Professional Documents
Culture Documents
PMP Focus Area Test - Scope Management - With Answers
PMP Focus Area Test - Scope Management - With Answers
Total Questions: 10
Test Description
This practice quiz specifically targets your knowledge of the Project Scope Management knowledge
area.
Test Questions:
1. Which of the following is not a Group Creativity Technique used in the Collect Requirements process?
B) Pareto chart
C) Mind mapping
D) Affinity diagram
2. Linda is a project manager in charge of an online banking project. The project has completed phase 1
and is moving into the next phase of the project. For phase 2, which of the following processes must be
performed first?
A) Define Scope
B) Identify Stakeholders
3. Which of the following processes is not a part of the Project Scope Management process?
A) Create WBS
B) Control Quality
C) Control Scope
D) Collect Requirements
4. The WBS is finalized by establishing control accounts for the work packages and a unique identifier
from a code of accounts. This provides a structure for hierarchical summation of:
A) Scope creep
B) Scope verification
D) Scope control
6. While managing a project, you have included the product acceptance criteria in the Quality
Management Plan. While reviewing your plan, a senior manager asks you to reconsider this. You then
realize that what you have done is incorrect. Where should you place the product acceptance criteria?
A) Project Charter
B) Defining and controlling what is and what is not included in the project.
A) The WBS is a detailed project plan and includes the effort, resources and dates on which the tasks
for the project are completed.
B) The WBS is a task oriented decomposition of work that identifies each task and the resource
required to accomplish the task.
D) The WBS is a Gantt chart which contains details about the project deliverables required to be done
by the project team.
10. A project manager wants to use a group decision-making technique to generate, classify and
prioritize requirements. Which of these is not a valid group decision-making technique?
A) Dictatorship
B) Singularity
C) Majority
D) Unanimity
Answers
1.
B - The Pareto chart is not a Group Creativity Technique. The others are valid techniques. Additional
techniques are Brainstorming and the Delphi Technique. [PMBOK 5th edition, Page 115] [Project Scope
Management]
2.
B - Linda needs to initiate the second phase of her project. There is no need to revisit the Develop
Project Charter process. However, she needs to revisit the Identify Stakeholders process to determine
any change in the stakeholders for the second phase of the project. Stakeholder identification is a
continuous process. [PMBOK 5th edition, Page 31] [Project Stakeholder Management]
3.
B - Control Quality is not a part of the Project Scope management process. [PMBOK 5th edition, Page
105] [Project Scope Management]
4.
D - The WBS is finalized by establishing control accounts for the work packages and a unique identifier
from a code of accounts. This provides a structure for hierarchical summation of costs, schedule and
resource information. [PMBOK 5th edition, Page 132] [Project Scope Management]
5.
A - Scope creep is often viewed negatively, but can be managed using a change control process. [PMBOK
5th edition, Page 137] [Project Scope Management]
6.
C - The project scope statement documents and addresses the characteristics and boundaries of the
project and its associated products and services, as well as product acceptance criteria and scope
control. [PMBOK 5th edition, Page 123] [Project Scope Management]
7.
B - Project Scope Management includes the processes required to ensure that the project includes all
the work required and only the work required to complete the project successfully. It is primarily
concerned with defining and controlling what is included and what is not included in the project.
[PMBOK 5th edition, Page 105] [Project Scope Management]
8.
C - The WBS is a deliverable oriented hierarchical decomposition of the work to be accomplished by the
project team to accomplish project objectives. [PMBOK 5th edition, Page 132] [Project Scope
Management]
9.
C - Validate Scope is the process of formalizing acceptance of the completed project deliverables by the
customer or sponsor of the project. [PMBOK 5th edition, Page 133] [Project Scope Management]
10.
B - Singularity is not a valid method to reach a group decision. The other choices are valid methods to
reach a group decision. [PMBOK 5th edition, Page 115] [Project Scope Management]