Professional Documents
Culture Documents
Process Process
Economics Safety
What is Process Economics?
When you design a plant, try to When you operate a plant, try to make
make it financially viable by it more profitable by considering
considering • Operating costs
• Location & layout • Materials, labor and utilities
• Capital needed • Depreciation
• Financing, taxes, insurance
• Time value of money
• Plant overhead costs
• Other resources including manpower,
• General expenses
energy, electricity, water.
• Revenue
• Return on investment, payback period
• Productivity
• Alternative investment
• Sales price
• Government policy
• Marketing plan
• etc. • Replacement of equipment
Process Economics in the plant design
1. Inception (Idea generation)
9. Production
8. Start-up
and Trial Runs
2. Economic Possibility
Analysis (accuracy ±30%)
7. Construction
3. Development of and installation
Data for design
6. Procurement
4. Final Economic Evaluation 5. Engineering (Purchase)
(accuracy ±10%) Design
Process Economics
Chapter 1:
Estimation of Capital
Capital & Cost Estimation Investment
Chapter 2:
Estimation of Equipment Cost
Product Cost & Revenue
Chapter 3:
Project Economic Evaluation
Chapter 1: Capital and Cost Estimation
Goals:
• List the components of Fixed Capital and Working Capital.
• Estimate the capital investment using various methods
• Estimate the equipment cost after adjusting time and capacity
Types of Capital Investment
Overview: Types of Capital Investment
Capital Investment is the procurement of money to further a company’s
business goals.
What costs do you need to build a plant?
What costs do you need to operate a plant?
Key points:
• Types of various capital investment
• Fixed Capital Investment (FCI)
• Working Capital Investment (WCI)
• The components of each capital investment
Why do we need capital investment?
Firm Type:
• Profitability:
Profit or Non-Profit
• Business nature:
Manufacturing, Trading, Service
Direct Indirect
Equipment Buildings/Offices/Shops
Piping Warehouses/Labs
Plant
Components
Instruments Shipping/Receiving/Utilities
Foundation Supervision/Engineering
Insulation Construction/Contractors
Construction
Overhead
Site preparation Contingencies
Components of Capital Investment
Takeaway:
• Capital investment is needed to build and operate a plant!
• FCI is used for machinery and infrastructure, covering the majority of TCI.
• WCI is related to operation, before sales revenue is available, and it will
be recovered later.
• Ratio of WCI/TCI varies and a typical percentage for most chemical plants
is 15%.
Estimation of Capital Investment
Overview: Estimation of Capital Investment
Whether to proceed with a new project proposal depends on the money needed.
Questions to be answered
• How to estimate the investment to build a plant?
• How to compromise between accuracy and convenience on estimation?
Key points:
• List the detailed components in capital investment
• Apply common methods to estimate capital investment
• Understand factors affecting the accuracy and convenience of estimation
Major Components of Capital Investments
• What do you need to consider for your plant:
type of equipment
size of equipment
construction material
approximate purchase price of each equipment from a supplier, a reference, or past-
experience
Cn = E (1 + f1 + f2 + f3 + ... + fn)
Where E = delivered equipment cost, f1, f2,…= multiplying factors for piping, electrical, instrumentation, etc.
• For method A & B, if the costs of major equipment are given, you should estimate
the total capital investment to build a plant.
• The question is how to obtain the cost for major equipment, since they
o may not be easily ready from suppliers, and
o may change with size, time, and other conditions
Estimation of Equipment Cost
Overview: Estimation of Equipment Cost
Key points:
• Understand that the cost of purchased equipment is the basis of several methods for
estimating capital investment.
• Select a suitable method to estimate equipment cost for different situations
A. Vender price quotes
B. Summary graphs
C. Past cost data
• Incorporate time and capacity effect into the cost estimation
Methods to estimate equipment cost
B. Summary Graphs
Study most common equipment
Preliminary cost estimation
Methods to estimate equipment cost
Published in Chemical
Engineering monthly
Cost index: scaling factor
• When no cost data is available for the particular size, estimates can be obtained by
using the six-tenths-factor rule.
• If the cost of another capacity of the same type equipment B is available, thus:
0.6
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐴
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐴 = 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐵
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐵
Cost index: scaling factor
0.6
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐴
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐴 = 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐵
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐵
Notes:
• Applicable for similar equipment with regard to type, materials, temperature and pressure range, etc.
• In general, this concept should NOT be used beyond a tenfold range of capacity.
• The 0.6 factor should only be used in the absence of other information.
• The 0.6 rule for most equipment is oversimplified since the actual values vary.
Typical exponents for equipment cost as a function of capacity
Equipment Size range Exponent “n”
Blower, centrifugal 0.5-4.7 m3/s 0.59
𝒏 Centrifuge, solid bowl, carbon steel 7.5-75 kW drive 0.67
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐴
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐴 = 𝐶𝑜𝑠𝑡 𝑜𝑓 𝐵
𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝐵
Compressor, reciprocating, Air-cooled, two- 0.005-0.19 m3 0.69
stage, 1035 kPa discharge
Evaporator (installed), horizontal tank 10-1000 m2 0.54
Heat Exchanger, shell-and-tube, fixed sheet, 10-40 m2 0.44
NOTE: carbon steel
Sizes for both equipment should locate in the Pump, centrifugal, horizontal, cast steel 4-40 m3/s-kPa 0.34
range given in this table.
Reactor, glass-lined, jacketed (without 0.2-2.2 m3 0.54
drive)
Reactor, stainless steel, 2070-kPa 0.4-4.0 m3 0.56
Separator, centrifugal, carbon steel 1.5-7 m3 0.49
Tank, carbon steel, glass-lined 0.4-4.0 m3 0.49
Tower, carbon steel 5×102-106 kg 0.62
Summary: Estimation of equipment cost
• Now you know the cost estimation for major equipment, then you can also
estimate capital investment using the relevant methods.
Summary of Chapter 1: Capital & Cost Estimation
Now, you are able to estimate the capital needed for building a plant.
Next, we will calculate the product cost when we operate a plant and if the plant is profitable.