Professional Documents
Culture Documents
2009 Paper CIRED BEMI RJDN
2009 Paper CIRED BEMI RJDN
Paper 0796
Distribution
ma rgy
INTRODUCTION ito
rin
na
system
Ene
g
operator ~
Since the share of distributed generation (DG) in the grid is =
growing, there has been increasing awareness of arising grid BEMI BEMI
BEMI BEMI
~ ~
problems, but also potentials for optimizing DG operation. ~
~
Paper 0796
Considering this context, Fig. 2 proposes a BEMI System services in normal state - where they are to support the DSO
state chart from the ESP’s perspective. Operation states are in order to retain this state - and services in compromised or
divided into three groups: disturbed state, where they should support the DSO in
leading system state back to normal. Fig. 3 proposes a
Normal (green): all customers are connected, all ICT classification of possible applications in accordance to the
elements are operational, CDE unit operation as planned state chart.
Compromised (yellow): e.g. one or more BEMI out of
operation More critical operational states
Disturbed (red): at least one customer cut off from public Normal Compromised Disturbed
Grid Disturbed Grid & ICT Disturbed Disturbed & Isolated Figure 3: BEMI System applications according to state
O A V I P B D O A V I P B D O A V I P B D
© ISET
grid reconstruction by DSO with grid reconstruction by DSO
house- or residential island mode
Reconstruction
with island grid
Reconstruction
without island grid
It should be noted that some applications in disturbed state
O A V I P B D O A V I P B D need communication within the BEMI System during power
O: Optimal operation
failure. This can be achieved by using uninterruptibe power
A:
V:
No quick load adaption needed
No grid regions blacked out
Normal state supplys for the BEMI’s computing core and ICT systems
I: No island grids
P: Pool-BEMI in full operation equipped with backup power. E.g. broad-range radio
B: All BEMI in full operation Compromised state
D: No DG derated or off-line frequency communication could still be available during
power outage.
Figure 2: BEMI System state chart (not all state Some applications can be implemented by mere data
transitions shown) © ISET exchange and usage of BEMIs local intelligence. For
example, supervision of grid voltage can be carried out by
Note that the system state changes due to failures on the one BEMIs alarming the Pool-BEMI when measurement values
hand and repair or reconstruction on the other hand. For exceed voltage thresholds set by the DSO. The Pool-BEMI
example, state could change from optimal to derated due to again can assess the overall network state by requesting
a grid congestion and the subsequent derating of DG. If a voltage measurements from additional BEMIs and inform
grid failure were to occur in this situation and some BEMI the DSO’s grid control center about the situation. Since
would cease operation, state would change to grid and ICT voltage rise is the first sign of a possible line overload in the
disturbed. If blacked out customers were allowed to build low voltage grid, the DSO could perform a switching
island grids in accordance to the DSO, another state change action, e.g. perform a ring closing. With this example it can
would occur to reconstruction with island grid. After grid be seen that using BEMI and Pool-BEMI intelligence is
reconstruction and restoration of all ICT functions, system crucial in order to reduce the need for wide-area
state would return to secure or optimal. communication, which can otherwise become a bottleneck
for the entire system operation.
There are also more advanced applications possible that
BEMI SYSTEM APPLICATIONS need a combination of distributed measurements and energy
An energy management solution aiming at economical and management by variable tariffs. However, it has to be kept
technical integration of loads and DG typically causes in mind that for security applications with tough real-time
significant changes in grid operation when compared to requirements solutions have to be found that do not need
today’s situation. Technical impacts of a high share of DG communication, since ICT quality-of-service is typically
on grid operation have been researched in various studies, limited. This applies, for example, to selectively switching
focusing on specific DG technology or systematically of distributed generators that feed a grid fault during
reviewing overall impacts [4]. BEMI System distribution automatic reclosing.
grid services are principally to support grid operation under
these circumstances. They can roughly be devided in
Paper 0796
BEMI SYSTEM SIMULATION around 12:00 due to the changed tariff. It can be expected
that a considerable efficiency increase in using locally
Algorithms for advanced applications typically can not be generated energy is possible if photovoltaic generators were
developed using BEMIs installed in real-field due to the installed in the considered grid region.
number of BEMIs required and the security of supply of
customers. Hence, a simulation was developed at ISET that 30 30
Tariff [ct/kWh]
Tariff [ct/kWh]
is able to model BEMI behavior in the distribution network. 20 20
200
devices was simulated using statistical approaches, which 100
200
ensure that many individual household load profiles add up Total Total
to known standard profiles. Photovoltaic generators and 4 SOC
FPS
4 SOC
FPS
Paper 0796
for tariff change proposals to every BEMI. voltage control as distribution grid service. This service can
4. BEMIs send individual tariff change proposals based on help improve grid operation with high share of DG.
local CDE unit states to the Pool-BEMI Apart from ongoing simulation-based studies, the BEMI is
5. The Pool-BEMI assesses the proposals and carries out the currently further developed in two projects funded by the
tariff change german environmental ministry (BMU) and the european
6. BEMIs reoptimize CDE unit operation after receiving the project “Smart House/Smart Grid”. The projects also
new tariffs. This leads to immediate voltage reduction by include further field testing. Current development includes
load connection or DG deration. increasing BEMI energy efficiency and testing new ICT
systems for radio based in-house communication.
The method was implemented as automatic algorithm
within the BEMI Simulation. Herefor a small network
246
shown in Fig. 6 was modeled, which resembles a quite
3m 39 m 240
Feeder D
HH 89 BEMI BEMI BEMI BEMI HH 98 238
236
3m 39 m
External Feeder C
Grid
234
HH 69 BEMI BEMI BEMI BEMI HH 88
8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00
0,4 kV 3m 39 m 3m 39 m
Slack- Feeder B Daytime
Node
HH 35 BEMI BEMI BEMI BEMI BEMI BEMI HH 68 Figure 7: Voltage at HH 34 without (upper) and with
3m 39 m 3m 39 m (lower curve) incentive-based voltage control © ISET
Feeder A
HH 1 BEMI BEMI HH 2 BEMI BEMI BEMI BEMI HH 34
REFERENCES
Figure 6: Simulation test grid © ISET [1] M. Braun, P. Strauss 2008, “A review on aggregation
approaches of controllable distributed energy units in
Fig. 7 shows the voltage level at household HH 34 in grid electrical power systems”, International Journal of
line A rising substantially due to high active power feed-in Distributed Energy Resources, Volume 4 Nr. 4, pp.
(upper curve). The voltage after application of the voltage 297-319
management method is also shown (lower curve). It can be [2] C. Bendel, D. Nestle, J. Ringelstein 2007, “Integration
observed that the method has led to voltage reduction of distributed generation in the future energy system in
between approx. 10:15 and 12:30. Due to the parameters of a multi-player situation – common legal and technical
the loads, voltage reduction cannot be maintained any interface for grid operation”, 19th International
longer. However, the time the voltage exceeds the 6% Conference on Electricity Distribution, CIRED,
threshold shown in Fig. 7 was reduced by 33%. This again Vienna, Austria
reduces the need for DG deration due to exceeding the [3] C. Bendel, D. Nestle, J. Ringelstein, K. Schwarz 2007,
threshold. A first result of a comparative simulation showed “Data models for the integration of the low voltage
that approx. 30% of the energy deration from photovoltaic level into grid communication and control using
generators could be saved by the method when compared to decentralised decision”, Workshop on International
the same scenario without any voltage control measures. Standardization for Distributed Energy Resources,
Herewith it could be shown that the method can support Oldenburg, Germany
avoiding LV grid congestions. [4] T. Degner, A. Shustov, J. Jäger, T. Keil 2007,
„Changing Network Conditions Due to Distributed
Generation - Systematic Review and Analysis of their
CONCLUSION AND OUTLOOK Impacts on Protection, Control and Communication
A strategic approach for enabling the energy management Systems”, 19th International Conference on Electricity
potential in the LV grid using a system based on BEMI was Distribution, CIRED, Vienna, Austria
introduced. New operational states that arise with [5] Vattenfall Trading Services GmbH, “The wholesale
introduction of this system were defined and applications product GH0”, http://www.ohv.nl/uploads/files/
were identified. The simulation system introduced has GH0%20brochure%20engels.pdf?PHPSESSID=ac221
already proven to be of high importance for BEMI System 5d27aca57b24db54bfa0c3f2462, Jan 09, 2009
algorithm development. It was shown that a method could [6] R. Witzmann, G. Kerber 2007, “Aufnahmefähigkeit
be developed that combines the BEMI System’s capabilities der Verteilnetze für Strom aus Photovoltaik”,
such as to implement the application of incentive-based Elektrizitätswirtschaft 4/2007, pp. 50-54