. It should be adopted whenever possible.
be lower than 6 GPa (see previous section). Near the face, only a limited amount of yielding may have
Better agreement was achieved by subtracting the displace- developed and the elastic properties of the medium stilI
ments measured at a depth of 21 m from the displacements dominate. Furthermore, the elastic modulus can be back-
at 3 and 7 m from the wall, respectively. They are compared calculated without knowing the displacement at the tunnel
PELLI ET AL. i 245
i

9 9 m , n.161

0 20 40 60 80 100 120
x (rn)
FIG. 11. Predicted radial displacement-profiles for chainage
800 m at 3 m from the tunnel wall for variable n and x, =
5-25.2 m.
0 20 40 60 80 100 120
convergence. For more information on the meaning of these
x (rn) parameters the reader is referred to Richard and Abbott
FIG. 10. Radial displacement profile measured at 3 m from the (1975). - -
tunnel wall (chainage 800 m) and fitted with Ramberg-Osgood The parameter n is important for defining the shape of
functions (n = 1.2-2). curves having the same initial gradient. For such cases a
lower n value corresponds to a flatter curve and it can be
face. This aspect is of considerable practical importance for used to quantify the difference in shape. 1n ~ i 10,~ the.
deep tunnels. radial displacement profile measured at 3 m from the tunnel
This back-analysis also illustrates that convergence face is compared with three Ramberg-Osgood curves. The
measurements alone may lead to erroneous results as they closest correspondence was obtained for n = the
are very sensitive to local effects (such as the compression linear elastic model, n = 2 fits best. This indicates that the
zone detected at Donkin-Morien). rock mass is affected by a certain amount of nonlinearity
and is in agreement with the detection of the nonelastic
3.4 Prediction of radial displacements by curve fitting deformations indicated in ~ i 8 and ~ 9.~ .
he numerical analyses revealed that the shape of the he ~ ~ ~ b function
~ ~can also
~ be- usedOto pre-
~ ~ ~
radial displacement curves is a valuable indicator of the rock dict the final radial displacement, based on the initial part
mass ~ r o ~ e r t i eIn
s . particular, flatter displacement profiles of the displacement profile. This feature can be very useful
are found if the rock exhibits a nonlinear stress-strain rela- because it may allow for a rapid evaluation of field data
tionship. To quantitatively evaluate the shape differences without having to wait for the tunnel face to be far ahead
of the radial displacement profiles, a fitting procedure by of the instrumented section. The procedure presented by
means of an appropriate analytical function was applied. Desai and Wu (1976) may be used to determine u, and n
he analytical function developed by Ramberg and Osgood 0. the basis of the initial gradient and two known points
(1943) in the form given by Desai and Wu (1976) was f ~ u n d on the curve. Desai and Wu (1976) also provide a simple
to match the displacement profiles given by convergence computer program to solve this problem by means of an
points and radial extensometers installed at the tunnel face iterative algorithm.
reasonably well. The function is defined by the initial slope, This method was applied to the radial displacement pro-
s,, and the slope of the final tangent, Sf, the intercept, UO, file measured at 3 m from the wall to verify its ability to
of the asymptote at x = 0, and a shape factor, n (see inset predict the radial movement, for various distances of the
in Fig. 10). It can be expressed as follows: tunnel face from the instrumented section (Fig. 11). A hor-
(Sl - Sf)x izontal asymptote (Sf =0) was assumed and each curve
[I] u r = ( ~ l - ~ f ) x ( l + l uo I~)-'"+S~~ was forced to pass through the last available measurement
(at x,) and one intermediate point. For instance, the first
Low n values indicate slow convergence to the asymptote prediction was made assuming the first 5 m of the radial
and large radii of curvature. Rapid slope variations are displacement curve to be known (x, = 5 m). The two
associated with high n values. For n = 1 the Ramberg- points selected were at x = 2.5 and x = x, = 5 m from
Osgood function degenerates to a hyperbola. Sf can be the tunnel face. When the face is situated at 5 or 9.9 m from
assumed to be zero (horizontal asymptote) for time- the instrumented section, relatively high n values, close to
independent problems, i.e., u, is directly related to the final those suitable for linear elastic conditions, are predicted.
246 CAN. GEOTECH. J. VOL. 28, 1991 j

1 4 '

A back-analysis of the in situ stress field is not possible


because of insufficient data at each section. The displace-
ments should have been measured at various locations
around the tunnel to allow for an effective back-analvsis
process. In particular, measurements taken at the tunnel
crown are known to be strongly affected by the virgin axial
stress pa (Pelli et al. 1990) whose magnitude is not accu-
ratelv known for this case. Failure observed at the tunnel
crown and invert indicates a relatively high horizontal stress,
ph, consistent with the field measurements. A constant
KO = 2 was selected for the purpose of the following
discussion.
4.2 Back-analysis of rock mass strength
To back-analyze the peak strength of the rock mass, the
in situ stresses and the location at which the strength of the
rock is exceeded must be known. The distance of the failure
initiation point from the tunnel face can, for example, be
detected by extensometers installed at the tunnel face. How-
ever, if the location at which the strength of the rock mass
is exceeded cannot be identified, only very general conclu-
FIG. 12. Predicted radial displacement profiles for chainage sions can be drawn. Examples of both situations will be pre-
800 m at 3 m from the tunnel wall for n = 1.2 and x,,,= sented in the following discussion.
5-25.2 m).
4.1.1 Strength from extensometer results
The relative displacement profile far behind the tunnel
This is in agreement with the observation that the initial part face, as measured by the vertical multipoint extensometer
of the curve reflects the elastic properties of the medium. located at chainage 2263.m, is depicted by Fig. 13a. This
As the face of the tunnel continues to advance, the n value instrument is located in the interbedded mudstone-siltstone
decreases and at less than two radii (x, = 12.24 m) from (up to 2 m from the wall), coal (up to 3.6 m), mudstone,
the excavation front a good prediction of the final displace- carbonaceous mudstone, and interbedded sandstone-
ment is obtained. The gradual departure from the linear siltstone. Most of the movement occurs within 2 m from
elastic conditions can be detected in this manner, as the the tunnel and a relatively high radial displacement of
excavation proceeds, by several sequential back-calculations 25 mm is found at the crown of the excavation. A sudden
of n. This is useful in practice because it allows to detect change in curvature, between 1 and 1.4 m from the tunnel
yielding conditions and permits to respond rapidly to unex- wall, indicates the thickness of the loosened rock zone. The
pected rock conditions. The n value characterizing the radial displacement curves measured by this extensometer
displacement profile can then be used for movement predic- are plotted in Fig. 14 against the distance from the tunnel
tions in other similar sections by forcing the curve to pass face. The deepest anchor depth has been chosen as the
through the last measurement. The results obtained by this datum. From this figure, the location at which failure
procedure are shown in Fig. 12, where it can be observed occurred can be identified (indicated by the arrow labeled
that a reasonable estimate can be provided based on the "loosening"). Relatively small displacements take place in
initial 12 m of the curve if the n value is correctly predicted. the rock within 14 m (3.7 radii) from the tunnel face, then
failure occurred and affecting the rock between 1.0 and
4. Interpretation of radial displacement records in 1.4 m. Note that only a portion of the siltstone unit below
direction of minor principal stress the coal failed.
The radial displacement records detected in the direction The relative radial displacement profile far behind the
of the minor stress can reveal the strength and deformation face, as measured by the multipoint extensometer at chain-
properties of the rock mass. In the following sections, the age 3205 m, is presented in Fig. 13b. This extensometer is
data collected by means of the multipoint extensometers are simulated in siltstone and interbedded sandstone-siltstone
discussed and the strength and deformational properties of up to 5.8 m away from the tunnel wall. In this case, the
the mixed sediments are back-analyzed. thickness of the mobilized zone is deeper but does not exceed
All extensometers considered here were placed immediately 3 m. Again, a relatively large displacement of about 40 mm
behind the tunnel face (between 0.25 and 1 m from the face). is detected at the tunnel wall. This curve flattens gradually
One of them was a rigid probe type, whereas the remainder and does not reveal the thickness of the loosened zone by
were flexible probe extensometers equipped with a large a sudden change in gradient. The radial displacement curves
number of anchors. Zero readings were taken at the face given by the extensometer at chainage 3205 m are shown
after installation and, because of the lack of access owing in Fig. 15. Again, failure occurred far from the tunnel face
to the shield of the TBM, no readings could be taken within (at about 14.5 m) and a considerable amount of loosening
one diameter from the excavation front. Therefore, the can be observed. The broken zone propagated to more than
shape of the radial displacement curves is not available near 2 m and is approximately twice as thick as for the previous
the face and the otherwise preferred method of data inter- case.
pretation proposed by Barlow (1986) and Barlow and Kaiser If the same initial stresses can be assumed to exist at
(1987) could not be applied. chainages 2263 and 3205 m, the rock at these two locations
PELLI ET AL. 247
\

(a) Extensometer 2T 2263 E A


10
----

A 8 - E-m
-E

z2 6-
----
XI
U ----
w
> (.,
0
n P
a
w 4 - ----
U
C
0
C
(.) I D A
.-U) \ Phalen Seam
n 1
2-l+----
TZL
0 4\_
I - I I
20 40 60 80
Displacement ( Downward )
(mm)

4
(c) Extensometer 2T 1428 E A

Displacement ( Downward) Displacement ( Downward)


(rnrn) (rnm

FIG. 13. Measured radial displacement profile (relative to deepest anchor) at (a) chainage 2263 m; ( b ) chainage 3205 m; ( c ) chainage
1428 m; and (d) chainage 2996 m (after Yuen et al. 1985). I, sandstone; 11, interbedded sandstone-siltstone; 111, siltstone; IV, interbedded
siltstone-mudstone; V, mudstone; VI, carbonaceous mudstone; VIA, coal.

must have failed under similar load conditions and the uni- The stress distribution near the tunnel face was determined
axial rock mass compressive strengths for the siltstone by means of three-dimensional numerical analyses and by
(chainage 3205 m) and the interbedded mudstone-siltstone assuming linear elastic rock. This assumption is reasonable
(chainage 2263 m) can be quantified. However, the stress for rocks that exhibit a brittle behaviour as evidenced by
concentration in the crown must be estimated first. the observed, sudden failure initiation. For cases where a
248 CAN. GEOTECH. J. VOL. 28, 1991
,

s _ _ - -,---
-
$?!!-------
,'

,--

Loosening :
-; m/-/------
----
o:? - -
,'
I
--
,-
I I
r I
I
, ,
I

2
.- ,.' , I

- Y
.P
.=C 1
; ,

, \.op-----------
,----

- ,' *. _ r e

2 ; ," ,----
-
? I , '
.- :
2 ;,,' ,; ; ------- _ _ - -
\,4? - - - - - - - - - - - , - - - -
I ,
,' t
: ,,, ;
::
I
, ,/
' I

,, ,,-,
# I
t I

;; ,,,' ----
1.9-m..-_-.._..-
;;; ,, ----
,-----
; ;I /,

1 (:I
IS,, ,
,__;
;;; ,/' n ~2:.9tl-~.~;~~
.=--==.--.------
/&&' _----.-
*<-.-.. ----
4.9m-5.7m
I I I I I

FIG. 14. Measured radial displacement profiles for the crown FIG. 15. Measured radial displacement profiles for the crown
at chainage 2263 m (relative to the deepest anchor; extensometer at chainage 3205 rn (relative to the deepest anchor; extensometer
installation at the funnel face) (after Yuen et al. 1985). installation at the tunnel face) (after Yuen et al. 1985).

considerable degree of nonlinearity is expected in the pre-


peak range, the linear elastic assumption may lead to 1990). The uniaxial compressive stress of the rock mass a,,
unrealistic stress predictions as discussed by Santarelli et al. and the uniaxial compressive strength measured in the lab-
(1986) and Santarelli and Brown (1987). Also, heterogeneities oratory a, can then be related for a3 = 0 as follows:
and anisotropy of the rock deformation properties can cause 1
stress concentrations around the tunnel that may dominate. [3] a,, = (s 037
The tangential stresses at the tunnel crown, as obtained where s can vary between 1 (intact rock) and 0 (heavily
by a three-dimensional finite element analysis, are plotted jointed or broken rock). Substituting a, with the value
in Fig. 16 against the distance from the tunnel face. The found for the siltstone by laboratory testing (Table 1, mean
stresses have been obtained for KO = 2 and are normalized values) and a,, with the tangential stress value back-
with respect to the vertical stress. The distance from the face analyzed above:
is normalized with respect to the tunnel diameter. For the
two cases discussed above, failure initiation took place at
about 1.9 diameters behind the face of the tunnel where,
as indicated in Fig. 16 (point A), 98% of the ultimate the parameter s applicable to chainage 3205 m can be
tangential stress has been reached. This implies that, for the calculated as s = 0.21. For a power of less than one-half,
cases considered here (chainages 12263 and 3205 m), failure a lower s would be back-calculated.
occurred at a tangential stress of about 24.5 MPa. This stress According to Hoek and Brown (1988), an undisturbed silt-
must correspond to the uniaxial compressive strength of the stone rock mass of very good quality with tightly interlock-
rock mass. ing rock and unweathered joints at 1-3 m spacing ( Q = 100
The strength of the rock mass can be described, for or RMR = 85) is to be represented by an s value of 0.189
instance, by the failure criterion proposed by Hoek and and rn should be in the order of 5.85. If the rock was
Brown (1980a, 1980b): disturbed, for example, owing to stress concentrations in
1 the crown, the corresponding recommended s and rn values
[2] al = a3 + (rn aca3 + s a z ) ~ are 0.082 and 3.43, respectively. The recommended values
where al and a3 are the maximum and the minimum (effec- for the range of Q = 100-0.01 are presented in Fig. 17 by
tive) principal stresses, a, is the uniaxial compressive solid and empty squares.
strength of the intact rock, s and rn are empirical param- Considering the state of stress with relatively low confin-
eters, and the power is commonly assumed to be one-half. ing pressure near the tunnel wall and the curvature of the
Recent work has shown that the power in [2] may, within Hoek-Brown failure criterion in this range, the back-analyzed
the stress ranges encountered near underground openings, s value of 0.21 seems to represent an upper limit for the con-
be as low as one-third (E. Hoek, personal communication, ditions encountered at Donkin-Morien.
ET AL. 249
J I \,

Hoek & Brown (1988) for


Undisturbed Rock

FIG. 16. Normalized tangential stresses at the tunnel crown as I* Hoek & Brown (1988) for
Disturbed Rock I
predicted by a three-dimensional finite element analysis (linear
elastic, KO = 2).
* FS=I i

0, K=2 and Ocm =53.6MPa

A- FS=I 3, K=2 and Cicm=53.6MPa


For a given s value, m can then be back-analyzed by
"A- FSz1.3, K=2 5,CTcm =53.6MPa
considering the extent of the failed zone as detected by the
multipoint extensometer. For this purpose a simple two- -*, FS=f 3, K=2 and Ocm=24.5MPa
dimensional stress analysis was applied. Although this
( J ~ ~uniax~al
= compressive strength
approach does not simulate progressive failure or the post-
peak behaviour of a rock mass, it can be used as an approx-
imation in conditions where yielding is not excessive. FIG. 17. Hoek and Brown parameters (m,s) according to 1988
A series of two-dimensional plane strain numerical anal- recommendation and values back-analyzed for FS = 1 and 1.3.
yses were carried out using the boundary element program
EXAMINE^^. The code performs a stress analysis, assuming Failure in the field was only observed in the crown and
a linear elastic constitutive relationship for the medium and parameters falling outside the shaded area in Fig. 17
compares the calculated state of stress with the strength given representative for a continuous yield zone (e.g., Fig. 18b
by the Hoek-Brown failure criterion. A safety factor is com- with FS = 1.3 at the failure zone limit of 1.5 m depth) are
puted as a measure of the proximity of the stress state to clearly not realistic.
the failure envelope. Experience from similar applications Figure 17 confirms the earlier conclusion that s = 0.21
in mining suggests that the factor of safety contour at 1.3 with an intact rock strength of 53.6 MPa and KO = 2
represents a good approximation of the yield zone boundary represents an upper limit for the siltstone as it cannot be
in moderately yielding ground. Hence, the parameters used to reproduce failure to a depth of 1.5 m (unless m = 0).
matching the extent of the failed zone detected by the exten- Guided by the fact that yielding was localized in the crown
someters were determined for FS = 1.0 (ignoring stress and not continuous around the tunnel, the best-fit (m, s )
redistribution) and FS = 1.3. value pairs determined by this back-analysis procedure fall
The resulting (m, s ) pairs are also plotted on Fig. 17 in the ranges of 0.01 < s< 0.08 and m 5 0.75. These
together with the s-m pairs recommended by Hoek and values are far outside the range recommended by Hoek and
Brown (1988) for disturbed and undisturbed rock masses Brown (1988) (Fig. 17 curves with solid and empty squares).
(solid lines with solid and empty squares, respectively). The Correspondence between back-analyzed and recommended
corresponding rock mass quality Q values are indicated near values would only be possible for 0.0001 < s < 0.05 and
the curves. The remaining four curves presented in Fig. 17 0.5 < m < 1.35. The rock quality of the essentially
refer to the boundary element analyses conducted for various undisturbed rock mass was determined by Golder Associates
assumptions, as listed in the legend, and indicate s-m pairs to range from Q = 1.3-7 leading to 1.5 < m < 2.5 and
compatible with the extent of the plastic zone observed in 0.0003 < 5 < 0.01. Hence, the back-analyzed ranges do
the field. Note that only the points falling in the shaded area clearly not agree with the recommended values.
(upper left side of Fig. 17) correspond to a discontinuous These findings can be extended to the interbedded
yield zone. The shaded area thus indicates the range of siltstone-mudstone formation located at chainage 2263 m.
parameters for which a discontinuous yield zone (at floor With a mean compressive strength of 35.8 MPa, determined
and roof but not at springline), as observed in the field, is in the laboratory, s = 0.47 is obtained from [3]. With ref-
predicted. The factor of safety contours for three parameter erence to Fig. 17, where extreme strength values have been
sets ( m ,variable; s = 0.015) are presented in Fig. 18 considered, it can be concluded that the discontinuous nature
(KO = 2.5 in Fig. 18a, and KO = 2 in Figs. 18b and 18c). of the yield zone can again not be reproduced.
250 CAN. GEOTECH. J. VOL. 28, 1991
\

FIG. 19. Measured radial displacement profiles for the crown


at chainage 2996 m (relative to deepest anchor; extensometer
installation at tunnel face) (after Yuen et al. 1985).

Factor of Safety tions. In Fig. 13c, the strata in the proximity of chainage
1428 m is shown. A 21 m long rigid probe extensometer,
FIG. 18. Factor of safety contours for two (m,s) parameter equipped with four anchors (including head), was installed
pairs: (0.33, 0.0015) and (0.75, 0.015) for KO = 2 and (1.25, at the tunnel crown, immediately behind the face. Even
0.015) for KO = 2.5.
though the tunnel is completely contained in a thick siltstone
layer, a coal seam is located only 1 m above the crown. Sur-
Back-analyzed m and s values depend on many parameters ficial loosening and spalling was observed at this location
such as the stress ratio and intact rock strength. The effect and considerable downward displacements were measured.
of these two parameters on m and s is illustrated in Fig. 17 A very large radial displacement of almost 80 mm was
by the back-analyzed parameter pairs for FS = 1 and 1.3, detected at the tunnel wall. The radial displacement curves
KO = 2 and 2.5, and a,, = 53.6 and 24.5 MPa. These s plotted in Fig. 23 show that failure in the siltstone took place
and m values are only valid for a power of one-half in [I]. at a much earlier stage than for the two cases discussed pre-
Considering the sensitivity of m and s to variations in these viously. At the back of the shield, failure had already
parameters, it is obvious that there is a high degree of uncer- occurred and a significant amount of loosening was revealed
tainty in the back-analyzed strength parameters. Neverthe- by the large gap between the displacements measured at the
less, we conclude that these parameter values clearly differ wall and at 3 m from the excavation. Because of a lack of
from the values recommended by Hoek and Brown (1988) measurements near the tunnel face, the location at which
in that 0.01 < s < 0.2 with a corresponding range for m of the strength of the rock was exceeded is unknown. The
0.2 < m < 1.5. Many more back-analyses of this type are reason for early failure is found in the relatively low stiff-
needed to establish practically meaningful rock mass ness of the coal causing a high stress concentration in the
strength parameters for tunnel design. Despite the many thin siltstone layer at the crown of the tunnel. In section 5.2,
uncertainties and practical limitations associated with the it will be confirmed by the elastic modulus back-analyzed
back-analysis of rock mass strength parameters, the impor- for chainage 1428 m that the coal is highly deformable
tance of applying back-analysis procedures to validate and relative to the siltstone.
improve the Hoek-Brown failure criterion cannot be over-
4.1.3 Effects of low-strength rock at the tunnel crown
emphasized. This work also identified a need to reevaluate
The stratigraphy in the tunnel crown near chainage 2996 m
the assumed power in [I] for application in low confinement
is depicted in Fig. 13d. A flexible probe extensometer was
areas close to underground openings.
installed at the tunnel crown, immediately behind the face
4.1.2 Influence of inhomogeneities of the tunnel, in a 5.5 m thick layer of interbedded
For certain conditions, inhomogeneities in the rock mass siltstone-mudstone. Surficial loosening at the crown, within
must be considered because they may cause stress concentra- a 60" arch, was observed. From the radial displacement pro-
PELLI ET AL.
,i h 25 1

FIG. 20. Axial stresses at the tunnel crown as predicted by a


three-dimensional finite element analysis (linear elastic, KO = 2).
FIG. 21. Partial radial displacement profiles at the tunnel
crown predicted by two three-dimensional finite element analyses
file in Fig. 19, a considerable radial displacement of more (elastic and elasto-plastic; extensometer igstallation at the tunnel
than 40 mm is detected at the wall owing to loosening. face).
As opposed to chainage 2263 m, where the interbedded
siltstone-mudstone failed at about 14 m from the tunnel laboratory strength (35.8 MPa), an value of approx-
face, in this case, failure has already occurred immediately imately 0.2 is also found for this location.
behind the of the TBM (point A in Fig' 19) and a In this section, an attempt taback-analyze the rock mass
loosened a ~ ~ r O x i m a Oe5
tel~ is revealed the strength has been presented by studying the
gap between the measurements at Oe4 and 0.8 m. As the face of failure initiation at the crown of the tunnel. Such
of the tunnel advances, the tendency of tangential stress to studies are essential to confirm the recommendations of
'Oncentrate near the of the causes further Hoek and Brown (1988). However, the task is very complex
propagation of failure. At about two diameters behind the and the results are sensitive to many assumptions such as
face the (point in Fig. 19) portions the in state of stress. To define the parameters control-
the rock mass far from the a 'One ling failure propagation more accurately, further studies
exceeding 1.7 m in extent is detected. should be conducted using appropriate back-analysis
The back-analysis of rock mass strength is complicated
techniques.
by the fact that the location at which failure initiated is not
known accurately. However, it can be assumed that failure 4.2 Back-analysis of rock mass modulus
almost certainly took place behind the tunnel face. The Earlier, it was observed that the shape of the relative
radial stress increase occurring ahead of the face is in fact displacement curves, given by multipoint radial extenso-
very moderate at the tunnel crown (see Pelli 1987). Immedi- meters at the crown, is considerably affected by yielding (for
ately behind the face of the tunnel, the first possible condi- KO = 2). In Fig. 21, the relative radial displacement curves
tions of failure are found as the axial stress increases to calculated at the tunnel crown for linear elastic and elasto-
approximately 17 MPa (Fig. 20). If the rock strength is plastic rock are compared. The same modulus characterizes
assumed to be independent of the intermediate principal the rock masses in the elastic region. The two curves have
stress and the uniaxial compressive strength of the rock is considerably different shapes but intersect at point A.
exceeded by this value (17 MPa), faiIure occurred very close Point A represents the only location at which, by fitting
behind the advancing tunnel face. If not, failure took place results from linear elastic models to field data, the correct
somewhere within 0.8 and 1.0 diameters behind the face, rock mass modulus can be back-analyzed. Point A corre-
where the tangential stress reaches 23.5 MPa (point B in sponds approximately to the boundary between the elastic
Fig. 16). The upper limit for uc, = 23.5 MPa (equal to and the plastic zones. Failure tends to cause larger displace-
tangential stress at one diameter behind the face) can be ments in the plastic zone than for the elastic case and reduces
defined without problems; the lower limit is uncertain. If the inward movement outside the plastic zone by changing
the rock failed immediately behind the face of the tunnel, the equivalent shape of the cross section from circular to
because of the high axial stress value, this would only "elliptical" (see inset). Hence, to evaluate the rock mass
indicate that u,, is lower than 17 MPa. At the same time, modulus correctly, the closest measurement to the boundary
the relatively thin plastic zone (between 0.4 and 0.8 m thick) of the plastic zone should be fitted.
detected at the wall immediately behind the TBM shield Two cases will now be analyzed by using the procedure
indicates that the maximum uniaxial stress of 23.5 MPa has suggested above. The selected cross sections are those of
not exceeded the uniaxial strength of the rock by a large chainages 3205 and 2296 m (Figs. 13b and 13d). In Fig. 22,
amount. On the basis of these observations, a uc, = the results obtained by a three-dimensional finite element
17 MPa can be assumed for the interbedded siltstone- analysis are matched visually with the field data for chainage
mudstone in this tunnel section. By relating this value to the 2296 m obtained at 1.5 m from the tunnel wall (near the
252 CAN. GEOTECH. J'. VOL. 28, 1991 \

I I I I I
I
0 5 10 15 20 25
x (m)
FIG. 22. Measured and predicted radial displacement profile at FIG. 23. Measured and pre8gcted radial displacement curves at
chainage 2996 m; fitted at 1.5 m from the tunnel wall with chainage 1428 m; fitted at 3 m from the wall with E = 0.5 GPa.
E = 1.65 GPa.

plastic zone boundary) and 7.5 m behind the tunnel face. ( E = 0.5 GPa) demonstrates that the coal is highly deform-
The fitting was carried out by scaling the numerical results able compared with the siltstone. This supports the conclu-
until proper matching of the field data was obtained at the sion that this stiffness variation could have caused a stress
boundary of the plastic zone (Fig. 13d). The measured concentration that failed the thin siltstone layer at the crown
curves at 3.2 and 3.7 m from the wall give lower displace- of the tunnel at this location.
ments than predicted by the finite element analysis, whereas
the movement of the anchors in the plastic zone considerably 4.3 Summary
exceeded those predicted (based on linear elasticity). The radial displacement records detected in the mixed
A Young's modulus of 1.65 GPa for the interbedded sediments and in the direction of the minor principal stress
siltstone-mudstone is the outcome of this analysis, whereas have been considered to back-analyze the rock mass strength
E = 9 GPa was measured in the laboratory (Yuen et al. and elastic modulus. The uniaxial compressive strength of
1985). the rock mass was back-calculated at chainage 2263 and
Chainage 3205 m was analyzed in the same manner. 3205 m (Figs. 13a, 13b, 14, and 15) by defining the distance
A point 40 m behind the tunnel face and an anchor at 2.9 m from the tunnel face at which failure initiation took place
from the tunnel wall were selected for comparison with the and by making reference to three-dimensional linear elastic
finite element results (point A in Fig. 15). The back-analyzed finite element analyses (Fig. 16). The initial stress field was
Young's modulus for the siltstone is 5.6 GPa at this loca- approximated from field tests conducted at the site. The
tion, whereas E = l l .5 GPa was measured in the labora- back-calculated strength values are presented in Table 2 (sec-
tory (Yuen et al. 1985). The data collected within 15 m from tion 5) together with laboratory values for comparison. Con-
the tunnel face were not considered for back-analysis sideration was also given to chainage 1428 m (Fig. 13c)
because they displayed erratic behaviour, perhaps owing to where a coal seam was detected near the tunnel wall and
the action of the rib expansion mechanism. chainage 2296 m (Fig. 13d) where failure initiation could
The corresponding ratios of E(field)/E(lab) are 0.18 and not be localized from the extensometer records.
0.49, respectively, for interbedded siltstone-mudstone and The Hoek and Brown failure criterion was adopted for
siltstone. the rock mass at chainages 2263 and 3205 m, and the
Finally, the deformability of the rock at chainage 1428 m strength parameters s and rn were back-calculated by com-
was analyzed. In the previous section, it was stated that the paring stresses induced by tunnelling with laboratory
low stiffness of the coal seam caused by early failure (near strengths and from the extent of the plastic zone measured
the face of the tunnel) at this location. The elastic modulus in the field. A series of linear elastic boundary element anal-
of the rock was obtained by visually fitting the numerical yses were carried out to investigate, by comparing the com-
results to the displacements measured at 3 m from the wall puted stresses with the Hoek and Brown failure criterion,
(Fig. 23). The very low modulus back-analyzed value the effect of s and rn on the extent of the plastic zone. The
PELLI E T AL.
i

TABLE
2. Summary of deformation and strength properties
'r

. ~ Interbedded
siltstone-mudstone
Portal sandstone Siltstone (chainage 2996 and 2263 m)

Rock modulusa
E(B), GPa 5-6
E(L), GPa 34.2
E(F), GPa 8-28
(average 10)
Average E(L)/E(B) 5.7-6.8
Average E(F)/E(B) 1.7-2
Rock strength
ucm(~),MPa
ffcm(~),
MPa 93.8
ucm(~)/ucm(~)
S
rn
NOTE:E(B), back-analyzed Young's modulus; E(L), mean laboratory Young's modulus; E(F), field (pressure
meter) Young's modulus; uC,(~),back-analyzed uniaxial compressive strength; uCm(~),
mean laboratory uniaxial
compressive strength; s and m, back-analyzed Hoek and Brown parameters.
a Similar low values of E were calculated in the other mixed-sediment group formations.
Based on failure initiation and extent of yield zone.
Based on failure initiation only. A much lower s value would have to be assumed to justify the-&tent of
the observed yield zone.

results of these analyses, summarized in Fig. 17, show sig- (ii) The complete radial displacement curve (measured
nificant differences between the back-analyzed values and behind the tunnel face) in the direction of the major prin-
those proposed by Hoek and Brown (1988) for good quality cipal stress may reveal the extarof the nonlinearity and time
rock masses. These differences are due to the high sensitivity dependency of the rock mass. A procedure based on fitting
of s and m in areas of low confinement. The back-calculated the field data with the Ramberg-Osgood nonlinear relation-
s and m values are listed in Table 2 (section 5), even though ship was presented. Further studies are required, based on
it was concluded that these values are not representative for more extensive field data, to allow a quantitative determina-
the rock mass at some distance from the opening wall. tion of rock mass parameters by application of this
Based on the results of linear elastic and elastic plastic procedure.
three-dimensional finite element analyses (Fig. 21) the elastic (iii) Fitting the convergence curve in the direction of the
modulus was back-calculated by fitting the field measure- major radial initial stress with the Ramberg-Osgood relation-
ments, collected at chainages 3205 and 2996 m (Figs. 15 ship also proves effective in predicting the final radial
and 22) in proximity of the elastic plastic zone boundary, displacement from the initial part of the curve, measured
to the results of linear elastic three-dimensional finite ele- near the tunnel face. For the Donkin-Morien project, a rea-
ment analysis. The back-analyzed values are shown in sonable prediction of the rock mass modulus was possible
Table 2, together with laboratory data for comparison. Con- at distances of 1.5-3 diameters from the tunnel face.
sideration was also given to chainage 1428 m, where the coal (iv) Partial displacement measurements, recorded imme-
layer near the tunnel wall lead to a very low value of the diately behind the tunnel face, can be used to arrive at a
back-calculated elastic modulus. good estimate of the Young's modulus. On the other hand,
estimating the amount of nonlinear deformation taking place
5. Conclusions in the direction of the major principal stress based on the
A history matching back-analysis based on the procedure magnitude of the radial displacements measured behind the
and findings presented by Pelli et al. (1990) was applied to tunnel face can lead to significant over- or under-estimates.
data from a case history of a TBM driven tunnel in sedimen- The reason is that these readings are profoundly affected
tary rocks. The analysis was conducted to determine both by the magnitude of the displacements ahead of the tunnel
rock mass deformation and strength properties. face (unknown in most underground monitoring projects).
The back-analysis methodology presented in this paper Therefore, methods relying on the shape of the convergence
seems to be effective despite the relatively limited number curve (see point ii above) rather than on displacement
of available instruments. The following conclusions can be magnitude seem more promising.
drawn. (v) When data from multipoint radial extensometers
(i) The elastic modulus of the rock mass can be back- placed in the direction of the minor radial initial stress are
analyzed by fitting the results of the universal, three- available, the elastic modulus of the rock mass should be
dimensional linear elastic analysis with the initial part (near calculated by fitting the results of a three-dimensional
tunnel face) of the convergence curve in the direction of the universal analysis (linear elastic) to a measurement taken in
major principal stress. This procedure proves to be effective the elastic zone, as close as possible to the plastic zone
even if a moderate amount of nonlinearity characterizes the boundary. This procedure has provided reasonable modulus
rock deformability. Furthermore, it can be applied even if values at the Donkin-Morien project. However, measure-
no measurements ahead of the tunnel face are available. ments taken in the direction of the major principal stress
254 CAN. GEOTECH. J. VOL. 28, 1991
I
should also be available at the same section, to reduce BIENIAWSKI, Z.T. 1984. Rock mechanics design in mining and
uncertainty. tunnelling. A.A. Balkema, Publishers. %he Netherlands.
(vi) For data collected in the direction of the minor prin- DESAI,c.s~, and Wu, T.H. 1976. A general function of stress-
cipal stress, the uniaxial compressive strength of the rock strain curves. Proceedings, 2nd International Conference on
Numerical Methods and Geomechanics, American Society of
mass can be back-calculated if the distance from the tunnel Civil Engineers, Blacksburg, VA, vol. 2, pp. 306-318.
face at which failure takes place is detected by the field GIODA,G., and MAIER,G. 1980. Direct search solution for an
instrumentation and if the initial stress field is known. If inverse problem in elastoplasticity: identification of cohesion,
the constitutive relationship of the rock does not exhibit sig- friction angle and in situ stress by pressure tunnel test. Interna-
nificant nonlinearity in the pre-peak range, the principal tional Journal for Numerical Methods in Engineering, 15:
stresses at failure can be calculated by three-dimensional 1823-1848.
finite element analyses, based on linear elastic rock HEUZE,F.E. 1980. Scale effects in the determination of rock mass
behaviour. strength and deformability. Rock Mechanics, 12: 167-192.
(vii) The rock mass strength parameters s and rn (Hoek- HOEK,E., and BROWN,E.T. 1980a. Underground excavations in
Brown failure criterion) could be back-calculated by com- rock. Institution of Mining and Metallurgy, London, U.K.
-1980b. Empirical strength criterion for rock masses. ASCE
paring stresses induced by tunnelling with laboratory Journal of the Geotechnical Engineering Division, 106(GT9):
strengths and from the extent of the plastic zone measured 1013-1035.
in the field. For this particular case, the observation of -1988. The Hoek-Brown failure criterion - a 1988 update.
discontinuous failure assisted in establishing the most likely Proceedings, 18th Canadian Rock Mechanics Symposium,
parameter pair. A simple procedure, based on linear elastic Toronto, Ont., October 1988, pp. 31-38.
stress analysis has been used for the Donkin-Morien project. KAISER,P.K. 1991. Deformation monitoring for stability assess-
The parameters s and rn are related variables and very sen- ment of underground openings. In Comprehensive rock
sitive when determined from areas of low confinement (near mechanics. Edited by J.A. Hudson, Pergamon Press, vol. 4,
an opening). The power in the Hoek-Brown failure criterion chapter 26.
needs to be reassessed for applications to rock mass failure MARSH,J.C., CURRIE,D., LANDRY,G., and LAMB,T. 1986.
Cape Breton Development Corporation's experience with a
in low confinement zones. tunnel-boring machine in coal measures. Canadian Institute of
(viii) The results of the back-analyses are summarized in Mining and Metallurgy Bulletin No. 891, pp. 49-55.
Table 2. The modulus ratio of laboratory to back-analyzed PELLI,F. 1987. Near face behaviour of deep tunnels in rock.
values varied between 2 and 6.8. The back-analyzed uniaxial Ph.D. thesis, Department of Civil Engineering, University of
strength is about one-half to two-thirds of the laboratory Alberta, Edmonton.
strength. PELLI,F., KAISER,P.K., and MORGENSTERN, N.R. 1990. The
(ix) The quality of the results from back-analyses are con- influence of near face behaviour on monitoring of deep tunnels.
trolled by the quality of the field data. Two major limita- Canadian Geotechnical Journal, 28, this issue.
tions were detected at the Donkin-Morien monitoring and RAMBERG,W., and OSGOOD,W.R. 1943. Description of stress-
testing program: (a) the stress measurements were limited strain curves by three parameters. National Advisory Committee
for Aeronautics, Washington, D.C., technical note No. 902.
to a single location and, because of technical problems dur- RICHARD,R.M., and ABBOTT,B.J. 1975. Versatile elastic-plastic
ing testing, an accurate assessment of the in situ stresses was stress-strain formula. ASCE Journal of the Engineering
not provided and (b) only one extensometer was installed Mechanics Division, lOl(EM4): 5 11-5 15.
at each instrumented section, mostly at the tunnel crown. SAKURAI, S., and TAKEUCHI, K. 1983. Back analysis of measured
Both of these aspects limited the amount of information displacements of tunnels. Rock Mechanics and Rock Engineer-
obtainable from the back-analysis process and it is strongly ing, 16(3): 173-180.
recommended that, on similar projects, more than one SANTARELLI, F.J., and BROWN,E.T. 1987. Performance of deep
extensometer be installed per section. wellbores in rock with a confining pressure-dependent elastic
modulus. Proceedings, 6th Congress of the International Society
Acknowledgements of Rock Mechanics, Montreal, Que., September 1987, vol. 2,
pp. 1217-1222.
The monitoring of the Donkin-Morien project was SANTARELLI, F.J., BROWN,E.T., and MAURY,V. 1986. Technical
initiated by CANMET (Canadian Centre for Mineral and note. Analysis of borehole stresses using pressure dependent
Energy Technology) and the consulting company Golder linear elasticity. International Journal of Rock Mechanics and
Associates executed the monitoring program and documented Mining Sciences and Geomechanics Abstracts, 23(6): 445-449.
the results. The authors wish to acknowledge the tremendous YUEN,C.M.K., GILBY,J.L., and BOYD,J.M. 1985. Measure-
efforts of these two groups. Without the data collected in ments and analysis of rock deformation and support system
a professional manner this back-analysis would not have response in the drill and blast and bored access drivages at the
been possible. The research was financed by operating grants Donkin-Morien project (UP-(3198). Canada Centre for Mineral
from the Natural Sciences and Engineering Research Council and Energy Technology, report No. 26SQ.23440-2-9159.
YUEN,C.M.K., BOYD,J.M., and ASTON,T.R.C. 1987.- Rock-
of Canada.
support interaction study of a TBM driven tunnel at the Donkin
BARLOW,J.P. 1986. Interpretation of tunnel convergence Mine, Nova Scotia. Proceedings, 6th Congress of the Interna-
measurements. M.Sc. thesis, University of Alberta, Edmonton. tional Society for Rock Mechanics, Montreal, Que., September
BARLOW,J.P., and KAISER,P.K. 1987. Interpretation of tunnel 1987, V O ~ .2: 1339-1344.
convergence measurements. Proceedings, 16th Congress of the
International Society of Rock Mechanics, Montreal, Que.,
September 1987, vol. 2, pp. 787-792.

You might also like