Submitted to:
Submitted by: Muhammad Junaid
Registration #: 2017-TE-20
Rawalpindi-Islamabad Metrobus
Introduction:
Islamabad is the Capital City of Pakistan and the ninth largest city in the country. Located within
the Islamabad Capital Territory (ICT), the population of the city has grown from 100,000 in
1951 to 1.30 million in 2012. The greater Islamabad – Rawalpindi Metropolitan Area is the third
largest conurbation in Pakistan with a population of over 4.5 million inhabitants.
The concept of Metro Bus System (MBS) is a rapid mode of transportation that can provide the
quality of rail transit with the flexibility of buses. MBS has been implemented in several cities
throughout the world as a low-cost, rail-like method of moving people quickly and efficiently.
1|Page 2017-TE-20
CM
WBC of project:
2|Page 2017-TE-20
CM
PROJECT OVERVIEW
-
% Complete
100%
% COMPLETE
Status for all top-level tasks. To see the status for subtasks, click on the chart and update the
outline level in the Field List.
LATE TASKS
3|Page 2017-TE-20
CM
WORK BURNDOWN
Shows
WORK work stats for all top level tasks.
STATS
WORK OVERVIEW -
4|Page 2017-TE-20
CM
5|Page 2017-TE-20
CM
6|Page 2017-TE-20
CM
Activity list
%
Task Name Duration Start Finish Predecessors Resource Names Cost Variance CPI SPI
Complete
Sat Thu
ROAD WORKS 351 days 100% Rs 9,697,201.00 0 0
4/17/21 6/16/22
PROJECT Sat Thu
56 days 100% Rs 103,504.00 0 0
KICKOFF 4/17/21 6/24/21
Contract Award 1 day Sat 4/17/21 Sat 4/17/21 100% Rs 0.00 0 0
Mobilization of
Mon Thu
Machinery and 10 days 3 Supervisor 100% Rs 7,600.00 0 0
4/19/21 4/29/21
Equipment
providing of
6 days Fri 4/30/21 Fri 5/7/21 4 100% Rs 0.00 0 0
project laboratory
preliminary joint Wed Site
8 days Sat 5/8/21 5 100% Rs 29,184.00 0 0
survey 5/19/21 Engineer,Supervisor,Surveyor
detailed joint Thu Mon Labour,Site
10 days 6 100% Rs 37,840.00 0 0
survey 5/20/21 5/31/21 Engineer,Surveyor
centre line
10 days Tue 6/1/21 Fri 6/11/21 7 Site Engineer,Surveyor 100% Rs 28,880.00 0 0
marking
Thu
shift of control 5 days Sat 6/12/21 8 100% Rs 0.00 0 0
6/17/21
project kickoff
0 days Fri 6/18/21 Fri 6/18/21 9 100% Rs 0.00 0 0
complition
Fri Mon
EARTWORK 110 days 100% Rs 2,506,120.00 0 0
6/18/21 11/1/21
Thu
clearing 30 days Fri 6/18/21 10 Tractors with trolley 100% Rs 186,960.00 0 0
7/22/21
Compaction of Thu
15 days Fri 7/23/21 12 100% Rs 0.00 0 0
natural ground 8/12/21
Tractors with trolley,Tyre
excavation of Wed mounted crane, Dumper ( 18
10 days Fri 8/13/21 13 100% Rs 725,280.00 0 0
unsuitable material 8/25/21 Ton ), Excavator,Site
Engineer
Thu
granular backfill 10 days Thu 9/9/21 14 Dumper ( 18 Ton ) 100% Rs 203,200.00 0 0
8/26/21
formation of
Mon Compactors,Site
embankment from 15 days Fri 9/10/21 15 100% Rs 355,320.00 0 0
9/27/21 Engineer,Surveyor
roadway
formation of Compactors,Surveyor,Tractor
Tue
embankment from 10 days Fri 10/8/21 16 s with trolley,Tyre mounted 100% Rs 509,920.00 0 0
9/28/21
borrow excavator crane
Compactors,Geotechnical
prepration of Mon
20 days Sat 10/9/21 17 Engineer,Protect 100% Rs 525,440.00 0 0
subgrade 11/1/21
Manger,Surveyor
eartwork Mon Mon
0 days 18 100% Rs 0.00 0 0
complition 11/1/21 11/1/21
SUB BASE AND Mon Thu
120 days 100% Rs 3,612,287.00 0 0
BASE 11/1/21 3/24/22
breaking of
Tue Fri Dumper ( 18 Ton ),
existing road 20 days 19 100% Rs 837,280.00 0 0
11/2/21 11/26/21 Excavator,Labour
pavement structure
Dumper ( 18
prepration of Sat
30 days Sat 1/1/22 21 Ton ),Aggregate[1 100% Rs 1,233,635.00 0 0
subbase 11/27/21
ft3],Compactors
Aggregate[1 ft3],Site
water bound Mon Tue
20 days 22 Engineer,Water[1 100% Rs 43,607.00 0 0
macadam 1/3/22 1/25/22
tank],Sand[1 ft3]
scarification of
Wed
existing road 15 days Sat 2/12/22 23 Labour,cutter 100% Rs 14,640.00 0 0
1/26/22
apvemnet
disposal of
Mon Mon Excavator,Tractors with
existing unusable road 13 days 24 100% Rs 651,040.00 0 0
2/14/22 2/28/22 trolley,Tyre mounted crane
apver
7|Page 2017-TE-20
CM
Resources sheet:
Material Max. Cost/Us Base
Resource Name Type Initials Group Std. Rate Ovt. Rate Accrue At
Label Units e Calendar
Materia Prorate
Aggregate ft3 A Rs 35.00 Rs 0.00
l d
Materia Prorate
Bitumen kg B Rs 85.00 Rs 0.00
l d
Materia Prorate
Cement bags C Rs 530.00 Rs 0.00
l d
Materia Prorate
Water tank W Rs 1,000.00 Rs 0.00
l d
Materia Prorate
Sand ft3 S Rs 12.00 Rs 0.00
l d
Materia Prorate
Steel kg S Rs 65.00 Rs 0.00
l d
Concrete 100 Rs Prorate Standar
Work C Rs 308.00/hr Rs 0.00
Mixer % 0.00/hr d d
Tyre mounted 100 Rs Rs Prorate Standar
Work T Rs 0.00
crane % 2,900.00/hr 0.00/hr d d
100 Rs Rs Prorate Standar
Excavator Work E Rs 0.00
% 2,581.00/hr 0.00/hr d d
Dumper ( 18 100 Rs Rs Prorate Standar
Work D Rs 0.00
Ton ) % 2,540.00/hr 0.00/hr d d
100 Rs Prorate Standar
Gantry Work G Rs 0.00/hr Rs 0.00
% 0.00/hr d d
Tractors with 100 Rs Prorate Standar
Work T Rs 779.00/hr Rs 0.00
trolley % 0.00/hr d d
100 Rs Rs Prorate Standar
Compactors Work C Rs 0.00
% 2,600.00/hr 0.00/hr d d
8|Page 2017-TE-20
CM
Resources usage:
Resource Name Work
Unassigned 0 hrs
Contract Award 0 hrs
providing of project laboratory 0 hrs
shift of control 0 hrs
project kickoff complition 0 hrs
Compaction of natural ground 0 hrs
eartwork complition 0 hrs
base and sub base work complition 0 hrs
cold milling 0 hrs
Aggregate 2 ft3
9|Page 2017-TE-20
CM
10 | P a g e 2017-TE-20
CM
11 | P a g e 2017-TE-20
CM
12 | P a g e 2017-TE-20
CM
13 | P a g e 2017-TE-20