You are on page 1of 30

CHAPTER

2
SECTION VII—RECOMMENDED
GUIDELINES FOR THE
CARE OF POWER BOILERS
James T. Pillow, Edmund W. K. Chang and Geoffrey M. Halley1
2.1 INTRODUCTION - CHAPTER 2 can use Section VII as an intro duction to these activities. Expe-
rienced personnel, too, can use Section VII, for they will find it to
ASME Section VII, Recommended Guidelines for the Care of be a good periodic review of the essentials of power boiler opera-
Power Boilers, falls within the purview of the BPV Committee on tion, maintenance, and inspection.
Power Boilers (BPV I). There have been no significant changes to Unlike how they treat other Sections of the ASME Boiler and
Section VII for the last several Editions and as of this writing neither Pressure Vessel Code, jurisdictional authorities do not adopt Section
BPV I nor the ASME Board on Pressure Technology Codes and VII, so consequently its use does not become mandatory. Nor does
Standards (BPTCS) have plans to update the document. With that Section VII require interpretations (which are much-needed for the
said, Section VII remains very useful tool for operators of power other sections), for its relative user-friendliness enables any operator
boilers to follow. As stated in the Introduction of Section VII: of power boilers to use it in its present state. In light of the relatively
recent emergence of the “on demand” power availability and con-
The purpose of these recommended guidelines is to promote sumption requirements, particularly in the United States, many large
safety in the use of power boilers. These guidelines are industrial boiler operators and also operators of utility size HRSG
intended for use by those directly responsible for operating, boilers are shutting boilers off when not required, even when the off
maintaining, and inspecting power boilers. cycle is for a relatively short period of time. This obviously can
significantly increase the number of operating cycles, often on boilers
As with other ASME Sections, the nine subsections—C1–C9— that were not designed for highly cyclic operating conditions. This
of Section VII discuss guidelines for safe, reliable operation as changed mode of operation often results in fatigue type failures of var-
well as avoiding unsafe conditions in the power boilers. ious boiler structural elements. Experience has shown that the majori-
This chapter is written from the perspective of Owner– Operators ty of boiler failures are due to misoperation in the field either due to
personnel experienced in operating, maintaining, and inspecting improper operator training, or a change in operating conditions, pres-
industrial and utility power boilers. Certain parts of this chapter are, sured by economics or environmental conditions. Thus, should it be
in some instances, reiterations of Section VII subsections, which was updated and maintained current, there is an opportunity for Section
done to stress the importance of the information already provided; in VII to become more important to the power generating community.
other instances, however, additional information is provided where it Most U.S. jurisdictions and all Canadian provincial and territorial
is felt to be warranted. Where there are no comments on a section, jurisdictions have adopted certain ASME Boiler and Pressure Vessel
the material is believed to have been covered sufficiently to not need Code Sections into law. Many have also become members of the
additional clarification. The reader is suggested to review existing National Board of Boiler and Pressure Vessel Inspectors (NBBI, or
literature, such as manufacturer’s instructions or company procedures, simply the NB). Typically U.S. and Canadian jurisdictions require
for additional pertinent information. new boilers and pressure vessels to be registered with the NBBI and
Section VII, along with Section VI [1], contains recommended repairs and alterations to be performed by holders of an NBBI Repair
practices and thus serves as a guideline. Consequently, it is consid- Symbol Stamp (R-Stamp, or VR-Stamp in the case of pressure relief
ered a nonmandatory standard; however, Section VII does discuss valves). This means that all work performed on the pressure-retaining
many activities that the Owner–Operator personnel must master parts of a boiler must be performed by accredited organizations using
before a power boiler is commissioned. New personnel, who might approved material control and repair or alteration methods.
not be familiar with boiler operation, maintenance, and inspection,

2.2 INTRODUCTION - SECTION VII


1
Edmund W. K. Chang and Geoffrey M. Halley were the authors of
this chapter for the second and third edition that was initially authored by The Introduction clearly states that the Section VII guide-
Edmund W. K. Chang for the first edition. – Editor. lines apply to power boilers that produce steam for external use

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-2 • Chapter 2

at a pressure exceeding 15 psig from the application of heat, as they are applied in this guide, do not include Section I-type
which may come from the combustion of fuels, from various hot locomotive, high-temperature water, and miniature boilers;
waste gases, or from the application of electrical energy. The Section III-type nuclear power plant boilers; Section IV-type heat-
guidelines apply to the boiler proper and to the boiler external ing boilers (recommended rules are covered in Section VI [1]);
piping as specified in the Code jurisdictional limits diagrams in and Section VIII-type pressure vessels; and marine-type boilers.
ASME Section I, Figs. PG-58.3.1a (given here as Fig. 2.1) and The reader should also note that once-through-type boilers are
PG-58.3.2 [2] or in ASME B31.1, Figs. 100.1.2(a) and (b) [3]. also not included in the discussions. This chapter clarifies who
(The ASME Section I diagram for drum-boilers is included as should use Section VII to enable users of excluded boilers to go
Fig. 2.1.) Furthermore, the reader should note that power boilers, to other sources for the needed information.

FIG. 2.1 CODE JURISDICTIONAL LIMITS FOR PIPING: DRUM-TYPE BOILERS (Source: Fig. PG-58.3.1(a), Section I of the ASME
B&PV Code)

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-3

Section VII guidelines are not covered in detail. However, Deregulation trends in power generation and greater permitting
Section VII does provide an overview of the activities necessary and citing difficulty of new plants add additional problems for
for safe, reliable power boiler operation, maintenance, and inspec- Owner–Operators. The need to extend boiler life requires renewed
tion. The guidelines stress the importance of the checklist, of emphasis in generating assets management and care of the power
which those in the Appendices are both helpful and essential to boilers. To help them stay competitive a separate dedicated Section
the boilers’ safe, reliable operation, maintenance, and inspection, VII Code Committee subcommittee may be warranted to tend to
and should be adapted by all Owner–Operators for use in their the necessary changes and advances. The task of the subcom-
own particular installations. (Checklists are discussed in the next mittee would include taking care of errata and adding new tech-
paragraph.) Owner–Operator personnel can become complacent, nology and trends such as heat recovery steam generator
believing that they will remember the required steps in any activ- (HRSG) and solar boiler provisions. While a number of editorial
ity without using a checklist—a bad habit, for it will in all likeli- changes have been made, particularly in the 2011a Addenda,
hood create serious consequences in the future. For example, if a number of errata and needed clarifications remain. Examples
less-experienced personnel are required to act as replacements for include FIG. C3.3-1, Typical Tubular Air Heater (i.e., “exhaust
the normal boiler operators, they are likely to overlook some cru- gases in” is shown entering the hopper drain) and FIG. 6.1-1,
cial item if they do not use checklists. Typical Boiler Water Level Gage Installation (i.e., this figure
A checklist is a listing of required activities in which each item does not correlate with the text referencing it). Also, changes to
is “signed off ” as it is completed. Although a checklist is not the ASME Section I, PG-60.2.5 and PG-60.4 have yet to be updated
procedure, it is as an important tool for ensuring that repetitive in Subsection C9.
procedures are done correctly by listing the sequence of steps that The nine subsections—C1–C9—of Section VII are reviewed
must be followed. Many Owner–Operators have assembled com- individually in this chapter to explain the reasons for which
pany procedures for the operation, maintenance, and inspection of each subsection exists. Each subsection is presented in sequence
power boilers. In some cases, however, the company’s procedure of what would be required for the normal ongoing operation,
book is kept at a location remote from the operating personnel and maintenance, and inspection of power boilers—beginning with
is therefore not readily available if needed. Ideally, these proce- the fundamentals, then followed by the progression of time
dures should be under constant review, updated whenever changes from when a plant is newly started and then ages, requiring
are made to the boiler installation or operating system, and made maintenance and inspection to maintain safe, reliable operating
readily available to plant personnel. conditions.
Throughout Section VII, the reader is reminded to consult the The user of these guidelines should note that throughout this
following: review, ASME Section I, “Rules for Construction of Power
Boilers” [2], provides rules for the construction of power boilers,
(1) manufacturer’s instructions; whereas the National Board Inspection Code (NBIC) [4] provides
(2) the ASME Code Section I; rules for boilers already placed into service.
(3) the National Fire Protection Association’s Codes; The reader of this chapter should particularly note the first few
(4) the National Board Inspection Code (NBIC); sentences of each subsection and subsubsection, for they preface
(5) the Authorized Inspector or Insurance Inspector. the basic information to follow.

Many Owner–Operators are familiar with the Electric Power


Research Institute (EPRI). Some may be members of EPRI and
thus have access to its publications regarding boiler concerns. Of 2.3 FUNDAMENTALS—SUBSECTION C1
these publications, some may be relevant to Section VII guidelines
for which an Owner–Operator requires additional information. Section VII is a useful guide for both beginner and experienced
Many independent books have been published as guidelines that power boiler operating personnel. The Preamble and the Glossary
cover the safe, reliable operation, maintenance, and inspection of are both needed in addition to the Fundamentals subsection to
power boilers. Unlike Section VII, however, these other guidelines introduce or review common terminology used in Section VII.
do not receive ongoing administration and updating, making Section Although it is obvious that the brief Fundamentals subsection
VII a logical first reference. Section VII was added to the Boiler and does not cover everything, it does attempt to introduce the basic
Pressure Vessel Code in 1926 as a branch of Section I and can be principles needed to understand the sections that follow. If addi-
compared to an attachment operating manual or guide. The title, tional information is needed, the user should consult such
“Recommended Rules for Care of Power Boilers,” remained as such resources as the boiler and equipment manufacturer’s installation,
until the 1980s, when the word “Rules” was replaced with the more operating, and maintenance manuals. It should be noted that if a
appropriate word “Guidelines.” For many years, a separate subcom- variance exists between the equipment manufacturer’s instruc-
mittee existed to administer Section VII with the greatest attention tions and any other reference, the normal practice is to follow the
focused on large electric-generating system boilers. However, with manufacturer’s instructions.
declining interest in Section VII, the subcommittee became a sub- It is important that the boiler is operated in the manner for which
group of the Subcommittee of Power Boilers (now BPV I) in the it was designed. For example, a boiler which has been designed for
1970s, with efforts made toward giving attention to smaller boilers. baseload operation (steady state) may well suffer from fatigue type
Because the care and maintenance practice of boilers changed little problems if operated in a cyclic fashion (swing loaded), due to
over the years, there was seldom a need to revise Section VII. With varying thermally induced operating stresses. It is therefore impor-
the issue of the 1995 edition, Section VII was no longer listed as a tant that the boiler owner/operator and the manufacturer each have
subgroup; presently, Section VII is still administered by the Section I a clear understanding of the manner in which the boiler is going to
Standards Committee and is still issued with new editions of the be operated if problems are to be avoided down the road. Similarly
Boiler and Pressure Vessel Code. if the operating mode of an existing boiler installation is to be

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-9

Safety training and refresher training classes become mandatory those references, persons with access to EPRI and NBBI literature
to help ensure that personnel will be conditioned to practice safe may find the information provided by these organizations highly
work habits and to show regulators that the company is serious in useful. This section reminds readers that most types of opera-
preventing workplace accidents. Unless there are laws with seri- tional problems have previously occurred and that certain prob-
ous consequences to lawbreakers specific work practices, such as lems can be avoided by learning from the combined knowledge
following operating procedures and use of checklists, will usually and experiences of these resources.
not be practiced. In addition, as with safety programs, at a mini-
mum a review of operating procedures should be performed annu- 2.4.3 Preparing for Operation
ally with quizzes included to encourage attentiveness and to Once the new power boiler is erected or installed, it is time for
demonstrate that an ongoing training program is established for one to prepare for its operation. This section provides the check-
the record. list format to ensure that nothing is missed before the fires are
started. The first reminder is related to jurisdictional inspection
2.4.2 Other General Guidelines requirements; states (U.S.), provinces (Canada), and some cities
This section continues with reminders and preludes of precau- have different inspection requirements, for some follow the provi-
tions covered in more detail in subsequent subsections. Here again sions of the NBBI, others require installation permits, and still
these precautions should be covered in the user’s procedures and others require operating permits. The reader should note that a
checklists. To prevent explosions, there is a constant reminder for permit is generally required from the local air pollution control
one to purge the fireside of the boiler, during which the proper authority before the commencement of construction or installa-
water level and the proper furnace pressure must be maintained. tion, and as one of the first steps in preparing for operation, the
Clearance for boiler expansion must also be maintained. responsible Owner–Operator must be knowledgeable of local
Section C2.140, Maintaining Proper Furnace Pressure, men- jurisdictional requirements. In most cases, the Authorized
tions that boilers with positive pressure furnaces have furnace Inspection Agency will assist the Owner–Operator with the
pressure varying from 5 in. to 25 in. of water (1.3 kPa to 6.2 kPa) inspection and permit requirements.
as the boiler operates from minimum to maximum, and that The next reminder is chemical cleaning. (Internal cleaning is
design pressure of furnaces rarely exceeds 28 in. of water because also covered in Subsection C8, “Control of Internal Chemical
of the cost of reinforcing the furnace wall support system. Boiler Conditions.”) For new power boilers, both alkaline boilout and
operators can be misinformed when changing their alarm and trip solvent or acid cleaning is necessary. The alkaline boilout is for
setpoints for high furnace pressure. The boiler manufacturer spec- removing grease and oils; the solvent or acid cleaning, for remov-
ifications may state that the furnace is designed to withstand an ing rust and mill scales.
internal pressure (furnace design pressure) of 26.5 in. of water Section VII does not mention steam blowing as one of the pre-
gage with no permanent deformation of the furnace buckstay sys- liminary steps. New boilers with separate superheat or reheat sec-
tem and as recommended by the National Fire Protection tions usually include steam blow to remove manufacturing mill
Association (NFPA) standard NFPA-85, Boiler and Combustion scale and erection debris in these steam circuits to prevent dam-
Systems Hazards Code. The boiler operator may be confronted age to downstream components such as the turbine. For in-service
with the nagging problem of high furnace pressure caused be boilers when superheat and reheat tube replacements are required,
dirty air preheater baskets and believe that he can change the high steam blow may or may not be necessary depending on the
furnace pressure trip setpoint to as high as 26 in. of water. confidence in the fabricator and erector leaving the tube free of
However, they may be unaware that the boiler manufacturer’s debris.
design terminology may have a different meaning. The following are brief synopses gathered from the preopera-
For one boiler manufacturer the furnace design pressure is tional checklists presented in this section. Readers are reminded
really the furnace yield point. They design the furnace with a to pay particular attention to the details of this section, for the
margin of safety between expected maximum operating furnace information as provided is good for training. These preoperational
pressure and the pressure at which the furnace begins to yield and checklists are preludes to the discussion in Subsection C6,
suffer permanent deformation, which may be 60 percent of the “Inspection.”
yield point. The boiler operator should, therefore, follow a trip
setpoint of 16 in. of water or 60 percent of 26.5 in. of water (fur- Safety Checklist for Inspection—for the safety of inspecting
nace yield point). personnel entering the boiler. Part 2, Inspection, of the NBIC
According to design practice, the furnace yield point must be at provides useful guidelines to follow that consider inspection
least equal to or greater than the forced draft (FD) fan capacity. If to be the primary business of the NBBI, and it also stresses
the FD fan capacity is 26.5 in. of water, the furnace yield point the importance of lockout and tagout procedures [4].
must be at least equal to this to withstand the maximum pressure
Waterside Checklist—to ensure that the accessible internals
the FD fan can supply. However, this is not a safe operating pres-
are free of erection and/or manufacturing debris, with the
sure. For example, in a worst-case situation of a “run-away-fan,”
inclusion of precautions related to relocated or inservice
the unit must trip long before the yield point or possibly suffer
power boilers. The checklist includes inspecting the inside of
permanent damages to waterwalls and points beyond. In addition,
steam- and mud-drums for deposits, loose or missing parts,
since control systems may not function instantaneously it would
and erosion-corrosion. In addition, similar comments apply to
be risky to have the trip setpoint so close to the furnace yield
the shell internals of firetube boilers.
point. Before changing high furnace pressure alarm and trip set-
points, the boiler operator must know and understand the furnace Fireside Checklist—to cover the inspection of ducts, flues,
design practices and the risks. furnaces, windboxes, and vestibules. The discussion includes
A general list of reference resources is provided for use as looking for overheating in relocated or inservice power boil-
power boiler guidelines. In addition to the organizations listed in ers. Common areas to inspect are given as well. Dirty boilers

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-5

be adhered to. Minimal references are made to electric boilers in cent uncovered tubes—a difference that, if the tube-to-header
general, for they have limited use as power boilers. connections are rolled and seal-welded, may cause the connec-
Watertube boilers comprise most utility power boilers as well tions to loosen. The boiler operator personnel must be aware that
as the majority of the larger high-pressure industrial boilers. Basic the natural circulation flow rate will differ throughout the boiler.
facts include the following: This is especially helpful when evaluating boiler tube failures.
The longer water flow circuit with multiple tube bends will defi-
(1) water flows inside the tube and the combustion gases flow nitely have less flow. This will promote deposit formation inside
on the outside; the tubes and most likely resulting in tube metal overheating.
(2) lower unit weight of boiler per pound of steam generated; The Fundamentals subsection further emphasizes that to ensure
(3) less time is required to raise steam pressure; that unimpaired natural circulation is continued, the required level
(4) greater flexibility for responding to load changes; of water must be maintained in the steam drum at all times. An
(5) greater ability to operate at high rates of steam generation; unacceptably low steam drum water level can reduce the natural
and circulation flow rate to a level that may cause the generating or
(6) close control of boiler water chemistry is required. waterwall tubes to overheat. National Board Statistical data on the
Throughout the rest of the Section VII subsections, the reader causes of boiler accidents spread over many years shows that
should remember that the circulation of water through a natural failure of the low-water fuel-cutoff device from lack of proper
circulation boiler depends solely on the difference in the weight maintenance is the most common cause of boiler accidents. The
of the steam–water mixture in the generating or waterwall tubes low-water fuel-cutoff device must be maintained in good working
and the weight of the water in the downcomers. Figure C 1.2-2 condition on all types of boilers to ensure that, while the boiler is
(Steam Drum with Tubes) is a basic diagram showing a simple operating, the water level does not drop to an unsafe level. This
natural circulation loop and is presented as Fig. 2.3 in this chap- fact should be remembered when the reader reviews other sub-
ter. As the water is heated in the generating or waterwall tubes, sections that cover water level.
steam bubbles are formed and the heated steamwater mixture The importance of the steam drum of watertube boilers in sepa-
rises through the tubes from the force of the weight of the rating the steam from the steam-water mixture will be more easily
denser, unheated water in the downcomers, thereby establishing understood after reviewing the steam drum cross-sectional views
circulation. in Figs. C1.2-3(a) and (b) (Steam Drum Internals), which are
Considering the natural circulation concept applied to actual given here in this chapter as Figs. 2.4 and 2.5, respectively. As
conditions, take for example an older tangent-tube waterwall mentioned, the upside-down Fig. C1.2-3b Steam Drum Internals–
boiler. The waterwall tubes’ fireside surfaces should not be cov- Double-Row Arrangement, Cyclone Separator Type was an exam-
ered with any refractory to repair or prevent hot spots caused by ple why Section VII should be reviewed more frequently and
the deteriorated outer sealing refractory. If refractory is applied updated along with Section I. Of all the different watertube boiler
on the fireside surfaces contrary to original design, the natural components, the steam drum has the most parts, of which the
circulation in the refractory-covered tubes may be affected, pos- design differs from manufacturer to manufacturer. Operating and
sibly leading to deposit buildup in sloped tube sections and to maintenance personnel must understand the function of each part
problems with tube expansion and contraction and causing dam- to effectively operate, maintain, and inspect a power boiler. In
age at the tube-to-header connections. some designs, the crawl space is so tight that the drum internal
Another example is a boiler in which the outer insulation has parts should be removed during each overhaul outage to ensure
fallen out in places and the condition is neglected rather than that the internal parts near the middle of the drum are not loose,
repaired. By understanding the fundamentals, it is obvious that defective, or missing.
the natural circulation may be adversely affected. If the insulation The steam drum is also a critical element of boiler internal
is missing in the upper areas, cooling may occur, making the fluid inspection. During firetube boiler inspections, the shell, furnace,
inside the tubes heavier. In addition, for tangent-tube waterwalls tubesheets, and the rear waterwall of water-backed boilers are
the covered tube may expand and contract differently from adja- important inspection areas. By inspecting inside the steam- and/or
mud drums of watertube boilers, or inside the shell and outside
the furnace and flue tubes of firetube boilers, a good assessment
of boiler water chemistry (or treatment) is obtained. Access must
be provided for a thorough inspection to be made in all the afore-
mentioned areas.
Feedwater enters the steam drum below the normal water level.
In most watertube designs, the feedwater is directed toward the
downcomers to minimize the flow of steam bubbles to them,
which would reduce the head available to maintain natural circu-
lation. If the incoming feedwater enters at the ends of the steam
drum without a distribution system, the feedwater somehow has
to be able to distribute evenly throughout the drum length to
ensure that downcomers have nearly equal amount of water to cir-
culate. This will help ensure good circulation is established to
prevent overheating. In firetube boilers feedwater is directed
FIG. 2.3 NATURAL CIRCULATION FOR STEAM DRUM WITH along the inside of the shell away from any heated surfaces,
TUBES (Source: Fig. C1.2-2, Section VII of the ASME B&PV which minimizes the possibility of any damaging thermal effects
Code) caused by cool-water impinging on the hot furnace or flue tubes.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-6 • Chapter 2

FIG. 2.4 STEAM DRUM INTERNALS: BAFFLE-TYPE (Source: Fig. C1.2-3(a), Section VII of the ASME B&PV Code)

pection personnel should be familiar. As the steam-water mixture


enters the steam drum from the heated risers, the deflection baffles
help separate the water from the mixture by directing the water
to the downcomers as free of steam bubbles as possible. These
deflection baffles are designed so that individual pieces can be
passed through the drum manhole for removal or replacement. The
pieces are held in place by brackets, welded studs, and acorn-type
nuts—the latter covering the ends of the studs to slow the corro-
sion process. Many parts are needed, all of which should be in
good condition. Maintenance and inspection personnel should be
fully aware that loose parts can break away, causing flow restric-
tions or preventing the proper separation of steam and water. The
basic criterion is that the boiler’s natural circulation is aided by
keeping the steam separate from the water inside the steam drum.
Additional information is helpful here or in section C4.600
Blowdown to add to an inspection checklist that the continuous
blowdown piping (CBD) shown in Fig. 2.4 should be inspected to
ensure that the pipe holes are in the correct orientation and spaced
properly. Inspection personnel should be wary that the pipe holes
are normally positioned at the top of the pipe so deposits are
sucked in at the top and collected on the bottom to be drained out.
FIG. 2.5 STEAM DRUM INTERNALS: CYCLONE SEPARA-
The piping should be cleaned out during outages. Obviously, this
TOR–TYPE (Source: Fig. C1.2-3(b), Section VII of the ASME
aids in the boiler water chemistry to control conductivity and
B&PV Code)
deposits.
If chemical feed piping is provided, the pipe holes orientation
Another example to show why maintenance and inspection per- and spacing also needs to be checked along with holes plugging.
sonnel should be familiar with the different boiler parts is that, in The holes are normally placed on the underside of the pipe.
certain steam drum designs, several small nozzles come off the
feedwater pipe and are directed downward toward the downcom- 2.3.2 Combustion
ers. Sometimes the maintenance personnel did not remove the The Fundamentals subsection reviews the following basic
internals for access and so did not know that some of these noz- requirements for combustion: fuel, oxygen, and heat. Coal, oil,
zles were missing; in other cases, the maintenance personnel did and gas are the most common fuels used in boilers.
not understand the function of these nozzles and therefore did not Although nonflammable, oxygen is needed to support the com-
list the missing nozzles on a punchlist. bustion of fuels. (Air is approximately 21% oxygen and 78%
The steam drum deflection baffles are another component used nitrogen.) One should remember that even though nitrogen carries
to aid in separating the steam from the steam-water mixture that away heat and makes no contribution to the overall combustion
enters the drum with which the operating, maintenance, and ins- process, it does react with oxygen to form nitric oxide (NOX)

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-7

compounds that are limited by environmental regulations. More Including more basic information is helpful to understand why
air for the combustion beyond the recommendations of burner a component is important. This information is helpful here or in
manufacturers normally reduces boiler efficiency. Heat is required section C3.240 Oil Systems. For example, the flames of oil-fired
to raise the fuel to its kindling or ignition temperature. burners must provide as complete combustion as possible.
Probably the most useful information covered in this section is Optimum flame condition of traditional burners is affected by
the discussion about coal and oil and the need for maximizing the conditions of atomizer and refractory throat, position of the air
fuel surface area exposed to air for faster, more complete burning. register or damper, and orientation of swirlers or stabilizers. See
The combustion of coal is improved by crushing or grinding the Fig. 2.6 Simple Circular Oil Burner. The atomizer helps break
coal into small particles and by creating turbulence with the air down the oil into smaller particles for the mixing with air.
supplied to thoroughly mix the fuel and air. The combustion of oil Atomizers wear out and need to be replaced regularly. The bell-
is improved by atomizing the oil into a very fine mist and by cre- mouth shaped refractory throat help create the aerodynamic con-
ating turbulence with the air supplied, again to promote thorough ditions for proper flame shape and combustion. Deteriorated
mixing. Fuel oil is atomized either mechanically with the high- refractory or incorrect throat contour and dimensions will affect
pressure drop across the oil-gun tip or by using steam or air to flame shape and satisfactory combustion and should be inspected
create an emulsion that is then subjected to a shearing action at regularly. The air register or damper delivers air into the burner
the nozzle tip. with the desired amount of rotation and velocity and helps control
The Fundamentals subsection provides only the very basic the flame shape. Throttling the air register door produces a higher
information about the combustion process. The reader should rotary velocity of air through the burner, increases the rapidity of
consult other references to fully understand the process. combustion and tends to shorten the flame. The swirler or stabilizer
further creates rotation of air around a turbulent flame resulting in
2.3.3 Boiler Efficiency laminarization of the jet flow and improves flame stability.
Boiler operators should understand the fundamentals of boiler Understanding the function of the components will help the boiler
efficiency, particularly as fuel prices increase, and they can opti- operator recognize why the components must be in satisfactory
mize fuel usage by knowing what factors affect boiler efficiency. condition and properly installed for optimum boiler efficiency.
Stack losses are the predominant factor affecting boiler efficiency. Although not mentioned in Section VII, the heat rate is com-
Stated simply, boiler efficiency is dependent on how much of the monly used to measure efficiency in utility plants—a measure that
heating value of the fuel is lost as either sensible heat or by incom- simply determines how much energy or fuel must be burned to
plete combustion. Sensible heat loss is the heat content of the vari- produce a certain amount of electrical energy that can be sold.
ous stack gas components (primarily nitrogen, carbon dioxide, The units of heat rate are measured in Btu/kWh. This efficiency
oxygen, and water vapor) that, upon traveling up a stack, are lost performance pertains to the power plant, not just to the boiler.
to the atmosphere—a loss that may be caused by the oversupply of Industrial boiler efficiency is typically expressed as output divided
excess air, by moisture in the fuel, or by humidity in the air. by input. The ASME Performance Test Code PTC 4, “Fired Steam
It is important to remember that (as stated previously) air is Generators,” covers the testing methods.
about 78% nitrogen and 21% oxygen. Nitrogen does not support The Fundamentals subsection provides basic information that
combustion; it travels up a stack with any unused oxygen and fosters thinking and helps to explain why and how power boiler
helps to cool the boiler flame. The more excess air, the more heat components function.
nitrogen traveling up a stack takes with it. Moisture in the fuel,
enhanced by ambient air humidity, becomes superheated steam
traveling as the fuel burns; it too is lost to the atmosphere upon 2.4 BOILER OPERATION—
traveling up a stack. This section briefly mentions that hydrogen SUBSECTION C2
in this moisture also combines with available oxygen, to form
superheated steam, which makes less oxygen available for the This may be the most useful subsection for boiler-operating
combustion process. This steam travels up a stack with the heat personnel. Despite this subsection’s title, however, maintenance,
normally used for the water in the tubes. inspection, and engineering personnel will also find reading this
The cleanliness of boiler tubes both inside and out and of air subsection to be of value—either as new knowledge or as a
preheaters whether tubular or regenerative affects boiler efficiency. refresher for existing knowledge.
External cleaning of watertube boiler tubes is performed with Again, the reader is reminded that one purpose of Section VII
timely sootblowing. Steam sootblowing should only be done when is to help the Owner–Operator achieve safe, reliable power boiler
necessary. Excessive steam sootblowing will lead to an over use of operation. This short subsection provides boiler-operating proce-
steam requiring additional water makeup and heating. Maintaining dures mainly for new boilers, but it can also be applied to inser-
clean watertube boiler tube interior is accomplished with proper vice boilers to help provide safe, reliable operation. It is stressed
boiler water chemistry and occasional cleaning either chemically that written procedures and checklists should be developed and
or mechanically. used by operating, maintenance, and inspection personnel.
Another contributor to the loss of fuel heating value is incomplete This subsection provides most of the information necessary to
combustion. The subsection states simply that poor mixing of fuel develop step-by-step boiler-operating procedures for the individual
and air causes it, as does a lack of sufficient air supply. Poor mixing stages of operation. The “Preparing for Operation” section pro-
in oil-fired boilers may be attributed to poor atomization and the vides just a sampling of sections called checklists: for example,
poor mixing action of the fuel and oxygen. A sufficient supply of air “Safety Checklist for Inspection,” “Waterside Checklist,” “Fireside
(which denotes a sufficient supply of oxygen) means a delicate bal- Checklist,” and “External Checklist.” The other sections of the
ance of air. Too little air produces unburned hydrocarbons and may Boiler Operation subsection, although they lack the title “Check-
cause flame instability, whereas too much air may allow an exces- list,” can also be easily adapted for checklists used by operating,
sive amount of heat to be lost up a stack into the atmosphere. maintenance, and inspection personnel.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-8 • Chapter 2

FIG. 2.6 SIMPLE CIRCULAR OIL BURNER

Because of the heavy volume of information to remember in that may help prevent accidents or damage to the boiler. Operator
the safe, reliable operation of a boiler, relying on memory alone training should also include familiarity with equipment, in which
would be foolish. It is hoped that boiler operator readers will one’s knowledge will develop with on-the-job experience and
review existing procedures, or else develop their own procedures periodic refresher training, and one’s pride in work and attentive-
and checklists after they review Section VII. ness is fostered.
This section reminds the user that following the manufactur-
2.4.1 Operator Training er’s instructions enhances his or her operating and maintenance
Some jurisdictions require qualified boiler operators or compe- skills. Some manufacturers issue periodic service bulletins to
tent attendants of power boilers. As a minimum to be qualified, alert the Owner–Operator of experiences indicating that
the operator may be required to be familiar with the Section VII modifications or corrections to his or her equipment may be nec-
contents. As the Boiler Operation subsection and the rest of essary. Plant supervisors should ensure that these changes are
Section VII are reviewed, the reader will see that valuable infor- communicated to operating and maintenance personnel. It is par-
mation is provided for safe, reliable power boiler operation, and ticularly important that product-recall bulletins on component
will also see that the Section VII contents can be adapted to parts be directed to the appropriate personnel and then followed.
develop boiler operator training courses and examinations. Many reference books have been written about boiler operations,
The Operator Training section is short and clearly written. and interactive computer programs have been developed to assist
Safe, reliable operation does depend largely on the skill and atten- with continuous training.
tiveness of the operating personnel. In some plants, the operating This section also mentions that the written procedures prepared
and maintenance personnel can be the same persons. Operator before and during the commissioning period are of special impor-
training and retraining is a must, and operator attitude must be tance. As was stressed previously, procedures and checklists are
one of attentiveness. extremely important for all stages of boiler operation, but just
Operator training should include a knowledge of fundamentals having them is not enough; the procedures and checklists must be
such as that which is presented in the Fundamentals subsection. used and revised whenever necessary. Unfortunately, many proce-
To have an appreciation of his or her job, and also for the encour- dures and checklists are published into books that are rarely used.
agement of attentiveness, the operator should understand why cer- It is recommended that a periodic review of operating procedures
tain functions are required to be performed—an understanding be handled in the same way that safety programs are handled.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-9

Safety training and refresher training classes become mandatory those references, persons with access to EPRI and NBBI literature
to help ensure that personnel will be conditioned to practice safe may find the information provided by these organizations highly
work habits and to show regulators that the company is serious in useful. This section reminds readers that most types of opera-
preventing workplace accidents. Unless there are laws with seri- tional problems have previously occurred and that certain prob-
ous consequences to lawbreakers specific work practices, such as lems can be avoided by learning from the combined knowledge
following operating procedures and use of checklists, will usually and experiences of these resources.
not be practiced. In addition, as with safety programs, at a mini-
mum a review of operating procedures should be performed annu- 2.4.3 Preparing for Operation
ally with quizzes included to encourage attentiveness and to Once the new power boiler is erected or installed, it is time for
demonstrate that an ongoing training program is established for one to prepare for its operation. This section provides the check-
the record. list format to ensure that nothing is missed before the fires are
started. The first reminder is related to jurisdictional inspection
2.4.2 Other General Guidelines requirements; states (U.S.), provinces (Canada), and some cities
This section continues with reminders and preludes of precau- have different inspection requirements, for some follow the provi-
tions covered in more detail in subsequent subsections. Here again sions of the NBBI, others require installation permits, and still
these precautions should be covered in the user’s procedures and others require operating permits. The reader should note that a
checklists. To prevent explosions, there is a constant reminder for permit is generally required from the local air pollution control
one to purge the fireside of the boiler, during which the proper authority before the commencement of construction or installa-
water level and the proper furnace pressure must be maintained. tion, and as one of the first steps in preparing for operation, the
Clearance for boiler expansion must also be maintained. responsible Owner–Operator must be knowledgeable of local
Section C2.140, Maintaining Proper Furnace Pressure, men- jurisdictional requirements. In most cases, the Authorized
tions that boilers with positive pressure furnaces have furnace Inspection Agency will assist the Owner–Operator with the
pressure varying from 5 in. to 25 in. of water (1.3 kPa to 6.2 kPa) inspection and permit requirements.
as the boiler operates from minimum to maximum, and that The next reminder is chemical cleaning. (Internal cleaning is
design pressure of furnaces rarely exceeds 28 in. of water because also covered in Subsection C8, “Control of Internal Chemical
of the cost of reinforcing the furnace wall support system. Boiler Conditions.”) For new power boilers, both alkaline boilout and
operators can be misinformed when changing their alarm and trip solvent or acid cleaning is necessary. The alkaline boilout is for
setpoints for high furnace pressure. The boiler manufacturer spec- removing grease and oils; the solvent or acid cleaning, for remov-
ifications may state that the furnace is designed to withstand an ing rust and mill scales.
internal pressure (furnace design pressure) of 26.5 in. of water Section VII does not mention steam blowing as one of the pre-
gage with no permanent deformation of the furnace buckstay sys- liminary steps. New boilers with separate superheat or reheat sec-
tem and as recommended by the National Fire Protection tions usually include steam blow to remove manufacturing mill
Association (NFPA) standard NFPA-85, Boiler and Combustion scale and erection debris in these steam circuits to prevent dam-
Systems Hazards Code. The boiler operator may be confronted age to downstream components such as the turbine. For in-service
with the nagging problem of high furnace pressure caused be boilers when superheat and reheat tube replacements are required,
dirty air preheater baskets and believe that he can change the high steam blow may or may not be necessary depending on the
furnace pressure trip setpoint to as high as 26 in. of water. confidence in the fabricator and erector leaving the tube free of
However, they may be unaware that the boiler manufacturer’s debris.
design terminology may have a different meaning. The following are brief synopses gathered from the preopera-
For one boiler manufacturer the furnace design pressure is tional checklists presented in this section. Readers are reminded
really the furnace yield point. They design the furnace with a to pay particular attention to the details of this section, for the
margin of safety between expected maximum operating furnace information as provided is good for training. These preoperational
pressure and the pressure at which the furnace begins to yield and checklists are preludes to the discussion in Subsection C6,
suffer permanent deformation, which may be 60 percent of the “Inspection.”
yield point. The boiler operator should, therefore, follow a trip
setpoint of 16 in. of water or 60 percent of 26.5 in. of water (fur- Safety Checklist for Inspection—for the safety of inspecting
nace yield point). personnel entering the boiler. Part 2, Inspection, of the NBIC
According to design practice, the furnace yield point must be at provides useful guidelines to follow that consider inspection
least equal to or greater than the forced draft (FD) fan capacity. If to be the primary business of the NBBI, and it also stresses
the FD fan capacity is 26.5 in. of water, the furnace yield point the importance of lockout and tagout procedures [4].
must be at least equal to this to withstand the maximum pressure
Waterside Checklist—to ensure that the accessible internals
the FD fan can supply. However, this is not a safe operating pres-
are free of erection and/or manufacturing debris, with the
sure. For example, in a worst-case situation of a “run-away-fan,”
inclusion of precautions related to relocated or inservice
the unit must trip long before the yield point or possibly suffer
power boilers. The checklist includes inspecting the inside of
permanent damages to waterwalls and points beyond. In addition,
steam- and mud-drums for deposits, loose or missing parts,
since control systems may not function instantaneously it would
and erosion-corrosion. In addition, similar comments apply to
be risky to have the trip setpoint so close to the furnace yield
the shell internals of firetube boilers.
point. Before changing high furnace pressure alarm and trip set-
points, the boiler operator must know and understand the furnace Fireside Checklist—to cover the inspection of ducts, flues,
design practices and the risks. furnaces, windboxes, and vestibules. The discussion includes
A general list of reference resources is provided for use as looking for overheating in relocated or inservice power boil-
power boiler guidelines. In addition to the organizations listed in ers. Common areas to inspect are given as well. Dirty boilers

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-10 • Chapter 2

or internal tube deposits at high-heat flux areas or where and Alterations, of the NBIC. It should be noted that the purpose
burner flame impingement can occur can be inspected visu- of the hydrostatic test is to verify component tightness and to
ally by using a flashlight beam directed parallel to the outside check for gross design errors; it is not a proof test.
of the tube surfaces, or they can be inspected by touch (e.g., This section defines the normal, good practices in preparing
sliding the hand over the tube surfaces to feel for bulges or for the hydrostatic test, such as using new gaskets and ensuring
blistering along the fireside surfaces). The noting of defects that the pressure gage has been recently calibrated. For safety
during inspection is stressed rather than relying on memory valves welded in place on high-pressure boilers, either gags or
until the end of the inspection. hydrostatic test plugs are recommended. This section recom-
mends the use of test plugs for high-pressure boilers over 2,000
External Checklist—for use especially with new power boil-
psig design pressure because of the possibility of misapplied
ers. The inspection includes, for example, ensuring that free
gags damaging the safety valve seat or spindle. It is recom-
access to burner equipment exists, as well as removing any
mended that gags not be fully tightened until the hydrostatic
temporary shipping or construction restraints, verifying free
pressure reaches 80% of operating pressure—the same recom-
expansion, verifying that all instrumentation and controls are
mendation given for inservice testing of safety valves to prevent
operational, and checking that personnel protection from hot
damage to the seat and spindle caused by thermal expansion.
surfaces is provided. When saying that “Piping should be free
(Safety valves are covered in more detail in Subsection C4,
to move from cold to hot position,” operations and mainte-
“Appurtenances.”)
nance personnel should be aware that any high energy piping,
The Testing section discusses water temperature; the use of
such main steam piping, should be floating, except at the des-
deaerated, distilled, or demineralized water in nondrainable sec-
ignated rigidly supported areas. Routine inspection of the
tions; the venting out of all air; the inspecting during the test; and
constant and variable spring supports should indicate no
the returning of the boiler to its normal operating condition after
topped or bottomed out conditions of the spring supports.
the test. The reminders provided in this section are useful and
Safety valve outlet guidelines are also provided, for the outlet
appropriate as items for a checklist.
part of the safety valve is not designed to hold the pressures
ASME Section I [2] specifies that the water temperature should
seen at the inlet, thereby necessitating precautions when
not be less than the ambient temperature, but in no case should it be
attaching the discharge piping. The rule provided here is that
less than 70⬚F. This minimum temperature prevents a brittle fracture
the safety valve should not support a weight exceeding the
failure during the pressure test and, to a lesser degree, minimizes any
weight of a short elbow and drip pan or a comparable weight,
false leak indications from atmospheric humidity-induced metal
and when one is in doubt, he or she should consult the safety
“sweating.” A maximum temperature of 120⬚F is specified for the
valve manufacturer. For safety valves outdoors, wind load can
safety of the Inspectors during close-up inspections if any leaks
add stress to the valve, especially if, the discharge piping
occur.
exceeds the short elbow and drip pan criteria. The proper
It is noted that all air should be vented or removed from the
location of the safety valve discharge away from potentially
system before applying pressure. Air is compressible; as such, air
deleterious positions (i.e., where it could cause injury or
in the system will make applying and holding the test pressure
property damage) is also stressed.
difficult. Safety is also a concern, for compressed air can be
explosive and dangerous to those performing the inspection.
The subject of hydrostatic testing completes the Preparing for
Operation section. It should be remembered that all jurisdictions
do not follow the same rules. For example, many jurisdictions
who have adopted ASME Section I requirements [2] may or
2.4.4 Starting Up
may not have adopted the NBIC requirements [4]. Therefore, This section provides many items that can be used in a check-
the boiler operator must first be aware of his or her jurisdiction’s list format before starting up a new or inservice boiler and that
requirements. ASME Section I requirements apply to new con- also act as good reminders. Placing the information in checklist
struction or new boilers, whereas the NBIC requirements apply to form simplifies its use and ensures that important steps are not
inservice boilers. When the boiler passes the hydrostatic test and missed. Relevant information to put into checklist form should
the manufacturer’s data report is signed by the Authorized include verifying the following:
Inspector, repairs become the responsibility of the NBIC [4]; (1) that instrumentation and protective devices are operable;
however, for both Section I and the NBIC, usually an Authorized (2) that valves are in good working condition and in the correct
Inspector is required to witness the hydrostatic testing. Where open or closed position;
permitted by the jurisdiction, the boiler operator who holds an NB (3) that gage glasses are illuminated (if required) and function-
Owner/User Inspection Organization accreditation may permit his ing properly;
or her NB Owner/User Commissioned Inspector to witness the (4) that safety valves are free to operate and expand;
hydrostatic testing after weld repairs are completed. (5) that the main steam-stop valve stem will not be damaged by
This section recommends that new power boilers be subjected thermal expansion stresses;
to a hydrostatic test of 1.5 times the design pressure. However, for (6) that fans and boiler feed pumps are ready for service; and
a boiler in service for an extended time period, such a hydrostatic (7) that the chemical injection system is operable.
test is unreasonable because of advanced age and normal deterio-
ration. A provision of Part 2, Inspection, of the NBIC addresses In installations heavily reliant on computerized controls, boiler
use of a pressure test at the discretion of the Inspector. The operators still must provide at least one operable gage glass. Note
method used for the test is to be as agreed by the owner-user and that ASME Section I, PG-60.1: “Water Level Indicators,” states
the Inspector. This provision goes on to say that pressure tests for the following: “When both remote level indicators are in reliable
repairs or alterations are to be in accordance with Part 3, Repair operation, the remaining gage glass may be shut off, but shall be

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-11

maintained in serviceable condition” [2]. The use of the gage glass (6) Test the water column and gage glasses by operating the
is especially important during start-up when verifying the water drain valve.
level at the gage glass instead of monitoring the remote level indi- (7) Test the safety valve by using a lift-assist device.
cators provides more ensurance.
This section reminds the reader of an often neglected or forgot- The reader is also reminded in this section that the curing (or
ten fact: that ASME Section I, PG-60.3.7, specifies that shut-off drying out) of new refractory is performed during the start-up
valves between boiler and gage glasses be locked or sealed open period. If proper curing and firing process is not followed, the new
[2]. PG-67.3.7 goes on to explain that the valves need not be refractory may spall or crack due to moisture in the refractory
locked and sealed open under certain conditions: the boiler maxi- turning to steam and expanding in the refractory. It is wise to fol-
mum allowable working pressure (MAWP) does not exceed 250 low the refractory manufacturer’s instructions. This will minimize
psig (1.7 MPa); the boiler is not hand fired or fired with solid fuel refractory damage, and consequently, boiler hot spots during oper-
in suspension; the burner control system stops fuel supply and fir- ation. This curing period may take from 48hr. to 1wk. to complete.
ing if the valves are not in the open position; and the minimum
valve size is NPS 1. This specification is obviously attributed to 2.4.5 On-Line Operation
the high importance of water level, especially if the remote level This section reminds the on-line operator which conditions
indicators should fail. need to be monitored for the safe, reliable operation of a power
Another useful reminder pertains to the main steam-stop valve boiler. Boiler-operating procedures, if not already in existence,
stem being eased up just enough to reduce thermal expansion can be adapted and developed further from this section. In addi-
stresses. This information may be applied to repairs when a valve tion, modifications can be made to fit the boiler operator’s experi-
is welded and the welds are heat-treated. Some maintenance per- ences. Maintenance, inspection, and engineering groups may use
sonnel may be unaware of what is required: for example, leaving this section to verify that a boiler is operating properly, for the
the valve seat and stem closed may damage them. basic information provided in this section can be applied to any
The discussion moves in sequence from “Establishing Water boiler operation. A separate checklist may be assembled starting
Level,” to “Light-Off,” and to “Going On-Line.” The boiler opera- with the waterside operation.
tor can develop written step-by-step start-up procedures from the
information provided. If the boiler operator already has such pro- 2.4.5.1 Waterside Operation Although feedwater treatment is
cedures, the information provided here can be used as a compari- very important, its title is misleading. Feedwater is about half of
son to possibly improve existing procedures. the water cycle; the other half is obviously boiler water. However,
A basic “Establishing Water Level” procedure to which details it is agreed that a competent feedwater and boiler-water chemist or
can be added includes the following: engineer should prepare instructions for feedwater and boiler-
water treatment. If the boiler operator cannot justify having a water
(1) drum vent opened; chemist on his or her staff, then he or she must provide in addition
(2) economizer drains closed; to the necessary chemicals all pertinent water chemistry instruc-
(3) superheater and main steamline drains opened; tions, training, and monitoring by means of companies specializ-
(4) header vents opened; ing in this type of service. This subject is discussed further in
(5) the boiler-feedwater line is filled; and Subsection C8, “Control of Internal Chemical Conditions.”
(6) safe, observable minimum water level is maintained. Undesirable operating conditions are also reviewed in this sec-
tion, among which are the following:
There is a reminder in this section that the water temperature
should be as close as possible to the drum and header metal tem- (1) oil in the boiler water;
peratures to protect the thick-walled drum from excessive tempera- (2) low water level; and
ture stresses and also to prevent leaks in rolled-tube joints. The (3) high water level.
boiler manufacturer specifies the temperature deviation limits: for
example, 100⬚F (38⬚C) between drum top and bottom and/or 100⬚F In addition to informing the reader who knows that the fuel
(38⬚C) between inside and outside surfaces of the drum. The pro- should be shut off under extreme conditions, this section provides
cedure must follow the boiler manufacturer’s requirements. other helpful information. When faced with the water level not
The “Light-Off “ procedure may include the following: being visible in the gage glass, one is recommended as a first step
to blow down the water column or gage glass to determine
(1) Light off and operate the specified burners that produce the whether the level is above or below the visible range. However, if
most uniform gas temperature distribution leaving the fur- a water-level indicator and a level recorder are available for
nace (furnace exit gas temperature, or FEGT). In many comparison—and if the levels are in agreement—blowing down
cases, the specified burner may be the lower-middle burner may not be necessary. As a second step, one is recommended to
of a single-wall burner boiler. shut off the fuel and air while continuing to feed the water.
(2) Maintain the water level within safe limits by feeding or Guidelines are presented for the high-water-level emergency.
blowing down while the pressure is raised. Under the aforementioned—and other—emergency conditions,
(3) Maintain the rate-of-pressure increase to keep within the the question may arise if the operating personnel are satisfactorily
thick-metal-temperature–specified gradients and the maxi- equipped and trained to react immediately and properly. The
mum metal temperatures for superheater elements. boiler operator must ask him- or herself this question constantly;
(4) Close the drum vents when the steam pressure reaches moreover, he or she must have a program that ensures a proper
25 psig (172 kPa). Nondrainable superheater vents shall be response to emergency conditions. The solution may be regular
left opened to permit condensation to boil out. training of personnel, a periodic review of procedures, or the use
(5) Check the free expansion of the boiler. of readily available checklists.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-12 • Chapter 2

2.4.5.2 Leaks As stated several times previously, Section VII is (1) For oil and gas firing, reduce the load to the minimum sta-
helpful to operating, maintenance, inspection, and engineering per- ble firing rate. Coal firing requires placing igniters in ser-
sonnel. For some persons, it provides new information; for other vice until the mill runs until empty.
(more experienced) persons, it is a useful review. This section (2) For oil and gas firing, trip the fuel shut-off valves at the
describes the steps to be taken if a serious tube failure in a water- appropriate time. Close all manual valves at the burners
tube boiler occurs, among which the following are recommended: immediately.
(3) As the boiler steam flow drops toward zero, close the main
(1) shut off the fuel flow; feedwater control valve and manually regulate the water
(2) shut down the fans; level with the bypass valve.
(3) shut off the feedwater supply. (4) When drum pressure falls to 25 psig (172 kPa), open the
The question of whether the boiler can continue to remain in drum vents to prevent the formation of vacuum.
service if small leaks are discovered in waterwall areas is (5) Cool boiler at the controlled rate recommended by the
addressed, to which this section’s response is “yes” if the water boiler manufacturer. Do not force-cool the boiler beyond
makeup is sufficient. However, other questions not addressed the recommended rates.
include the following:
For step (5) in the preceeding list, the boiler manufacturer’s
(1) Is the tube leak stream eroding or cutting adjacent tubes or instruction should be followed closely to avoid overstressing and
headers? (consequently) damaging the boiler structure. As a general practice,
(2) Will the tube leak cause starvation and overheating of the thermocouple differential temperatures are monitored as the boiler
leaking tube downstream of the leak? is cooled. Some watertube boiler manufacturers recommend moni-
(3) Will damage be caused to other components if there is sub- toring differential temperature readings between drum-top center-
sequent wet fly-ash plugging, causing channeling of gas- line and drum-bottom centerline thermocouples, and also between
flows? through-wall thermocouple differential temperature readings.
(4) Will there be additional chemicals fed as makeup that can Some manufacturers, such as Babcock & Wilcox, may use a
cause underdeposit-type corrosion? drum wall-thickness of 4 in. (100 mm) as a guideline when rais-
(5) Is the leak close enough to a burner that if the leak enlarges ing the temperature or for cooling curves provided to the boiler
it could possibly extinguish the flame? operator [11]. For drum wall-thickness of 4 in. (100 mm) or less,
temperature differentials of 100⬚F/hr (38⬚C/hr.). are used for both
An experienced engineer should review the considerations in
top-bottom and through-wall differentials; for drum wall-thickness
the foregoing list. When load demands are critical, operators
greater than 4 in. (100 mm), however, some manufacturers pro-
have been known to operate a boiler with leaking tubes for
vide separate heating and cooling curves for the boiler operator to
days. Many of the foregoing considerations also apply to
use when monitoring the two temperature differentials. The
firetube boilers; however, it has been noted that occasionally
expected practice is for an operator to plot the time-pressure-
leaking tubes have been fixed temporarily by applying a steel
temperature differentials as the boiler is cooled. Staying below
conical plug at each end of the leaking tube. This type of fix is
the chart differential temperatures will help to ensure that the
considered potentially dangerous, however, and is discouraged
steam drum is not overstressed and cracked.
because of the serious injuries that have occurred from this
Waterside and fireside cleaning is further discussed in
practice.
Subsection C6, “Inspection.” However, there are brief recommen-
Finding larger tube leaks is not a problem for most boiler oper-
dations given in this section that can be helpful reminders. One
ators. Indications of leaks normally include the following:
important consideration is inspecting the inside of the steam and
(1) high makeup water; mud drums and the fireside surfaces before any cleaning is done.
(2) excessive use of water treatment chemicals; Many operationally created conditions can be inspected and evalu-
(3) visibility of leaks from observation ports; ated before they are removed and lost during the cleaning process.
(4) water coming from hoppers or from insulation; and Before the inside of the waterside is cleaned and vacuumed, the
(5) white-vapor stack plumes. amount of deposit and other debris can be seen just after the man-
holes are opened; samples can therefore be taken and analyzed.
Small leaks may continue undetected for a long time. Any marks along the waterline can be investigated, and any areas
Ash removal is not addressed here except to say that Section of active corrosion can be seen and evaluated before conditions
VII can be enhanced and provide better understanding by adding are disturbed. Conditions of the water treatment program can be
pictures of the systems described. evaluated with this evidence seen firsthand, enabling samples to
be taken.
2.4.6 Out-of-Service Operation In addition, before the boiler wash, the inside of the furnace
The operation cycle is completed with the shutting down of can be inspected for the amount and type of ash and slag adhering
the boiler—in this case, a controlled shutdown. An orderly to the walls. Any flame impingement and clinkers can be inspected
procedure can be written on the basis of this section. and evaluated, and in the superheater areas, the amount and
Manufacturer’s instructions should be consulted to ensure that type of ash and slag can be inspected and evaluated. For boilers
all details are covered. without sootblowers in the secondary superheat and reheat tube
It has been stressed throughout this chapter that comprehensive sections due to over-designed surface areas, excessive attempera-
operating, maintenance, and inspection information is provided in tion and vibration may be created due to ash and slag on and
ASME Section VII. From the information provided in the Out-of- between tubes. Convection section components can be inspected and
Service section, considerations for a controlled shutdown may evaluated before the evidence is washed away, and soot-blowing
include the following activities: effectiveness can also be evaluated. Many Owner–Operator boiler

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-30 • Chapter 2

6. NB-18, Pressure-Relief Device Certifications; The National Board of 11. Steam: Its Generation and Use, Babcock & Wilcox, 40th ed., 1992.
Boiler and Pressure Vessel Inspectors.
12. Kohan, A. L., Boiler Operator’s Guide, McGraw-Hill, New York, 4th
7. ASME Boiler and Pressure Vessel Code Section VIII, Division 1, ed., 1998.
Rules for the Construction of Pressure Vessels; The American Society
13. Dooley, R. B., and McNaughton, W. P., “Boiler Tube Failures: Theory
of Mechanical Engineers.
and Practice,” EPRI TR-105261, Vols. 2 and 3, Water-Touched and
8. Standards for Closed Feedwater Heaters; Heat Exchange Institute, Steam-Touched Tubes, The Electric Power Research Institute, 1996.
Inc., 1998.
14. Flow-accelerated corrosion, Wilikipedia®, Wilikipedia Foundation,
9. Seat Tightness of Pressure-Relief Valves, ANSI/API Standard 527, Inc.
3rd ed., July 1991.
10. Bernstein, M. D., and Yoder, L. W., “Introduction to Power Boilers
Section I of the ASME Boiler and Pressure Vessel Code,” PVP
Conference, Honolulu, July 1995.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-14 • Chapter 2

Nonetheless, this subsection offers useful information about safe, reliable boiler operation. Answers to questions should not be
boiler auxiliaries. As is the case for the boiler, the reader is left unanswered; one should refer to manufacturer’s instructions
reminded that detailed operating instructions for these boiler or other resources.
auxiliaries should be developed following the manufacturer’s Before continuing, it is worthwhile to review by way of exam-
instructions. In particular, procedures for start-up, normal and ple one of the many useful pieces of information provided in this
emergency condition operations, and shutdown should be devel- section and in Section VII as a whole. We review the important
oped for each boiler auxiliary. In addition to procedures, checklists steps that operators should take if a major boilertube failure
should be developed for safe, reliable operation. occurs, requiring the boiler to be taken off-line immediately.
Throughout this subsection, as each auxiliary is presented, the Sometimes, boilertube failures are significant causes of inservice
reader reviews the following information: power boiler outages resulting in the loss of generation. Boiler
operators have adopted and optimized boilertube-failure reduction
(1) preparing the auxiliary equipment for operation; programs, but nevertheless, large boilertube failures cannot be
(2) placing the auxiliary equipment into service; and totally avoided. Large leaks or ruptures can drop pressure and
(3) normal operating conditions. water level very rapidly, put out the fires, and possibly cause
In essence, before a new boiler unit is started, the boiler opera- excessive temperatures in superheaters and reheaters, all of which
tor should be familiar with each piece of auxiliary equipment to would necessitate a boiler’s immediate shutdown. In its review of
be used. Regardless of whether the equipment is existing or new, the boilertube shutdown procedures recommended for coal, oil,
the appropriate personnel should ensure it is installed properly and gas burners, this section specifies that the following minimum
and will operate as intended. steps and precautions to be taken: shut off the fuel and, after
15–20 min., shut down the forced draft fans; then shut off all of
the steam outlets (main steam-stop valve and auxiliary steam con-
2.5.1 Fuel-Burning Equipment nections) (it is stressed that the latter action be taken as quickly as
The section covers gas-, oil-, and coal-burning systems in detail. possible to prevent a sudden drop in pressure from the corre-
Regardless of whether a boiler operator has one, two, or all three sponding sudden drop in temperature of the boiler water), shut off
types of burning systems, for this critical equipment where explo- the feedwater supply to prevent harmful thermal shock to the
sions are always a possibility it is obvious (as specified in the sec- thick boiler drums, and adjust the airflow rate to its permissible
tion “Preparation for Operation”) that detailed procedures covering minimum to prevent harmful temperature differentials. These
the step-by-step operation of each burner system should be devel- steps can be compared with existing company procedures, and
oped by the boiler operator personnel. In addition, as specified they may be used to develop new procedures. Operating personnel
continuously throughout Section VII, the manufacturer’s recom- should either memorize the steps or have them readily available.
mendations should be included and followed in these procedures.
Some common steps and important precautions for all systems 2.5.2 Air Heaters
are reviewed before each system is covered in more detail, exam- This section presents an informative review of air heater opera-
ples of which are the following: tions. The review is applicable to both regenerative (See Fig. 2.8
(1) Purge the furnace before any igniter or burner is lit— Regeneration Air Preheater) and tubular air heaters. These step-by-
including purging whenever flames are lost and before step procedures—beginning with preparing the auxiliary equip-
relighting. Follow the written company’s and/or manufac- ment for operation, followed with placing the auxiliary equipment
turer’s procedures precisely. The use of a checklist is highly in service, and ending with normal operating conditions—can be
recommended. used to develop the boiler operator’s own procedures. From this
(2) Never operate burners at a rate below the safe minimum section checklists can also be developed.
level at which a stable flame can be maintained. This section alerts the reader to the possibility of fires in the air
(3) The rate of firing during start-up must be controlled to not heater, of which the cause is primarily the accumulation of com-
exceed the specified or recommended drum-metal temper- bustibles in or around the air heaters. The review reminds the
ature differentials and to not exceed superheater-metal reader that temperature-indicating instrumentation should be
design temperature limits. installed at the inlets and outlets of both air and flue-gas paths
through the air heater. Doing so can warn of plugging conditions
To enhance Section VII, a useful example can be added to sub- or the presence of a fire. Checking that burner equipment is oper-
section C3.243 Oil Burning, to show the consequences when the ating properly can minimize the accumulation of combustibles,
noted precaution “Oil spray should not be permitted to strike and plugging may be minimized by proper soot blowing and off-
burner throats” is not taken seriously. Fires and damages occurred line water washing.
when an oil gun assembly was not positioned properly or was The reader is also reminded that units operating at low loads
retracted too far from the refractory throat during operation. The may develop such problems as the accumulation of unburned
result was fuel oil spraying onto the refractory throat creating combustibles and the corrosion of the cold end or of flue-gas out-
clinkers that formed a barrier for the ignited fuel oil to rebound let area. Units that must operate at low loads will not burn the
into the air register and windbox burning and damaging burner fuels as effectively as they do when burning at higher rates, and
components and windbox casing. This obviously caused a forced the flue-gas outlet temperatures may fall below the acid dew-point
outage of considerable duration, but could have had a more seri- temperature. More frequent soot blowing is necessary when the
ous consequence. units operate at low loads. If off-line water washing is performed,
The readers should review the burner-type section applicable to the procedures should be followed closely and the air heater
the systems in their plants and should also review their own com- should be dried thoroughly before it is placed back in service;
pany procedures regularly. Section VII covers many basic otherwise the ash, soot, and other unburned com-bustibles will
reminders that the boiler operator should review periodically for immediately adhere to the damp air heater surfaces. Some owners

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-15

FIG. 2.8 REGENERATION AIR PREHEATER (Source: Section VII ASME B&PV Code)

include an acid neutralization system in their washes to help mini- Severe external corrosion is possible whenever the fuel is laden
mize acidic corrosion after the wash should there be difficulties with sulfur, vanadium, iron, and sodium. The theory is that sulfur
drying the air heater surfaces. The wash water is made more alka- and sodium combine at temperatures typical of the convection
line to help neutralize the acidic condition caused by the wash pass to form a sticky deposit on the economizer surfaces.
water mixing with the ash forming a low pH residue. Vanadium in the sticky deposit helps to catalyze sulfur dioxide
It should be noted that the FIG. C3.3-1 Typical Tubular Air (SO2) into sulfur trioxide (SO3). Moisture from leaks or residual
Heater drawing was revised in the 2004 Edition. See Fig. 2.9 to boiler washwater will combine with the SO3 to form a corrosive
show how the flue gas passes through the tubular air heater. acid, so obviously any leaks in and around the economizer should
be repaired immediately. During the boiler wash, a neutralization
2.5.3 Economizers process should be considered to minimize residual boiler wash-
This short section stresses that the economizer should be treated water reacting with the SO3.
as part of a watertube boiler (as mentioned previously). Three
items mentioned in the section “Placing in Service” are worthy of
further discussion: thermal shock, steaming during start-up, and 2.6 APPURTENANCES—
severe external corrosion. See Fig. 2.10 Typical Economizer. SUBSECTION C4
Steaming is inherent to the economizer. As described, steaming
can occur during start-up if the feedwater flow is low or nonexis- Safety valves (now referred to as pressure relief vales in Section I),
tent. Moreover, feedwater is not added to the boiler during its pressure gages, feedwater regulator valves, and soot blowers are
initial start-up, so there would not be any flow through the econo- important boiler accessories or appurtenances. This subsection
mizer. The hot start-up gases pass the economizer and may form provides new, practical information for some boiler operator per-
steam inside the tubes that pass to the steam drum, leaving unfilled sonnel, and serves as a review to more experienced personnel. The
spaces in the economizer. Once the feedwater pumps start feeding amount of coverage given to each appurtenance appears logical in
the economizer, water hammer may result and possibly cause dam- the context of its importance for safe, reliable operation.
age. To avoid water hammer, an economizer-recirculating line is
installed from the boiler’s lower water space to the economizer 2.6.1 Safety Valves
inlet header, which will prevent the formation of any pockets or The first sentence of the section is all-important, for it states the
spaces that steaming may tend to create and also pre-vent damag- following: “The safety valve is a key device used to protect
ing water hammer from occurring when the feedwater line flows. against overpressure conditions.” In fact, the safety valve is the
Thermal shock is also inherent to the economizer. It can occur to last line of defense in protecting against a catastrophic failure of
the hot and thick economizer inlet header as it is being fed colder the pressure vessel itself. The safety valve has such importance in
feedwater. Designwise, not much can be done to prevent thermal safe, reliable boiler operation that the NBBI conducts a repair
shock except to inspect for cracking during outages. Inspections are program to certify qualified safety valve repair organizations
focused on the feedwater inlet area of the economizer inlet header. under its VR Symbol Stamp accreditation program. Many U.S.
Operating personnel should be aware that thermal shock problems jurisdictions mandate the use of the NBIC [4] and require that
are possible whenever feedwater heaters must be taken out of ser- repair of ASME V-stamped and NB-stamped safety valves be per-
vice because of feedwater tube leaks. formed by an NBBI VR-Certificate Holder.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-16 • Chapter 2

The reader should note that this section pertains mainly to safety
valves that have been in service operating on the boiler.
Obviously these safety valves should be inspected and tested at
regular intervals; however, no set code-determined required time
period exists for this inspection and testing. This section recom-
mends that the frequency be determined by a valve’s maintenance
history; it implies that if there is any doubt one should use 1 yr. as
the starting frequency of inspection, testing, and possibly repair.
The annual activity should include the following:
(1) a thorough visual inspection;
(2) testing, preferably on the boiler at its operating condition;
and
(3) repair, if necessary.
Stated another way, if the inspection and testing reveal that the
safety valve will operate properly, and if it was not damaged dur-
ing testing, the safety valve in its current condition can be
returned to service and the next inspection and testing can be
scheduled for the subsequent set period.

2.6.1.1 Safety Valve Maintenance The reader should be aware


that the VR Symbol Stamp accreditation program follows the
requirements of ASME Section I, Power Boilers [2] for new safety
valves. Much of the information provided in this section is similar
to the maintenance information provided in the NBIC [4]. The
points listed in C4 paragraphs 120(a)–(m) should all be included in
a safety-valve maintenance program, and are in the main easy to
understand; however, certain items will benefit from further
clarification. Section VII FIG. C4.1-2 Typical Safety Valve (given
here as Fig. 2.11) shows the components of a typical safety valve.
In (b), it is mentioned that the most reliable way to test a safety
valve is on the boiler at operating conditions. However, this
method is not recommended for safety valves set to open above
600 psig (4 MPa)—obviously for safety reasons. Testing of safety
valves on the boiler during operation requires one to closely
approach the boiler to hear the pop and the reseating of the disk,
and also to witness the amount of lift of the valve stem. A remote
lift indicator device can be rigged, but doing so is not always pos-
sible because of repair organization limitations.
In (f), a repair nameplate of the qualified repair organization is
required after the safety valve is disassembled and repaired. This
qualified repair organization may be a VR-Certificate Holder or
one that has received a special permission from a jurisdiction. If
the set pressure is changed, the corresponding new capacity must
FIG. 2.9 TUBULAR AIR HEATER DRAWING be shown on the repair nameplate. It is specified in (f) that the
(Source: Fig C3.3-1 Section VII of ASME B&PV Code) new capacity be based on that for which the valve was originally
certified. Typically, the NBBI publication Pressure Relief Device
Certifications (also called NB-18) can be consulted to determine
Much of the following information is from experiences with the new capacity [6]. It contains formulas and tables for that task.
this program, and should not be considered as official interpreta- It should also be noted that if the operating pressure of the
tions of any code. Codes may be revised and readers should con- boiler is derated by modification (or for any other reason), the
sult the latest code edition and addenda for current information. safety valves must be resized to pass the required capacity at
Besides providing the rules for certifying the safety valve repair the lower pressure. The newly sized valves will generally be larger
organization, the NBIC [4] provides guidelines and recommenda- than their predecessors; in some circumstances, they may actually
tions for the testing, inspection, and repair of safety valves. This require the valve openings in the boiler to be enlarged.
section on safety valves covers similar material as that covered by In (j), checklist items are provided for visual inspection whenever
the NBIC [4]. Section VII does not specifically refer to the NBBI a safety valve is to be tested on the boiler. One of the recommenda-
VR Symbol Stamp accreditation program because it has not been tions is to gag the safety valve before any close visual inspection–
adopted by all jurisdictions. For more information regarding this obviously to ensure the safety of the inspecting personnel.
program, the reader can refer to the NBIC or ANSI/NB-23 [4]
(ANSI is an acronym meaning the American National Standards 2.6.1.2 Safety Valve Testing This section states the following:
Institute), or can visit the NBBI Web site: www.nationalboard.org. “After visual examination and successful hand lift operation, each

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-17

FIG. 2.10 TYPICAL ECONOMIZER (Source: Fig. C3.4-1 Section VII of the ASME B&PV Code)

valve should be tested for the following operating characteristics.” give one the lift data necessary for determining the rated capacity,
This statement is not totally correct; if the valve were tested for the but one is also reminded that the lift measurement is meaningful
three safety valve operating characteristics—the opening pressure or only if the valve-adjusting rings are correctly adjusted.
set pressure, the closing pressure or blowdown, and the capacity—a As noted in this section, safety valve testing is normally per-
hand lift test would not need to be performed. The information pro- formed when the boiler is being shut down for inspection or for a
vided in this section is very useful for the safety valve repair person- planned overhaul. If the safety valve is damaged during testing it
nel and for the engineer in charge of the repair program. However, can be repaired during the outage. As would be expected, for this
when the NBBI VR Symbol Stamp requirements are followed, testing the boiler operator should have a written procedure,
testing is performed only to demonstrate the set pressure and which should be reviewed before the testing begins. If safety
response to blowdown, as well as the seat tightness. (This testing valve gag-ging is necessary, the seal at the spindle adjustment
applies to an inservice safety valve after it has been repaired.) The must be cut. Testing involves gagging the safety valves not tested.
capacity or measurement of the spindle lift is crucial when a repair Under most repair programs, the testing must be performed by,
organization is required to demonstrate the pressure-relief valve or under the supervision of, qualified pressure-relief valve repair
repair capability. personnel. If the safety valve passes the visual inspection and
The opening or set pressure for any safety valve must be within tests, it can be returned to service in its current condition. If a
the permissible variation specified in ASME Section I, PG-72.2 [2]. seal was cut off, that seal must then be replaced. Under most
For closing pressure (or blowdown), it should be noted that as of the repair programs, only qualified safety valve repair personnel can
1998 edition of Section I, PG-72.1 [2] was revised to expand the replace the seal.
maximum blowdown requirements for spring-loaded safety valves. Lift-assist devices may be used to set and check the set pressure
However, with the first addendum after the 2004 edition the blow- of certain safety valves. The safety valve manufacturers provide
down requirement were eliminated. For capacity, the measurement these devices for certain models in their product line. As men-
of the spindle travel or lift is useful for determining if the rated tioned in this section, lift-assist device testing cannot verify valve
capacity can be achieved without actually measuring the flow rate. performance; only full-pressure popping can provide the valve per-
Both the original valve nameplate and the NB-18 publication [6] formance data. However, lift-assist device testing is permitted by

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


CHAPTER

2
SECTION VII—RECOMMENDED
GUIDELINES FOR THE
CARE OF POWER BOILERS
James T. Pillow, Edmund W. K. Chang and Geoffrey M. Halley1
2.1 INTRODUCTION - CHAPTER 2 can use Section VII as an intro duction to these activities. Expe-
rienced personnel, too, can use Section VII, for they will find it to
ASME Section VII, Recommended Guidelines for the Care of be a good periodic review of the essentials of power boiler opera-
Power Boilers, falls within the purview of the BPV Committee on tion, maintenance, and inspection.
Power Boilers (BPV I). There have been no significant changes to Unlike how they treat other Sections of the ASME Boiler and
Section VII for the last several Editions and as of this writing neither Pressure Vessel Code, jurisdictional authorities do not adopt Section
BPV I nor the ASME Board on Pressure Technology Codes and VII, so consequently its use does not become mandatory. Nor does
Standards (BPTCS) have plans to update the document. With that Section VII require interpretations (which are much-needed for the
said, Section VII remains very useful tool for operators of power other sections), for its relative user-friendliness enables any operator
boilers to follow. As stated in the Introduction of Section VII: of power boilers to use it in its present state. In light of the relatively
recent emergence of the “on demand” power availability and con-
The purpose of these recommended guidelines is to promote sumption requirements, particularly in the United States, many large
safety in the use of power boilers. These guidelines are industrial boiler operators and also operators of utility size HRSG
intended for use by those directly responsible for operating, boilers are shutting boilers off when not required, even when the off
maintaining, and inspecting power boilers. cycle is for a relatively short period of time. This obviously can
significantly increase the number of operating cycles, often on boilers
As with other ASME Sections, the nine subsections—C1–C9— that were not designed for highly cyclic operating conditions. This
of Section VII discuss guidelines for safe, reliable operation as changed mode of operation often results in fatigue type failures of var-
well as avoiding unsafe conditions in the power boilers. ious boiler structural elements. Experience has shown that the majori-
This chapter is written from the perspective of Owner– Operators ty of boiler failures are due to misoperation in the field either due to
personnel experienced in operating, maintaining, and inspecting improper operator training, or a change in operating conditions, pres-
industrial and utility power boilers. Certain parts of this chapter are, sured by economics or environmental conditions. Thus, should it be
in some instances, reiterations of Section VII subsections, which was updated and maintained current, there is an opportunity for Section
done to stress the importance of the information already provided; in VII to become more important to the power generating community.
other instances, however, additional information is provided where it Most U.S. jurisdictions and all Canadian provincial and territorial
is felt to be warranted. Where there are no comments on a section, jurisdictions have adopted certain ASME Boiler and Pressure Vessel
the material is believed to have been covered sufficiently to not need Code Sections into law. Many have also become members of the
additional clarification. The reader is suggested to review existing National Board of Boiler and Pressure Vessel Inspectors (NBBI, or
literature, such as manufacturer’s instructions or company procedures, simply the NB). Typically U.S. and Canadian jurisdictions require
for additional pertinent information. new boilers and pressure vessels to be registered with the NBBI and
Section VII, along with Section VI [1], contains recommended repairs and alterations to be performed by holders of an NBBI Repair
practices and thus serves as a guideline. Consequently, it is consid- Symbol Stamp (R-Stamp, or VR-Stamp in the case of pressure relief
ered a nonmandatory standard; however, Section VII does discuss valves). This means that all work performed on the pressure-retaining
many activities that the Owner–Operator personnel must master parts of a boiler must be performed by accredited organizations using
before a power boiler is commissioned. New personnel, who might approved material control and repair or alteration methods.
not be familiar with boiler operation, maintenance, and inspection,

2.2 INTRODUCTION - SECTION VII


1
Edmund W. K. Chang and Geoffrey M. Halley were the authors of
this chapter for the second and third edition that was initially authored by The Introduction clearly states that the Section VII guide-
Edmund W. K. Chang for the first edition. – Editor. lines apply to power boilers that produce steam for external use

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-19

FIG. 2.12 SAFETY VALVE INSTALLATION

Installation) the bottom of the discharge piping should be posi- Hydrostatic plugs take more effort to install. For many safety valve
tioned well below the top of the drip pan. Especially if the dis- models, hydrostatic plugs are required by the manufacturer during
charge piping has bends that could increase the amount of shipment to prevent damage to the seating surfaces. If that is the
backlash should the valve pop. The side of the drip pan will mini- case, the manufacturer not uncommonly insists that his or her fac-
mize the sideways spray to personnel nearby. tory representative be at the installation site to supervise the hydro-
Before performing a boiler hydrostatic pressure test in which the static plug removal before the safety valve can be put into service;
test pressure is near or exceeds the set pressures, the safety valve otherwise, any warranty is voided. In hydrostatic testing, the
may be removed if it is flanged; or alternatively, gagged, or a hydrostatic plug is placed between the nozzle seat and disk, where
hydrostatic plug may be installed, installing a gag certainly being it protects the seating surfaces while adding space between the
the simplest. (However, one is reminded to not tighten the gag nozzle and disk to increase the compression of the spring, thereby
screw excessively to avoid damage to the spindle and/or seat.) allowing the 112 times working pressure for this type of testing.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-20 • Chapter 2

Another useful piece of information provided in this section is service experience gained by the boiler operator. This section,
that during boiler hydrostatic testing, a slight amount of leakage however, uses 6 mo. to 2 yr. Some Owner–Operators may be
may be expected across the seats because the seats are designed influenced by unit overhaul periods; if they are on a 2 yr. over-
for steam service, not for cold water. haul cycle, these Section VIII pressure-relief valves will be
(The reader is reminded that the information presented in this inspected and tested every 2 yr. If overhaul frequency is to be
section can be used with ASME Section I [2] and the NBIC [4] influenced by operating and maintenance experience, it is impor-
safety valve sections to provide knowledge necessary for the tant to establish a history for each valve. One way to accomplish
inspection, testing, and maintenance of safety valves.) this task is with repair checklists that also serve as written histo-
ries for the valves. The repair checklist records all relevant data
2.6.2 Safety-Relief or Relief Valves on each pressure-relief valve in addition to ensuring that the
This section covers the ASME Section VIII-jurisdiction safety- proper inspection, testing, and repair steps are completed.
relief and relief valves and other pressure-relief valves [7]. Safety- Whenever a replacement valve is procured, or whenever the set
relief valves can be used for steam, air, or gas; in other words, for pressure is changed or conversions are made to the valve, the
compressible fluids and for liquid service. Relief valves are limited proper capacity must be assigned or confirmed. Unlike the provi-
to liquid service and to noncompressible fluids. It is interesting to sion for ASME Section I [2], the provision for ASME Section VIII
note that because safety-relief valves are suitable for nearly all [7] does not provide criteria for assigning valve capacity to a pres-
services, relief can be by full-popping for steam, air, or gas, and sure vessel—a task that is left to the boiler operator instead.
by small releases for liquid service. Relief valves provide for a For feedwater heaters, most boiler operators follow the Heat
gradual release of liquid that is sufficient to lower the pressure; a Exchange Institute (HEI) criteria [8] for the shellside- and the
full, sometimes violent pop does not result. tubeside-relief valves capacities. The tubeside sees boiler feedwater
Again, one should remember that the NBBI VR Symbol Stamp or condensate. The relief valve protects the tubeside should the inlet
program provides for certification of qualified Section VIII and outlet isolation valves be closed and the pressure increases
pressure-relief valve repair organizations. A repair organization from the effect of the shellside heat. Because feedwater and con-
can be qualified for Section VIII pressure-relief valve repairs densate are noncompressible, the tubesiderelief valve needs only to
only, for Section I safety valve repairs only, or for both. The VR release a small quantity of fluid to reduce the pressure.
Symbol Stamp repair program ensures that qualified repair per- The shellside of the feedwater heater normally sees low-
sonnel working under an acceptable quality system program do pressure extraction steam; however, the shellside-relief is based on
repairs on Section VIII pressure-relief valves. The NBIC and/or a tube rupturing in two places within the shell, causing over-pressure
the NBBI should be consulted for additional information. when isolation valves are in closed position. The relief valve is
intended to relieve the feedwater pressure (a noncompressible
2.6.2.1 Inspection and Testing In a power plant, Section VIII– fluid) rather than steam. The reader should refer to the HEI
type pressure-relief valves are found on such boiler auxiliaries as document [8] for further information.
feedwater heaters, reboilers, fuel-oil heaters, air tanks, and certain The sizing or capacity of air tank-pressure-relief or air receiver
piping. In some jurisdictions, the NBBI VR Symbol Stamp repair tank–pressure-relief valves is sometimes based on it being at least
program includes the pressure-relief valves on these ASME two times the air compressor–rated capacity. Again, one is
Section VIII feedwater heaters, reboilers, fuel-oil heaters, and air reminded that the Owner–Operator is given the responsibility of
tanks. Possibly, some Owner–Operators ignore these pressure- determining the required capacity.
relief valves over a period of years, never touching them unless This section briefly reviews some of the available valve-
there was leakage. tightness tests. (Again, the reader should remember that these
The section recommends a periodic inspection, testing, and tests are for Section VIII–type pressure-relief valves; the tests do
maintenance program to ensure proper valve function. (The not apply to ASME Section I–type valves.) The section lists three
modifiers “highly” or “extremely” should perhaps precede the tightness tests: the bubble test (API Std. 527) [9], the wet paper
word “recommends” to stress the importance of ensuring that towel test, and the cold rod test. This section provides sufficient
the pressure-relief valves of the protected equipment will open information for the reader to decide which test is preferred.
at the predetermined pressure and at the minimum required capac- In the section “Lift and Blowdown,” to measure the valve stem
ity, and also of ensuring that the valves are not frozen shut from lift while the pressure-relief valve is tested on a test stand under
years of neglect.) This program should include verification of set shop conditions reveals whether the full-relieving capacity can
pressure, a valve-tightness test, and a test of valve lift (for steam, be reached. The rated lift can be found in the NB-18 publication
air, and gas service). This program does not require the automatic (or red book) [6] in addition to the manufacturer’s data. Only
removal and stripping down of the valve. It depends on the ser- Section I applications require that lift and blowdown information
vice fluid, the time elapsed since the previous repair, and the be included on the original valve nameplate. One is reminded that
service experience recorded. A typical pressure-relief valve main- blowdown characteristics are only meaningful for steam, air, and
tenance procedure includes the following: gas service, in which case at set pressure the valve fully pops or
(1) removing the valve from the equipment for the repair shop; lifts to reach as high a capacity discharge as possible. (Blowdown
(2) performing a close visual inspection; is the difference between the set pressure and the closing pres-
(3) testing on a test stand; and sure.) For Section VIII-type valves [7], the preferred blowdown
(4) disassembling (if necessary). should not exceed 7% of the set pressure or 3 psi, whichever is
greater. Blowdown does not pertain to liquid service in which
If the valve passes the visual inspection and testing, it most very little discharge is necessary for noncompressible fluids to
likely can be returned to the equipment without any further work. relieve the pressure to an acceptable level.
As stated previously, the frequency of this program depends on Finally, it is stressed that when repairs are made the manufac-
the service fluid, the time elapsed since the last repair, and the turer’s instructions must be followed precisely, and the qualified

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-21

pressure-relief valve repair personnel should work with the latest program is that it is too time-consuming. Also, the pressure gage
manufacturer’s repair manual. Each step in the manual should be conditions may be verified by comparing two or more pressure
followed; if any questions or discrepancies arise, the manufactur- gages on the same system. One reason for the comparison method
er’s service or technical group should be contacted and its instruc- is that operating pressures are normally less than the design or
tions followed. In addition, all critical parts should be procured maximum allowable working pressure; thus a certain amount of
from the valve manufacturer or its authorized agent. (Critical plus-or-minus variation is reasonable. However, industrial boilers
parts are the parts of the pressure-relief valve that affect flow and do sometimes operate close to the design pressure.
valve performance.) Many Owner–Operators may be required by various repair pro-
grams (e.g., the NBBI’s R- and VR-programs) to calibrate test
2.6.2.2 Testing This section describes requirements very similar pressure gages within a certain time period of performing a test.
to those of the NBBI VR Symbol Stamp repair program. Certainly, This is a quality control program requirement that encourages fol-
pressure-relief valves should be tested after being repaired to lowing the proper procedure as a whole. For the normal operation
ensure that the valves will function properly. There are various of equipment, however, some Owner–Operators believe that the
methods used for testing. Inexperienced, uninformed organizations comparison method may be sufficient if several pressure gages are
may use the simple hydraulic hand pump for all testing for steam, installed, such as on large boilers. If only one pressure gage is
air, gas, or water service, whereas others use a nitrogen gas source installed, as is the case with many ASME Section VIII–type pres-
connected directly to the underside of the valve to be tested. Such sure vessels as well as smaller industrial boilers, the comparison
organizations eventually learn that these are not appropriate meth- method obviously cannot be performed. Thus a scheduled inspec-
ods because testing should be performed with the same or similar tion and recalibration definitely should be in existence.
test media, and suitable capacity should be provided to test the In an instrumentation recalibration program in which dead-
functions of the valve. weight-testing devices are used to calibrate pressure gages, one
The more informed repair organization may add sophistication should not forget that these devices should be calibrated as well.
to its testing program by constructing a J-watertube test stand– Deadweight testers appear simple and durable; nevertheless,
device for liquid service valves or a nitrogen gas test stand–device weights and other parts of the devices may deteriorate over time.
for steam, air, and gas service valves. These devices are an Depending on the environment in which they are used and stored,
improvement from the first methods, for the amount of capacity the calibration period may range from 3–5 yr. The calibration sys-
for testing has increased, similar testing media are used, and the tem used should be traceable to the National Institute of Standards
strength or thickness of each design will determine the maximum and Technology (NIST).
set pressure test. However, for the nitrogen gas test stand-device,
the capacity is often insufficient because of the sizes usually built,
the source capacity, and the hazards involved when testing is done 2.7 INSTRUMENTATION, CONTROLS,
with a compressible fluid. If steam service valves are tested, it is AND INTERLOCKS—SUBSECTION C5
recommended that the test stand have heating provisions to repli-
cate the inservice temperature of the valve. This short subsection focuses on an important subject requiring
More sophisticated repair organizations build or procure larger specialization, expertise, and experience. In this age of rapidly
test systems with larger volume test vessels and accumulator ves- changing PC technology, control systems are redeveloped con-
sels, digital pressure gages, larger pressure sources, and using the stantly. Instrumentation and controls personnel must stay abreast
proper test medium. They verify the quality of workmanship for of such changes. Only a few years ago, pneumatic-type instru-
all functions (including lift and blowdown) depending on the mentation and analog control systems were still the norm, but
capacity of the test system and the size of valve tested. with the advancement in technology came the digital electronics–
Organized repair programs, such as the NBBI VR Symbol type instrumentation and digital control systems. Because the
Stamp program, require that the pressure-relief valve repair per- response to operation has become faster and the hardware has
sonnel pass the repair organization’s pressure-relief valve training been found to be more reliable in digital systems, pneumatic sys-
program before being allowed to perform repairs. Only qualified tems are quickly becoming obsolete. Parts for older pneumatic
pressure-relief valve repair personnel should be allowed to per- instruments may therefore be unavailable, so plants will find it
form the repairs under the repair organization’s formal program. necessary to change with the times to use hardware that is now
Once qualified, the pressure-relief valve repair personnel should more readily available.
be reviewed annually to ensure that proficiency is maintained. There still remain some small, older units in which the control
Repair includes valve inspection, repair, and testing. Testing panel is located on a convenient operating area. Instruments are
includes installing and removing test gags or hydrostatic plugs visible from the panel where the operator is more interactive with
and witnessing and recording test data on checklists in addition to the equipment and continuously monitors the conditions. In larger
any testing on the test stand. installations, however, central control rooms have become the
norm. In installations that used pneumatic-type instrumentation,
2.6.3 Pressure Gages controls, and interlocks, operators spent most of their time in cen-
Pressure gages are key to the safe, reliable operation of boilers. tral control rooms, listening and watching for alarms, monitoring
These gages should be removed, inspected, and calibrated on a many circular chart recorders and other indicators, and making
routine basis—the normal cycle of which may be once every adjustments with knobs and push buttons. By being remote from
12 mo. This section provides information on the selection and the boiler and its auxiliaries, it was necessary for operators to
care of pressure gages with which all operating personnel should include as much redundancy as possible for safety reasons.
become familiar. Modern power plants have all-electronic instrumentation, controls,
Some operators lack a schedule for tending to their pressure and interlocks—all controlled by a computer or microprocessor—
gages. One reason for not having a pressure gage maintenance often referred to collectively as the distributed digital control system

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-22 • Chapter 2

(DCS). Response is faster, hardware more reliable, and CRT-based of the ASME Boiler and Pressure Vessel Codes as the Authorized
consoles can display many controls on one or two screens. The dis- Inspectors are. Plant Inspectors should have detailed design
play area of coverage has become smaller, and controlling and knowledge of the components used so that during inspections any
adjustment points are more quickly accessible. nonconformance can be evaluated and decisions can be made for
Control engineers have become necessary to program the sys- the proper corrective action. Plant inspectors should also be
tems, using logic to institute various control strategies. In many knowledgeable of welding and nondestructive testing (NDT)
plants, the instrumentation and controls maintenance personnel methods, for repairs usually involve some welding and inspection
are called I&C technicians; as with the operators, they must have by these methods. Plant Inspectors perform the condition assess-
a thorough knowledge of the instruments, controls, and interlocks ment inspection to ensure that the boiler is in good operating con-
for the safe, reliable operation of the power boiler. dition and that it will operate safely and reliably. Authorized
Inspectors also perform the inspection to ensure safe operation in
2.7.1 Indicators and Recorders; addition to performing the operating permit inspection.
Controls and Interlocks With jurisdictions having mandated the use of the NBIC [4],
some Owner–Operator have received accreditation as part of the
These two rather brief sections provide basic information for
NB Owner/User Inspection Organization (O/U Organization).
less-knowledgeable personnel and provide a good review for
One requirement for accreditation is that the O/U Organization
more experienced personnel involved with instruments, controls,
will employ Inspectors with valid NB Owner/User Commissions,
and interlocks. From the basic information presented in these sec-
who obviously should have as much knowledge and experience in
tions, readers have many publications available to expand their
inspecting power boilers as Authorized Inspectors, as well as
knowledge on specific subjects. Regarding the section “Checking
plant Inspectors. Inspections may include the inservice inspec-
and Testing,” boiler operators may become complacent with that
tions for jurisdictional-operating permit requirements as well as
section’s provisions for the maintenance of automatic controls;
the repair and alteration inspections. When the plant Inspector is
they may forgo a regular, complete conditional and operational
also the O/U Commissioned Inspector, the two inspections—
check of instruments, controls, and interlocks. These two sections
condition assessment and operating permit—usually become one
therefore recommend annual conditional and operational checks
inspection. It is believed that this method of inspection to ensure
to ensure safe, reliable boiler operation.
safe, reliable power boiler operation gets better results than using
Adding pictures or illustrations should enhance and provide
a third party Authorized Inspector, for the O/U Commissioned
better understanding of the intricate subject of this subsection.
Inspector is typically very familiar with the equipment inspected
and is normally made aware immediately of all problems as they
are happening and therefore can (when necessary) respond faster.
2.8 INSPECTION—SUBSECTION C6 Bias should not be an issue with the required NB controls in
place. The O/U Commissioned Inspector has the same fears as the
This subsection concerns the inspection of inservice or operat- Authorized Inspector when violations and penalties become
ing power boilers. The particular inspections include the follow- issues. One such fear is the loss of his or her NB Commission.
ing: When the Owner–Operator does not have the O/U Organization
(1) condition assessment-type of inspections performed during accreditation, the plant Inspector must perform the first inspec-
operation and during outages; and tion, preferably by using a checklist of the items to be inspected
(2) jurisdictional-operating permit inspections also performed immediately followed by the use of discrepancy punchlists.
during operation and during outages. Follow-up to verify completion of the punchlist is then required;
the Authorized Inspector will then perform the jurisdictional-
The information covered in this subsection is similar to that operating permit inspection.
provided in the NBIC for NBBI-Commissioned Inspectors [4].
Section VII recommends two separate inspections: one by the 2.8.1 Inspection of Internal Surfaces and Parts
Owner–Operator, the other by the Authorized Inspector or Juris- The first paragraph of this section specifies the basic purpose for
diction Inspector. (For Code inspections: Authorized Inspector the internal inspection and what areas should be inspected. Whether
inspects new construction whereas an Inspector inspects inservice it is the plant Inspector, the O/U Commissioned Inspector, or the
boilers.) These inspections also depend on whether the jurisdic- Authorized Inspector performing the inspection, the physical struc-
tion where the power boiler operates is an NBBI member, ture should be examined to determine its adequacy for service. The
whether it mandates the NBIC, and whether it has adopted the R next paragraph suggests that the reader review ASME Section I,
Symbol Stamp program requirements for the repair of boilers and Fig. PG-58.3.1 (now PG-58.3.1a) titled “Code Jurisdictional Limits
pressure vessels. for Piping—Drum-Type Boilers” (See Fig. 2.1) or Fig. PG-58.3.2
To ensure safe, reliable power boiler operation, these inspec- titled “Forced Flow Steam Generators” [2] to define the limits of
tions should be independent. Owner–Operator Inspectors may the power boiler–operating permit inspection.
have varying titles: plant Inspectors, boiler Inspectors, boiler Obviously, this section pertains to the internal inspection during
engineers, or boiler maintenance engineers, for example. outages. All listed safety precautions must be taken to protect per-
Whatever their title, however, this subsection specifies that sons entering the boiler. Most boiler operators use an entry permit
Owner–Operator Inspectors should be knowledgeable by educa- system regardless of whether a “confined space” is involved. Sign-
tion and experience with the construction, inspection, operating, in and sign-out sheets, which must be completed, are posted at all
and maintenance procedures for power boilers, and should be manholes. Inspection inside the boilers should be of the “buddy
specifically designated by plant managers. Stated another way, system” type in which the Inspector does not enter the boiler unless
plant Inspectors are boiler experts, their decisions of which are to he or she is accompanied by another person standing by outside the
be followed. These plant Inspectors should be as knowledgeable manhole. A good safety reference is provided in the NBIC [4].

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-23

Especially when inspecting large power boilers, it is very itoring include magnetic-particle inspection of welds to detect the
important that the plant Inspector or the O/U Commissioned onset of fatigue and/or creep-damage cracking; ultrasonic thick-
Inspector be in good physical condition. As specified in the sec- ness testing to monitor corrosion and erosion; video-probe internal
tion’s first paragraph, the entire boiler shall be inspected. There inspections to monitor corrosion, erosion, fatigue, corrosion- fatigue,
are many tight, small openings where an Inspector, to gain entry, and creep damages; metallography in-situ replications to inspect
must hang on to a structural member and pull his or her weight up for the onset of creep damage; and steamside-oxide-scale-thickness
through the opening. In addition, there are many dirty, dusty measurements to estimate the remaining useful life in superheater
spaces into which the Inspector must crawl on his or her hands and reheater tubes. Tube samples are removed from the water-
and knees. Naturally the Inspector must not fear small, confined walls to assist with the determination for chemical cleaning and
spaces. for tube failure analyses.
The details provided in this section, along with checklists and When headers are videoprobe-inspected, access may be
11– * 812 – drawings, enable the plant Inspector to perform a rea- through the header handhole plugs; however, some utilities avoid
sonable inspection and be able to record items requiring immedi- going through these handhole openings for fear of causing dam-
ate attention or consideration. For boiler operators without their age to the header over time. Such utilities prefer to put forth more
own checklists, the checklists in the Non-Mandatory Appendices effort by cutting tubes near each end of the header and installing a
provide a good starting point. Plant Inspectors must know in pull-string to assist the videoprobe camera and insertion tube.
advance what they will be inspecting. In addition, they must be Less damage is created by cutting and re welding small-diameter
able to document findings and provide the necessary punchlists to thin tubes. In fire-tube boilers, areas to be inspected should
correct any nonconformances. include the water leg at the back of water-cooled reversing cham-
For the inspection of the steam drum interior, plans should be bers and the upper surfaces of the furnace, both to check for
made to remove necessary internals to inspect the full length of an accumulation of scale or other insulating deposits. In addition,
the steam drum. Some manufacturers have steam drum internals the tube-to-tubesheet joints and tubesheet ligaments should be
with designs that make access extremely difficult. Loose, worn, or inspected for signs of leakage or cracking. Other areas to be
missing components will not be seen if the steam drum access is inspected should include all stays and also the welds at the
limited to only the two manhole ends. furnace-to-tubesheet joint.
When inside the furnace of a watertube boiler, the Inspector
should pay particular attention to any signs of burner flame 2.8.2 Inspection of External Surfaces and Parts
impingement. Flame impingement, plus a dirty interior waterwall, The external inspection should take place both as a hot inspec-
may at first show bulges or blisters on the fireside. Later, these tion during operation and a cold inspection during an outage. As
bulges or blisters may cause tube leaks unless the boiler is inter- implied in this section, comparisons between hot and cold condi-
nally cleaned. There appears to be a misuse of the term blister. A tions are made in addition to other checks. The checklists in the
blister may occur if the overheated tubewall had internal disconti- Non-Mandatory Appendices also cover external surfaces. To
nuities such as laminations or seams. Overheating caused by make inspections more orderly when developing site-specific
flame impingement and internal deposits may cause the tube checklists, external items should be segregated into those items to
material to separate outward at the lamination or seam. A bulge, be checked when the boiler is in operation and those to be
on the other hand, occurs through sound tubewalls and occurs checked during an outage.
from the through-wall metal overheating that may be caused by For piping, hot and cold inspections must be performed by the
the flame impingement and internal deposits. During operation, plant Inspector for the main steam line, or for the hot reheat lines
burner flame impingement can be observed through the furnace or cold reheat lines if they exist, and it is also recommended that
view ports. During any overhaul outage, the plant Inspector the boiler feedwater line be both hot- and cold-inspected. These
should verify that the view ports are clear and that repairs are are all considered high-energy lines because of the high pressures,
made before the boiler goes back on line. or the high temperatures, or both. In case of damage, personnel
The refractory should be inspected, especially for tangent-tube are at risk and damage to equipment may require a costly and
boilers and wherever it is used for sealing (such as for tube pene- long outage period for repairs. Pipe support indicators and scales,
trations). Maintenance personnel do not always realize that refrac- whether constant-support– or variable-support–type spring pipe
tory does not last forever; the average lifespan is 10–15 yr. hangers, should be recorded and evaluated. The supports should
depending on the abuse to which it is subjected. Boiler washes provide a free-floating piping system to avoid undue stress to the
coupled with the sulfur in the flue gas help make the refractory piping system and connections to the boiler and other equipment.
brittle and crumbly. Vanadium in fuel oils is also known to cause Excessive vibrations should be evaluated and analyzed to prevent
refractory deterioration. Ensuring that the refractory is replaced at fatigue-creep damages. Piping stress analysis programs are avail-
the first signs of deterioration can reduce hot-spot forced outages. able and can be used with the proper training.
For the older watertube boilers, many Owner–Operators find it For boiler-operating permits, most jurisdictions require that a
necessary to conduct condition assessments beyond the visual 6 mo. external inspection be performed when the boiler is operat-
inspections, which can possibly help ensure that an unplanned ing. Obviously doing so will show whether the various compo-
forced outage does not occur. By anticipating problems, the boiler nents are functioning properly. If the Owner–Operator is part
operator may be able to properly plan and budget for the repair or of an NB O/U Inspection Organization, the O/U Commissioned
replacement. Much of this condition assessment involves the Inspector can perform the necessary external inspections during
monitoring of certain critical components over time, and it should these 6 mo. inspections. For external inspections while the boiler
be noted that many of the more modern flame safeguard controls is operating, visual inspections will include inspecting the safety
used on industrial boilers have firing-cycle counters and elapsed valves, gage glasses, and pressure gages. Also, valves should be
run-time indicators built into their annunciation system for this inspected for signs of leakage through packing glands and gas-
very purpose. Techniques used for the condition assessment mon- kets; any leak has the potential to cause serious damage if allowed

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-24 • Chapter 2

to continue, so it should be corrected at the earliest possible no longer true that “Alterations to boiler pressure parts should be
opportunity. made by an organization that holds a valid ASME Certification
of Authorization.” As of the 2010 Edition 2011a Addenda,
2.8.3 Care and Maintenance Section VII has not updated this paragraph.
In addition to covering housekeeping requirements, this section In the NBIC-mandated jurisdictions, to verify whether or not
covers the inspection documentation, records, and logs that typi- the component needing welded repair or alteration conforms
cally must be kept—all constituting the history and events precipi- to the rules of the NBIC [4], the reader should refer to the
tating a problem as well as the conditions that require fixing. It is ASME Code Section I Fig. PG-58.3.1a for drum-type boilers or
desirable to enter all relevant information into a computer program Fig. PG-58.3.2 for forced-flow steam generators [2]. The draw-
from which the information can be retrieved quickly and easily. ings in these figures show what is boiler proper and what is
Many Owner–Operators have created computerized work boiler external piping and joint. If the components to be weld-
orders, with which planning and scheduling, monitoring, updat- repaired or altered conform to these two drawings, the R Symbol
ing, and reporting are included. The plant Inspector may use these Stamp applies and the repair organization must necessarily be a
computerized systems to input punchlist items so that such items Certificate Holder.
will be dealt with immediately, if necessary. Status records, along If the Owner–Operator organization has a maintenance group,
with other information, can also be quickly retrieved. it is possible (if the Owner–Operator believes it to be beneficial)
More formal inspection reports or records of each inspection by to apply for and obtain the NBBI R Symbol Stamp Certificate of
the plant Inspector may need to be treated in separate book for- Authorization. As an R Symbol Stamp Certificate Holder, the
mats for reporting and archival purposes. These reports are usually Owner–Operator is permitted to perform welded repairs and alter-
separate from the records assembled from the work order system, ations, including the emergency repair of boilertube leaks.
and list the findings, provide evaluation and analyses, and present However, to qualify for the R Symbol Stamp Certificate of
recommendations. However, because computer scanners are now Authorization, the Owner–Operator must have (as a minimum)
readily available, these reports may be entirely computerized for qualified personnel including welders; qualified welding proce-
storage and easy retrieval. dures; acceptable repair and/or alteration procedures; an accept-
The plant Inspector or O/U Commissioned Inspector should able quality control or quality system program; and a third-party
have easy access to all boiler information, especially for repair inspection agreement with Authorized Inspection Agency (e.g.,
instructions. Because most boiler drawings were originally drawn the Hartford Steam Boiler Inspection & Insurance Company). In
and issued in large size, the plant Inspector may find the reduced- lieu of the Authorized Inspection Agency, the Owner–Operator
size boiler drawings in the manufacturer’s data books useful, or may choose to be an NB O/U Inspection Organization that pro-
he or she may prefer to reduce large drawings into 11– * 812 – size. vides its own repair inspections and in service inspections.
It is stressed that 11– * 821 – size drawings are easier to file in a
binder for each boiler, can be quickly reproduced in the copier, 2.9.2 Maintenance
and can also be reproduced by scanner when repair instructions The purpose of this section is clearly stated in its first paragraph—
are communicated. (It is so true that a “picture is worth a thou- namely, that this section assists the maintenance group in the preven-
sand words.”) As-built details can also be recorded on 11– * 812 – tion of unscheduled outages by defining the potential trouble spots
sheets for more convenient filing and retrieval. and conditions that should be checked during scheduled maintenance
outages or overhauls. It is stressed that because this presentation is in
general terms, the manufacturer’s literature should be reviewed for
2.9 REPAIRS, ALTERATIONS, AND detailed requirements.
MAINTENANCE—SUBSECTION C7 Maintenance checklists or checks, are presented by component
based on historical data of items requiring maintenance attention.
2.9.1 Repairs and Alterations (The actual checklist format is given in the Non-Mandatory
This section was added after the 1980 edition to acknowledge the Appendices B and D.) In addition, these maintenance checklists
wide acceptance of the NBIC by jurisdictional authorities [4]. This can be used as inspection checklists. Owner–Operator personnel
section is surprisingly brief for a subject of marked importance. can use these checklists as a basis to create new maintenance
However, the NBIC is covered more extensively in previous sub- checklists, or for inspection and overhaul procedures and also the
sections, to which the reader should refer back for additional Owner–Operator maintenance program. Despite the many reminders
information. for the reader to refer to the manufacturer’s literature, these check-
For maintenance personnel who are not too familiar with the lists are quite comprehensive and worth studying. However, Sec-
NBIC, it stressed that the Code applies to repairs and alterations tion VII will be enhanced if it took the extra step and provided the
of power boilers and pressure vessels that are operating and hence answers to why each maintenance check item was necessary. For
not of new construction. A more precise explanation is given by example, why do you check the condition of burner throat refrac-
Bernstein and Yoder in Ref. [10], who specify that once Section I tory, or why check for slag build up on refractory? With more
requirements are met and the data reports are signed, Section I no “answers to why,” Section VII would be a “go to” book.
longer controls the repairs and alterations. In many jurisdictions, Operating checks related to maintenance are also presented to
the NBIC assumes responsibility and provides the rules to follow. prevent unscheduled shutdowns simply because the operators are
The maintenance personnel should know or otherwise determine the personnel using the equipment and able to see firsthand the
if the jurisdiction is an NBBI member and if that jurisdiction actual operating conditions. The checks and checklists provided
requires welded repairs and alterations to be performed by an in this section and in Non-Mandatory Appendices C and E help to
organization holding an NBBI R Symbol Stamp Certificate of promptly detect problems that usually can be corrected before
Authorization. This is contrary to Subsection C7.100 where it is they become serious.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-25

The applicable component checks should be reviewed, from of copper, in which case the chemical cleaning is a two-process
which company procedures should be developed if they are operation with the second cleaning process used to remove the
nonexistent or otherwise improved. In many cases, company copper coating. Therefore, taking waterwall-tube samples essen-
inspection and overhaul procedures were developed many years tially have the following two purposes:
previously and thus have not been reviewed to incorporate latest
developments. (1) to determine the amount and composition of the internal-
tube deposit, and
(2) to determine which chemical cleaning solution is best.
2.10 CONTROL OF INTERNAL CHEMICAL It is very important where the tube samples are taken and how
CONDITIONS—SUBSECTION C8 many are taken for analysis. If specific boilertube problems did
Most power plant personnel understand that water treatment not occur, and if no particular areas to target exist, tube samples
and monitoring of the water used in the boiler and auxiliaries are normally are taken in the highest heat flux area. For oil-fired
critical in preventing boilertube failures and internal corrosion watertube boilers, this may be approximately 2 ft. (.6 m) above
damage. As with the other subsections, this one provides a good the top burners along this elevation of the furnace. However, for
introduction or review of the control of chemical conditions boilers experiencing tube failure from overheating problems,
within power boilers. Eight headings are covered, and under each caused by the combination of internal deposits and flame
heading Section VII attempts to do the following: impingement tube samples may be taken in the waterwall where
the signs of flame impingement are most distinct.
(1) state the type of water treatment problem; It is obvious that selecting the correct tube samples for analysis
(2) describe how each problem may be recognized; and is not guaranteed, for random samples are taken with the hope
(3) provide information about how these problems may be that they represent typical boilertube conditions. The more tube
corrected. samples taken, the better the chance of getting a correct sample;
for instance, many boiler operators take at least four tube samples
Many references are available for further study; see [11], [12], for the cleaning analysis. However, the more tube samples that are
and [13], for example. taken, the more work that is required in replacing the removed
tube sections. A domino effect may be initiated, whereby in addi-
2.10.1 Internal Cleaning of Boilers tion to creating more work there is a greater chance of there being
This section briefly discusses the internal cleaning of boilers, defective welds when replacing the removed areas and also a
including detergent cleaning (alkaline boilout), chemical cleaning greater chance of there being more areas where the tube weld root
(via acids or solvents), and mechanical cleaning. This section causes water flow disturbances upstream, allowing deposits to
specifically refers to new boilers or new construction. Both deter- collect there.
gent cleaning and chemical cleaning are part of the standard It is important that as a minimum, the boiler manufacturer’s
start-up procedure for most new boilers, for they remove the manu- post construction chemical cleaning piping setup for the new
facturing and erection contamination. Of interest to note is that boiler be followed for the inservice boiler cleaning. The manufac-
boilers operating under 900 psig (6 MPa) are not chemically turer should know how to ensure that the cleaning fluids reach all
cleaned to remove mill scale but only detergent-cleaned because the areas of the boiler. However, should any flow problems not antici-
operating temperature does not warrant acid or solvent cleaning. pated by the manufacturer occur, the boiler operator engineering
This section is short, considering the importance of cleaning. and chemical personnel must be sufficiently knowledgeable to
The manufacturer’s instructions and the expertise of the chemical make the proper adjustments for the flow of the cleaning fluids to
cleaning companies are expected to be used extensively. However, reach all areas of the boiler.
adequate information is given in this section for understanding Nonetheless, the boiler operator engineering and chemical per-
why cleaning is necessary. sonnel should evaluate and be aware of the possible restrictions
Inservice boiler internal cleaning follows basically the same the different flow paths the chemical cleaning fluid may have
procedure as for new boilers; however, items needing further con- from the downcomers to and up the wall tubes. The longer paths
sideration do exist. Inservice boilers mainly involve chemical or circuits with multiple bends will have less flow through them
and/or mechanical cleaning; detergent cleaning is rarely per- during operation and cleaning. These circuits will most likely
formed unless there is a need to remove oil and grease. For exam- have more deposits and will require more cleaning effort. In most
ple, an intrusion of oil during operation or if a considerable cases a forced flow cleaning system with external heating is neces-
portion of the boiler was replaced would both necessitate deter- sary to clean these longer circuits. The traditional natural circula-
gent cleaning. Replacing large sections of waterwall-tube panels tion chemical cleaning method does not provide adequate cleaning
justifies detergent cleaning for the removal of installation contam- for the larger utility boilers with differing circuit configurations.
inants and shipping preservatives. The retubing of firetube boilers This method uses the existing burners to provide the natural circu-
also falls into this category. lation to move the chemical cleaning fluid through the boiler. The
This section mentions that taking tube samples and analyzing circuits with the lesser flow resistance will continuously receive
the deposit is essential in the cleaning of inservice boilers. The the cleaning fluid, while the circuits with the most flow resistance
chemical cleaning company receives representative samples of will get very little flow.
tube sections and experimentally determines if cleaning is neces- In areas of questionable flow and/or in tube-damaged areas, it
sary and, if so, which cleaning solution is optimal. (Usually this is may be prudent for one to install flanged-cleaning-tube sample
a trial-and-error procedure.) In mixed-metal condensate-feedwater pieces. These are tube sections routed outside of the waterwall
systems, waterwall-tube deposits may include an adhering layer with isolation valves and flanges so that the tube sample can be

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-26 • Chapter 2

removed and visually inspected to monitor the cleaning process— where freezing may be a concern. Three separate methods of dry
especially helpful when removing an adhering layer of copper. layup are recommended: the thoroughly-dried-with-desiccant
One should remember that in jurisdictions where welded repairs method, the circulated-dry-air method, and the nitrogen-fill blanket
and alterations follow the NBBI R Symbol Stamp requirements, method.
chemical cleaning piping additions within the boiler proper and In the thoroughly-dried-with-desiccant method, it is critical that
boiler external piping jurisdictions follow specific procedures and the boiler be dried thoroughly and kept dried throughout the storage
requirements. The O/U Commissioned Inspector or Authorized period. A desiccant or a certain amount of moisture-absorbing
Inspector must be involved in these processes. material must be placed in the drums and replaced periodically, and
Of course, with environmental regulations becoming more strin- all openings must be tightly closed. Although these tasks may seem
gent, the “environmental” engineer or consultant must be involved easy, it is not at all simple to ensure that all boiler internal surfaces
for both possible air and water discharge concerns and permitting. have been dried. In addition, there is a tendency for one to forget
about replacing the moisture-absorbing material on schedule.
2.10.2 Laying-Up of Boilers In the circulated-dry-air method, the boiler must also be dried
Older, less-efficient boilers are being taken out of service and thoroughly before one commences the storage and air circulation.
stored for future use. In areas where shortage of generating capac- The air must flow over all areas, although to have it reach all areas
ity has been experienced—and the reserves are still marginal— may seem impossible.
utilities may choose to not eliminate these boilers until it is cer- The nitrogen-fill blanket method obviously is the most appeal-
tain that they will not again be needed; such boilers are being ing method used and is applicable to large industrial and utility
laid-up or stored. Similarly, certain industrial processes may oper- boilers. Nitrogen gas is filled as the boiler is drained, and a 5 psig
ate only during certain times of the year so they may also be laid- (35 kPa) nitrogen gas pressure is maintained throughout the stor-
up or stored for the remainder of the year. age period. Oxygen in water is minimal, and air in-leakage is
This section provides useful information for all sizes of boilers: prevented with the 5 psig (35 kPa) nitrogen pressure. Operating
both watertube and firetube. In addition, it provides the reader or maintenance personnel must remember to maintain this 5 psig
with available options. It is the boiler operator’s responsibility to (35 kPa) pressure. Maintaining a nitrogen cap or blanket can be
locate and obtain the references necessary for detailed informa- difficult for boilers in service. Closed valves do not seal tightly.
tion. Members can go to the EPRI publication [5]; otherwise the Safety is a concern if personnel need to enter the boiler spaces;
boiler manufacturer can be consulted. therefore, the proper amount of oxygen must be present when per-
sonnel enter the boiler.
2.10.2.1 Waterside There are two methods of laying-up or stor- Utilities have used vapor phase corrosion inhibitors (VPCI) as a
ing boilers, both of which depend on the length of storage time and dry lay-up option. The VPCI chemicals are proprietary having
climatic conditions. These methods are the wet lay-up method and been around for years. A utility has reported its use for boiler lay-
the dry lay-up method. up during a long outage for generator repairs. After draining the
The wet lay-up method is recommended for shorter periods boiler the VPCI powder was dusted in the steam drum using an
(4 days to 2 weeks), at which time the boiler may be needed on air horn, and the drum shut tight. The boiler was rinsed before the
short notice (during standby) and where freezing is not a concern. boiler went back on line. The rinse water may contain ammonium
This section gives recommendations for boilers operating below benzoate; therefore, disposal must be dealt with accordingly. Not
1,000 psig (7 MPa) and those operating above 1,000 psig (7 MPa). seeing VPCI discussed reinforces the need to review and update
In either case, the goal is to minimize the amount of oxygen in the Section VII regularly with the other ASME Boiler and Pressure
water; this is accomplished by initially adding an oxygen scav- Vessel Codes.
enger to the water to minimize oxygen content, and it is also nec-
essary to keep the pH reading close to 10 to minimize hydrogen 2.10.2.2 Fireside This section is useful for any condition and
ions and electro-chemical reactions. The wet method also has two situation; it is not applicable solely for layup or storage. Boiler
different applications: the boiler and superheater stored and filled operators may apply the information in this section for the firesides
to the top, and the boiler stored at normal operating water level. during overhaul outages whether they are for only 2 wk. or for
In the first application, to prevent oxygen infiltration during the longer than 8 wk. Although short, this section provides useful
storage period, the boiler is filled to the top (including superheater information concerning possible fireside corrosion problems and
tubes) and the pressure is maintained greater than that of the their solutions.
atmosphere. A nitrogen pressure or cap of 5 psig (35 kPa) can be A fundamental fact is that sulfur-bearing fuels create corrosion
applied and maintained during the storage period. Regardless of problems to surfaces in contact with the flue gas and also to sur-
whether one uses a boiler pressure or a nitrogen cap, the pressure faces that receive the runoff of the boiler washwater. Wherever
gage should be monitored at least weekly to ensure positive pres- there is refractory—especially old, worn refractory—the possibility
sure in the boiler. Maintaining a nitrogen cap can be difficult if exists that the ash deposits will get into and between the porous,
not impossible to maintain for older boilers. crumbly refractory and metal surfaces. During the boiler wash
In the second application, the boiler can be stored with the water performed during overhauls, this ash deposit is wet and may
at the normal operating level and with the superheater empty. With remain wet or damp throughout the overhaul outage.
this method, the water is treated with a sufficient amount of an Boiler washes for layup or overhauls should be a three-step
oxygen scavenger and a 5 psig (35 kPa) nitrogen cap is maintained operation such as follows:
throughout the boiler and superheater spaces. Again, the goal is to
minimize the oxygen concentration in the water and in the empty (1) water-wash with suitable pressure equipment;
spaces, as well as to minimize air in-leakage. (2) neutralize all surfaces using an alkaline solution (1% sodium
The dry lay-up method is recommended for longer storage peri- carbonate [Na2CO3]); and
ods (greater than 2 weeks) where the boiler is not on stand-by and (3) dry all surfaces.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-27

Owner–Operators should evaluate the process suitable for their nal deposit are embedded thermocouple and tube samples. Tube
needs. Some may neutralize, wash, and dry before an overhaul. samples were reviewed in previous sections. Embedded thermo-
With this process the boiler and air heater are first soaked couples have been in existence for many years, but perhaps its
overnight using an overhead spray system with an acid neutraliza- cost discourages more widespread use in power boilers.
tion solution. Then the boiler is washed. Nowadays you do not hear about utilities making new embedded
During the layup, the accepted practice is to maintain a maxi- thermocouple installations to monitor waterwall tube deposit
mum 50% relative humidity. build up. With the thermocouple junction embedded in the fireside
The reader may use the information provided in section tube-wall, changes in temperature can be monitored to track
C8.900, “Fireside Conditions,” to supplement this short section, deposit buildup and therefore to suggest when chemical cleaning
for C8.900 contains information about some severely corrosive is needed.
elements of coal and fuel oils. This section provides the funda- The two aforementioned monitoring tools are used to monitor
mental information by reviewing the various publications written internal deposits after they are formed. Section C8.430 Internal
about the subject. Deposit Monitoring, briefly mentions a deposit weight density
(DWD) range (20 g/ft2 to 40 g/ft2) when cleaning is needed. It
2.10.3 Deposits and Internal Corrosion would be more useful if existing cleaning guidelines specifying
This section discusses the water-touched boilertube internal three ranges when 1) cleaning not needed, 2) should consider
surfaces—mainly the waterwall tubes, which experience the high cleaning, and 3) must clean are included. This detailed informa-
heat flux from radiant heat. In the Fundamentals subsection, nat- tion will specify that these three ranges are dependent on the
ural circulation was explained. If the flow created by natural boiler operating pressure. Obviously, to minimize or prevent the
circulation is not able to sufficiently remove the heat from the internal deposits from building up, the best tool is proper water
burners, the tube metal temperature design limit will be exceeded treatment or a good water chemistry control program. Such a pro-
and overheating damage will occur. This section discusses situa- gram may include the following:
tions when deposits (i.e., scale, sludge, and oil) on the inside
(1) selecting the proper water treatment method, such as:
surface of the watertube boilertubes can impede the transfer of
AVT (all volatile treatment)
heat from burner flame to the water or to the steam-water mixture
CPT (congruent phosphate treatment)
flowing inside the tubes. In this discussion of the aforementioned
EPT (equilibrium phosphate treatment)
deposits and internal corrosion, damage has a strong relationship
OT (oxygenated treatment)
with these deposits. Similar comments apply to the waterside
PT (phosphate treatment)
surfaces of fire-tube boilers.
(2) establishing adequate control limits or ranges of the con-
trolled items, such as the pH, oxygen, and chloride level;
2.10.3.1 Deposits Scale, sludge, and oil deposits are discussed.
(3) setting the proper locations and quantity of sampling
It is apparent that the title of section C8.420 should be “Sludge and
points, such as at condensate pumps, economizers, and
Oil.” Scale and sludge are highly dependent on the quality of the
steam drums;
water source. Most smaller boilers do not have pretreatment facil-
(4) providing modern, functional monitoring instrumentation
ities such as demineralizers that remove impurities (minerals and
or meters;
salts) by ion exchange; the most they may have are filters to
(5) ensuring the proper training of all personnel involved with
remove particles from the water source. Their water treatment to
items (1)–(4) of this list, including operators and chemists;
control scale and sludge is based on proprietary additives provid-
and
ed by water treatment companies. In many cases, some form of
(6) ensuring that the program is working, with management
phosphate is added to react with the water impurities, helping to
and all personnel participating in it.
form soft compounds that do not adhere to the tube surface and can
be removed only by adequate blowdown. A brief description of sampling and testing of water for boilers
Other sources of deposits include the corrosion products of the is given in section C8.800, “Sampling, Testing, Controlling, and
“preboiler” equipment including the condenser, feedwater heaters, Reporting of Analyses of Water.” In developing the water treat-
and associated piping. Air in-leakage can accelerate corrosion of ment program, the responsible water chemistry personnel can
the carbon steel surfaces. For mixed-metal (i.e., copper and steel) refer to Table C8.8-1, “Methods for Sampling of Water and
feedwater heaters, the air in-leakage, oxygen, and ammonia accel- Steam”; Table C8.8-2, “Methods of Analysis for the Control of
erate copper tube corrosion, the products of which enter the boiler Water for Boilers”; and Table C8.8-3, “Useful Tests for the
and, under certain conditions, will deposit and adhere especially Control of Water for Boilers.” EPRI members have several publi-
to the inside surfaces of the boilertubes that face the fires. cations for personnel to reference in their program development
[5]. Once formulated, instituted, and working, this water treat-
2.10.3.2 Internal Corrosion Besides creating an insulating ment program will help to ensure that the water treatment does
effect and causing the boilertube metal to overheat, deposits can not cause overheating or corrode boiler components.
act as sponges, concentrating certain types of corrosives against It should be noted that Table C8.8-3 Useful Tests for the
the tube surface to cause “underdeposit corrosion.” This section Control of Water for Boilers, along with its notes is an informa-
discusses some forms of underdeposit corrosion including caustic tive and handy guide for boiler operating personnel to get a basic
corrosion or gouging, acid corrosion, and hydrogen damage. EPRI understanding of which chemicals are used to control corrosion,
has published several reports describing these failure mechanisms deposits and carryover. Section VII can be enhanced further by
in detail [13]. including a separate table listing and describing the use of water
treatment chemicals. Besides hydroxides, phosphates, and sul-
2.10.3.3 Internal Deposit Monitoring and Control of Water fites, adding polymers, chelants, and amines can make Section
Treatment The two monitoring tools mentioned to monitor inter- VII a more handy reference.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-28 • Chapter 2

2.10.4 Corrosion Cracking of Boiler Steel ing, it is theorized that hydrogen ion can enter the heat-affected
There are three categories of corrosion cracking reviewed in zones (HAZ) of the weld and combine with other hydrogen ions
this section: stress-corrosion cracking, corrosion fatigue cracking, in the steel to form the larger hydrogen molecule. Under certain
and hydrogen damage. Stress corrosion, or caustic embrittlement, conditions, and also because of the welded component loading,
is caused by a stress-corrosion combination and results in cracking the larger hydrogen molecule applies sufficient pressure to its sur-
along the grain boundaries of the steel, whereas corrosion fatigue roundings to cause cracking.
is caused by cyclic mechanical or thermal stresses that result in
transcrystalline cracking or cracking through the steel grains. 2.10.5 Auxiliary Equipment Corrosion
Additional, more detailed information on these two types of dam- Section C8.560 Auxiliary Equipment Corrosion briefly
age is provided; refer to the list of references [11, 13]. describes feedwater component “corrosion caused by dissolved
EPRI reports that the susceptibility of stress-corrosion cracking gases, especially oxygen, in the feedwater.” To keep Section VII
is more likely in austenitic stainless steel material having contact current, it should also include the “flow-accelerated corrosion
with hydroxides and chlorides [13]. Because stainless steels are (FAC) mechanism in which a normally protective oxide layer on a
rarely permitted by ASME Section I [2] for surfaces in contact metal surface dissolves in a fast flowing water. The underlying
with water, this type of damage normally is found in the super- metal corrodes to re-create the oxide, and thus the metal loss con-
heater section. tinue [14].” FAC is different from erosion corrosion mechanism
In addition, EPRI reports that corrosion fatigue cracking is because it does not involve impingement of particles causing a
found mainly in water-contacted boilertubes, including supply mechanical wear on the surface. It has the opposite effect of cor-
and riser tubes and the economizer [13]. Since corrosion fatigue rosion caused by dissolved gases (oxygen). The presence of oxy-
cracking (CF) is a major boiler tube failure mechanism, this sec- gen helps to prevent FAC.
tion should be expanded to provide more information. This addi- FAC normally affects carbon steel piping. The use of chrome-
tional information could be as follows: CF initiates on the inside moly piping will minimize or eliminate FAC. Boiler operators
surface of the boiler tube, commonly at rigid attachments such as with more air inleakage conditions experience less FAC damages.
buckstays and windboxes. Besides being transcrystalline or trans- FAC is a concern because of the possibility of larger diameter,
granular, the cracking is longitudinal to the tube axis, usually higher pressure piping thinning and rupturing causing property
multiple and parallel. The common method to inspect for CF is by damage and injury.
videoprobe inspection requiring access into the tube. Research is
being conducted by organizations such as EPRI to perfect nonde-
structive inspection methods using ultrasonic and digital radiogra- 2.11 PREVENTING BOILER FAILURES—
phy systems to eliminate cutting access windows in the boiler SUBSECTION C9
tubes. As an example, an older boiler operated in a cyclic manner
has tight 90 deg. tube-bends in the economizer above the inlet This subsection, the culmination of ASME Section VII, briefly
header. During its later service life, cyclic stress works on the reviews much of the material discussed in its preceding subsec-
existing residual stresses of these tight bends, resulting in crack- tions. The reader is reminded that the purpose of Section VII is to
ing at the sides of the bends where the original bending had promote safety in the use of power boilers. Throughout this chapter,
formed an egg-shaped bend cross section with sharper stress ris- safe, reliable power boiler operation, maintenance, and inspection
ers on both sides. After the damaged bend is removed, it is cut have been stressed. This subsection reviews some conditions that
perpendicular to the crack. The visual examination reveals the affect this safe, reliable operation, maintenance, and inspection.
cracks at the sides of the bend originating from the inside and cor- It reviews the three general classifications of boiler failure,
rosion products wedged inside the crack. To summarize, the fol- which are repeated as follows:
lowing appear to have influenced the cracking: (1) caused by overpressure;
(1) cyclic stresses caused by on/off cycling; (2) caused by structural weakening; and
(2) residual stresses and stress risers on the sides of the tight (3) caused by errors in the operation of combustion equipment.
90 deg. tube bends; and In the discussion of overpressure, equipment required to pre-
(3) corrosive condition on the waterside. vent boiler failures caused by overpressure is reviewed together
The water treatment program records should be reviewed for with how the equipment can be misused. The rest of this subsec-
the dissolved oxygen and pH readings, especially for sampling tion reviews precautions to be taken against conditions such as
points near the economizer inlet. The EPRI report mentions that furnace explosions or implosions.
low pH readings may promote hydrogen cracking or embrittle-
ment at the crack tip, thus increasing the probability of the crack 2.11.1 Overpressure
opening even further [13]. Of course, the level of oxygen in the The equipment or instrumentation included for the prevention
boiler water can affect the oxide scale growth as the cycling stress of overpressure boiler failure includes the following:
breaks off the protective coating at the side of the tube bend. (1) steam pressure gages;
An excellent description of hydrogen damage is provided in (2) water glasses or gage glasses;
this section. Hydrogen damage is included with internal corrosion (3) high- and low-level alarms;
or under-deposit corrosion. Actually, hydrogen damage can be (4) automatic trips;
included with both underdeposit corrosion and the stress-corrosion (5) safety valves; and
group, but the description in this section is reasonable. Hydrogen (6) fusible plugs.
is the smallest atom appearing on the chemistry periodic table,
and because of its small size, it apparently has a tendency to enter The operation and maintenance information provided on the
carbon steel grain boundaries and react with the carbon. In weld- listed equipment is very useful. Even the most experienced boiler

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


COMPANION GUIDE TO THE ASME BOILER & PRESSURE VESSEL CODE • 2-29

operator may find some of the information new and reasonable. subsection is essentially a review of the preceding subsections, it
The Owner–Operator can always use the information provided as does contain some precautions not previously discussed that the
an instruction manual or as a source of review. reader will find useful. Examples of such precautions are the
Pressure gages are covered in Subsection C4, “Appurtenances.” In sequence for operating the double blowdown valves; the necessity
this section, operational errors and maintenance errors of pressure of not using waterwall-blowdown valves during boiler operation;
gages are stressed. One error includes the failure to periodically test and the need to repair leaks at thick-walled components to prevent
for accuracy or instrument calibration. Many boiler operators fail to erosional damage.
verify that pressure gages are accurate; they may rely on comparison
with uncalibrated pressure gages already installed throughout the 2.11.3 Operation of Combustion Equipment
boiler unit. Because of the hazard from explosion when fuels are burned,
Gage glasses are discussed briefly in Subsection C2, “Boiler this section notes that the review in Subsection C9 is not intend-
Operation.” In this section, the operational and maintenance ed to provide detailed safety rules governing the design, installa-
errors of water glasses or gage glasses are stressed, and more use- tion, operation, and maintenance of fuel-burning systems. For
ful basic information is provided. Many boiler operators fail to such detailed information, the reader must consult other sources,
test water columns and gage glasses on a regular basis—if at all. such as the ASME CSD-1 “Controls and Safety Devices for
Level alarms should be tested at the same time that the water Automatically Fired Boilers,” for use on small boilers under 12.5
columns are tested. Most boiler operators understand readily that million Btu/hr. fuel input. The reader may also consult the appro-
ASME Section I PG-60.1, “Water Level Indicators,” permit the priate section of the NFPA 85 Boiler and Combustion Systems
remaining gage glass to be shut off but maintained in serviceable Hazards Code. The section “Fuel Burning Equipment” of
condition when both remote level indicators are in reliable opera- Subsection C3, “Boiler Auxiliaries,” should be used for general
tion [2]. Such activity constitutes “seeing is believing”-type think- recommendations and precautions.
ing. However, it is possible that many boiler operators neglect this A reminder: Only properly trained operators familiar with the
remaining gage glass because the lights are broken, the glass is fuel-burning equipment being operated should be in charge of the
dirty, the shut-off valves are frozen shut, and the bottom portion is boiler units.
plugged with debris. Many operators also forget the “locked-and-
sealed open” requirement of ASME Section I PG-60.3.7 for the
first valves off of the steam drum [2].
A common misunderstanding pertaining to gage glasses con- 2.12 FINAL NOTES
cerns “when the direct reading of gage glass water level is not This chapter has repeatedly emphasized that ASME Section
readily visible to the operator in the area where immediate con- VII contains valuable information for the power boiler opera-
trol actions are initiated.” Many boiler operators still believe that tion, maintenance, and inspection personnel. Section VII is a
a system of mirrors or fiber optic cable system is required. practical boiler book, a good review for experienced personnel
Section VII can have added value if it included clarifications such and a good teaching aid for less-experienced personnel. However,
as mentioning that two independent, reliable remote level indica- it cannot possibly provide all the details for such numerous
tors will satisfy this “direct reading” requirement making mirrors topics. Therefore, manufacturers’ instructions and other reputable
and fiber optics unnecessary. sources must be consulted for a more complete understanding of
each subject presented. Procedures and check-lists for operation,
2.11.2 Weakening of Structure maintenance, and inspection are critical requirements; they must
The review is begun in this section by listing its three cate- exist, be used regularly, and be reviewed periodically.
gories of failure caused by weakening of the structure: Finally, re-establishing a Section VII subcommittee or subgroup
(1) weakening of pressure parts; is warranted. It appears that the Section I Standard Committee is
(2) failure of supports; and not able to keep up with or give attention needed to revise and
(3) mechanical damage. update Section VII. Being made available for sale, ASME should
provide the purchaser with a product that is current.
Then, this section lists and reviews conditions that cause weak-
ening of the pressure parts. These conditions include the following:
(1) overheating; 2.13 REFERENCES
(2) loss of metal from corrosion;
(3) weakening of the furnace from improper combustion or 1. ASME Boiler and Pressure Vessel Code Section VI, Recommended
flame impingement; and Rules for the Care and Operation of Heating Boilers; The American
(4) soot blower erosion. Society of Mechanical Engineers.
2. ASME Boiler and Pressure Vessel Code Section I, Rules for the
The review on the weakening of pressure parts begins with the
Construction of Power Boilers; The American Society of Mechanical
boiler start-up, then proceeds to cover many necessary precau- Engineers.
tions. Again, it is stressed that the boiler operator must use the
proper procedures (and checklists) to ensure safe, reliable power 3. ASME B31.1, Power Piping; The American Society of Mechanical
boiler operation. It is highly recommended that checklists for Engineers.
boiler start-up be developed and followed during every start-up 4. ANSI/NB-23, National Board Inspection Code; The National Board
period. of Boiler and Pressure Vessel Inspectors.
The review continues with coverage of control of water level, 5. EPRI TR-107754, Cycling, Start-up, Shutdown, and Layup Fossil
erosion (via soot blowers), internal corrosion, external corrosion, Plant Cycle Chemistry Guidelines for Operators and Chemists; The
boiler shutdown, and boiler out-of-service time. Although this Electric Power Research Institute.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms


2-30 • Chapter 2

6. NB-18, Pressure-Relief Device Certifications; The National Board of 11. Steam: Its Generation and Use, Babcock & Wilcox, 40th ed., 1992.
Boiler and Pressure Vessel Inspectors.
12. Kohan, A. L., Boiler Operator’s Guide, McGraw-Hill, New York, 4th
7. ASME Boiler and Pressure Vessel Code Section VIII, Division 1, ed., 1998.
Rules for the Construction of Pressure Vessels; The American Society
13. Dooley, R. B., and McNaughton, W. P., “Boiler Tube Failures: Theory
of Mechanical Engineers.
and Practice,” EPRI TR-105261, Vols. 2 and 3, Water-Touched and
8. Standards for Closed Feedwater Heaters; Heat Exchange Institute, Steam-Touched Tubes, The Electric Power Research Institute, 1996.
Inc., 1998.
14. Flow-accelerated corrosion, Wilikipedia®, Wilikipedia Foundation,
9. Seat Tightness of Pressure-Relief Valves, ANSI/API Standard 527, Inc.
3rd ed., July 1991.
10. Bernstein, M. D., and Yoder, L. W., “Introduction to Power Boilers
Section I of the ASME Boiler and Pressure Vessel Code,” PVP
Conference, Honolulu, July 1995.

Downloaded From: http://ebooks.asmedigitalcollection.asme.org/ on 03/16/2015 Terms of Use: http://asme.org/terms

You might also like