Professional Documents
Culture Documents
MODULE
SEVEN
Individual Risks
Risk Management
The risk
breakdown
structure
(RBS) helps us
to identify
possible risks.
CASE – IDENTIFY 5 RISKS
Read the case study ‘Alaska Fly-Fishing Expedition’ (7.1, pg 233) and identify five
potential risks.
You have 15 minutes!
Probability of an event
Easier to quantify (but is it reasonable?)
Select a % value from 0-100.
Impact of an event
Severity of impact is dependent on project
priorities
Because of stakeholder involvement, may
be easier to use a qualitative scale (low –
medium – high) and then convert to a
numeric scale. Source: publicdomainpictures.net
e.g.:
30 = 5 x 3 x 2
RISK ASSESSMENT – IMPACT SCALE
RISK ASSESSMENT – THE RISK FUNCTION
3
Moderate
Risk
Red zone (major risk)
2
Yellow zone (moderate risk)
Minor
Green zone (minor risk)
Risk
1
1 2 3 4 5
Impact
CASE – BUILD RISK ASSESSMENT
E
RISK RESPONSE
Mitigate Avoid Transfer Accept
Reduce likelihood that Eliminate the risk or Pass the risk to When a risk cannot be
the event will occur. condition. another party. dealt with another
way.
• Identify the root cause • Switch a proven • Does not eliminate
of the event. approach in for an the risk. • Low probability
• Conduct testing. untested one. • Ensure the other events.
• Quality of equipment, • Use a known supplier party can absorb the • Use a budget reserve
training. instead of a new impact! This can (time or cost).
supplier. INCREASE risk. • Contingency planning
Reduce impact if the • Use a fixed price is important.
event does occur. contract.
• Insurance policies
• Have a ‘plan B’. (low probability / high
• Parallel development. impact).
• Delay ownership /
responsibility.
Have a parallel solution in the case where the failure of an experimental solution would
be high impact.
Technical You need to be able to continually assess the ongoing feasibility of technical solutions.
Prototypes may help.
Test, test, test!
Reduce project duration by ‘crashing’. This is covered later in the course.
Keep on top of scheduling delays, so that there is still time to act before it gets critical.
Schedule Maximize use of concurrent planning, and make sure you have the best resources on
critical tasks.
Get the right level of detail (don’t use a simple +x% approach across all cost items).
Cost Have a contingency fund available to cover overruns.
Is the funding supply stable? Depends on the environment.
Funding
THE RISK RESPONSE MATRIX
CASE – BUILD RISK RESPONSE
Response
Risk Event Contingency Trigger Responsibility
(mitigate, etc)
E
CONTINGENCY FUNDING
Risk register
Simply combines the first three exercises
into a formal document (Risk – Assessment –
Response)
Adds in a ‘status’.
Risks need to be managed as closely as the
other components of the project. A risk
identified early will normally be much easier Source: maxpixel.net
Split your team. One group will complete the case study questions for Case 7.2.
The other will complete the case study questions for Case 7.4.
Then, you will get together and write a short (1/2 to 1 page) comparison – how
are the cases similar? How are they different?
Watch videos on issues management.