Professional Documents
Culture Documents
MODULE
SIX
WBS
Celebration Party
1.3 4.3
3.3
Washing Setup /
Send
the dishes cleanup
PARTY PLAN PROJECT LOGIC
Order cutlery
Order Food
/ plates
Send /
Design Secure Setup Clean-
Process Find Location
Invitations location Party up
Invitations
Buy beverages
Relationship
Activity
PROJECT LOGIC
Compared to activity B:
C
‘A’ is a predecessor activity.
‘C’ is a concurrent/Parallel
activity.
PROJECT LOGIC
PROJECT LOGIC
DEVELOPING A PROJECT NETWORK
Sensitivity
The likelihood the original critical path(s) will change
once the project is initiated.
The critical path is the network path(s) that has (have)
the least slack in common.
FREE SLACK / CRITICAL PATH
Critical Path:
It is the network path
that adds up to the
longest duration. This
means if ANY activity
on this path is delayed,
the whole project is
delayed.
BREAK TIME
10 minutes
Licenced under CC
3.0
NOW YOU TRY…
Questions?
Work on exercise 6:
Draw the network. Which is a burst activity? Which is a merge
activity?
Complete the forward and backward pass, and float.
Identify the critical path.
Get a partner and see if you go the same result, modify and agree. (5
minutes)
Bonus: try drawing a Gantt chart!
We will review the answer together. (5 minutes)
EXERCISE 6 – GANTT HINT
EXERCISE 6 – PROJECT LOGIC
EXERCISE 6 -- DURATIONS
EXERCISE 6 – FORWARD PASS
EXERCISE 6 – BACKWARD PASS AND FLOAT
EXERCISE 6 – CRITICAL PATH
EXERCISE 6 -- GANTT
Laddering
Activities are broken into segments so the following
activity can begin sooner and not delay the work.
Lags
The minimum amount of time a dependent activity must
be delayed to begin or end.
Lengthy activities are broken down to reduce the delay
in the start of successor activities.
Lags can be used to constrain finish-to-start, start-to-
start, finish-to-finish, start-to-finish, or combination
relationships.
LADDERING
Trench
9 Lay pipe
6 Refill
3
LAG RELATIONSHIPS
Introducing a lag
time simulates
the ‘laddering’
approach
presented
FIGURE 6.14 earlier.
LAG RELATIONSHIPS