Method Statement For Hdpe Pipe Work PDF Free
Method Statement For Hdpe Pipe Work PDF Free
Project Name:
Design, Construction, Completion and Maintenance of Court at Madinat Zayed, AL Dhafra Region.
Method Statement Title:
Installation of HDPE pipes and fittings
Client: Method Statement Reference No:
MZC-00SIT-AL-NIM-MEC-MST-0024-00-Rev.00
MUSANADA
TABLE OF CONTENTS
1- Purpose:
2- Scope:
3- Legislation and code of practice:
4- References:
5- Definitions:
6- Resources:
6.1 Materials and their approval
6.2 Subcontractor approval
6.3 Shop drawings approval
6.4 Equipment
6.5 Human Resource
7- Safety Precautions/ Risk Assessment:
8- Detailed Construction Sequence (Methodology)
9- Inspection and Testing Plan ( ITP ):
10- Related Forms:
11- Attachments:
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
1.0. PURPOSE:
The purpose of this method statement is to define the procedures to be adopted, to assure that the
laying of the pipe line and associated works are carried out strictly in accordance with the requirement
specified in the relevant specification, procedures, manufacturer’s recommendation and relevant
drawings.
This procedure describes the methods to be used for the installation of HDPE Pipes, fittings and
associated works on this project.
2.0. SCOPE:
This Scope of Works shall be read in conjunction with the Drawings, Standard Specifications and
Particular Specifications if mentioned. The scope of this method statement & Quality plan shall cover the
following activity:
The legislation and code of practice to be followed as per approved HSE plan of the Project.
ASTM & ISO standards for pipes
Abu Dhabi Environment, Health and Safety Management System (ADEHSMS)
CoP 2.0-PPE
CoP 3.0-Occupational Noise
CoP 4.0-First Aid & Medical Emergency Management
CoP 6.0-Emergency Management
CoP 7.0-Fire Prevention Planning
CoP 11.0-Safety in heat
CoP 14.0-Manual Handling and Ergonomics
CoP 17.0-Safety signage and Singles
CoP 21.0-Permit to work
CoP 22.0-Barricades of Hazards
CoP 27.0-Confined space
CoP 29.0-Excavation
CoP 33.0-Working in, over or adjacent to road.
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
4.0. REFERENCES:
The following documents should also be read in conjunction with this method statement.
5.0. DEFINITION
6.0. RESOURCES :
6.1: Material
Only Approved Materials shall be used during the construction of Fire fighting system.
Any material changes encountered or should a change in a source of material be made
shall be submitted for Engineer approval before the construction stage.
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
HDPE pipes & Fittings (of the required types, sizes etc. in the contract)
Approved pipe bedding and surround material
Dune sand
Approved Backfilling material
Detectable warning tape
Concrete grade C20 as blinding, pipe bed and surround
Grade C20 precast concrete blocks
Approved Backfilling material
Not applicable.
6.4 Equipment
Please refer the detailed methodology of HSE requirements and risk identified in Risk
Assessment sheet
Safety Jackets
Safety shoes
Helmet
Hand Gloves
Safety Goggles
Ear plug
The Health, Safety and environmental Management Plan for the project has been
prepared to meet the various HSE & Traffic and Environmental management
requirements as mentioned in Contract Document and also as per the established
HSE & Traffic and Environmental Management System and Procedure of M/s
NIGM
Environment
o Noise control
o Air quality
o Control of Exhaust emission
o Control of dust emission
o Soil ground water quality
o Weekly and monthly environmental inspection shall be
conducted
General Safety
Induction
All workers and staff shall attend the HSE induction before commencing the
work at site
All personnel shall adhere the PPE
All work shall attend tool box talk held weekly
Any unsafe act or condition are to be identified and corrected immediately and
referred to respective supervisor
Any accident or incident shall be reported immediately to take preventive
measures
Training
After completion of the preliminary original ground level by GPS system the
area shall be marked in grid system. Before commencing this work all underground and
existing services and obstruction are clearly marked and dealt with approved method
statement
Surveyor shall ensure that all survey equipment is calibrated and having valid
calibration certificate and he shall also ensure that the pipe laying is done to the
require line and level.
Survey check Report / Other relevant data shall be recorded
Original ground level for the whole construction site will be surveyed and
recorded, After the completion of the daily joint survey, the data collected will be
printed in hard copies for joint signature, Work shall only be commenced in area
surveyed where survey sheet are jointly signed. After establishing full survey
record, plan will be prepared and submitted for approval.
Work location shall be designated well ahead according to Programme to enable
achieving the planned production.
Existing services shall be located by use of cable detectors and trial excavation;
they shall be clearly marked at site.
8.0.3A Preliminary
One set of relevant approved shop drawings, sketches etc. indicating the setting out
details, levels etc. shall be made available at the site of work for verifying &
inspection prior to commencement of pipe laying. All the existing utilities to be
confirmed and marked by using trial pits excavation.
Verify the survey points established as per previous approved method statement and
to ensure that all reference points are found intact without any damage or removed.
Ensure that trench formation is dry and free from obstructions, depressions, debris,
loose soil, stones etc. Dewatering if required shall meet the requirements.
Ensure that formation is compacted to the true line, level and gradient as per
specification.
WIR shall be submitted in the approved format 24 hours prior to inspection of any
activity, and be approved by the consultant.
Mobilize the required materials, plant, equipment and manpower as required to
ensure a prompt start & completion of work as per project schedule.
All materials shall be inspected (MIR) prior to use for installation and any damaged
material shall be identified and stored separately.
Care shall be taken not to damage the pipe when handling. Pipes shall not be stored
on rough or rocky ground. Pipes shall be placed without timber blocking on pipe
barrels. Pipes has to be inspected and any damage has to be recorded and notified.
Damaged goods shall be marked and removed from site. Pipes shall be handled and
stored as per manufacturers recommendations.
Pipe shall be cut using milling type cutter, rolling pipe cutter or abrasive cutter. Do
not use flame cut.
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
Generally the width of the trench should be the minimum dimension compatible
with safe working and the satisfactory laying, jointing and bedding of the pipe.
The cover height of all pipes shall not be less than 1200 mm measured from top of
the pipe to the finished grade level or as shown in the approved drawing.
Where trenches are required to be deeper than the general depth mentioned the
trench shall be dug to a required depth with a gradual slope necessary for proper
laying of the pipeline.
Pipe line shall not be closer than 300mm to the other pipeline services or structures.
The trench width depends on the nature of ground, depth and pipe size. The clear
width of the trench at any level shall be min of one pipe diameter plus 300mm (±
50mm).
In all cases trench shall be excavated sufficiently to ensure efficient laying and
jointing of pipes.
Pipe bedding and surround material for HDPE Pipes shall be as per specification.
All bedding & surround material shall be subjected to prior approval of the engineer.
Pipe surround material shall be wetted and lightly tamped or compacted in place.
All pipes shall be installed in trenches at variable depth below surface depending on
the architectural, shop drawing and road details
Pipes crossing the streets shall be well protected and embedded in sand.
All pipes fitting valves etc shall be carefully lowered into the trench with suitable
equipment in a manner that will prevent damage.
Open ends of the pipe shall be closed whenever pipe laying is not in progress and at
the end of the day to prevent entry of any foreign matter.
Install all items in accordance with recommendation of the manufacturer, installing
each item firmly in position, level, plump and properly connected.
Special foundations or other fixing supports/ blocks shall be provided as required
Care shall be taken to ensure pipeline is clear and free of all foreign matter at all
times. Sufficient backfill shall be placed on the pipe to prevent floatation. Any pipe
that has floated shall be removed from the trench and re-laid in a dry trench.
As the installation of the various system components are completed, they shall be
adequately cleaned before final closing. All foreign materials shall be removed from
equipment and surrounding areas.
HDPE Pipes and fittings can be assembled into a pipeline network by means of Butt
Fusion with same SDR & pipes & fittings of the same nominal diameter.
Butt fusion machine consists of machine body, hydraulic unit, heater and milling
cutter.
Butt fusion is thermo-fusion process which involves the simultaneous heating of the
ends of two pipe/fitting components which are to be jointed, until a molten state is
attained on each contact surface. The two surfaces are then brought together under
controlled pressure for a specific cooling time and a homogenous fusion joint is
formed.
An electrical heater plate is used to raise the temperature of the pipe ends, ends are
finished and made suitable for joining by using milling cutter.
The main requirements to be fulfilled are hydraulic tightness as well as structural
stability of the system.
The resultant joint is fully resistant to end loads and has comparable performance
under pressure to the pipe itself.
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
HDPE pipes can be flange jointed by using HDPE stub flange ends in conjunction
with backing plates and a sealing gasket to provide a demountable joint or to
matchup with pumps, valves etc.
Automatic welding equipment must be used which provides complete data storage
and data retrieval to record all conditions used for each weld.
Suitable electrical generator along with voltage regulator acceptable to the Client
engineer shall be used.
The welder performing the Fusion weld shall be subject to annual welder
qualification tests.
Fusion welding equipment selected shall ensure cycle is automatically controlled,
Pipe cannot be released from the machine or clamps until the specified cooling time
has elapsed, All critical parameters in the process are recorded.
Welding shall be performed as per the Client approved welding method statement.
HDPE pipe Manufacturer shall submit the welding method statement along with the
technical submittal which will be reviewed and submitted to client for approval prior
to its implementation at site.
To ensure high quality welds are produced, the welds shall be numbered to ensure
traceability, only certified welder shall be performed fusion welding. Certificates
shall be submitted for engineer’s approval.
Weld inspection & Testing shall be performed as per section
8.0.3H Testing
Proper backfilling should be provided to the testing pipe & keep the Joints open for
inspection.
It is necessary to fill, pressurize and test the section within the allotted time for the
test.
One end of the test section to be closed with the End cap or blind flange and the
other end of the test section to be connected with the testing flange having water
inlet connected to the calibrated pressure gauge & air out let.
Fill the test section slowly with water and ensure that no air is trapped in the test
section.
Air release valve to be connected to the system at the highest point to expel the
trapped air and to get the system completely filled with water.
During pressure testing, gradually increase the pressure in the test section to the
required test pressure.
Add make up water as necessary to maintain maximum test pressure.
Monitor the test section at test pressure for the test duration.
As per ISO standard, pressure test can be conducted 1.5 times the rated pressure for
2 hours at 20°C.
As the pipeline installation progresses, thrust blocks, valves, valve chambers, wash
out chambers, etc, will be constructed in accordance with the approved for
construction drawings.
8.0.3J Construction of Piping within the pump house and valve rooms
The piping will be installed using flanged joints in accordance with the Approved
shop drawings and shall be hydrostatically tested to the specified pressure.
The flange gasket shall be centrally located and the flange bolts shall be properly
tightened in accordance with the manufacturers and the mechanical requirements.
A torque wrench should be used securing the needed compression. Proper supports
METHOD STATEMENT
INSTALLATION OF HDPE PIPES & FITTINGS
shall be installed in accordance with the drawings giving importance to its elevation
and location. Torque shall be as per manufacturer’s recommendation if applicable.
Attachments: