Tangguh Expansion Project –LNG EPC
PT Prospera Brillar Indonesia – Material Receiving and Traceability Procedure
Table of Contents
1 Introduction ............................................................................................................ 4
2 Scope ...................................................................................................................... 4
3 Purpose ................................................................................................................... 4
4 Reference Document ............................................................................................. 5
4.1 CONTRACTOR Document ........................................................................................................... 5
4.2 SUBCONTRACTOR Document ................................................................................................... 5
5 Definitions & Abbreviations .................................................................................. 5
5.1 Definition ....................................................................................................................................... 5
5.2 Abbreviations ................................................................................................................................ 5
6 SUBCONTRACTOR Responsibilities .................................................................... 6
7 Receiving Material Inspection Procedures .......................................................... 6
7.1 Delivery Check .............................................................................................................................. 6
7.2 Material Inspection........................................................................................................................ 6
7.3 Surveillance Check ....................................................................................................................... 7
7.4 Reporting ...................................................................................................................................... 7
8 Traceability Material Procedures .......................................................................... 7
8.1 Incoming Material Traceability ...................................................................................................... 7
8.2 In-process Material Traceability.................................................................................................... 8
List of Appendix
Appendix 1 – Material Receiving Inspection Report ................................................................................... 9
Appendix 2 – Overage, Shortage, Damage Report .................................................................................. 10
Appendix 3 – Non Conformance Report ................................................................................................... 11
Appendix 4 – Overage Shortage and Damage Register .......................................................................... 13
Appendix 5 – Material Traceability Table .................................................................................................. 14
Revision History
Amendment Revision Amender Name Amendment
Date Number
18 March 2019 01 Chairulzen First Issue
Related documents
Document Document name Description of Content
number
1 Introduction
BP Berau Ltd., hereafter known as COMPANY, is the operator of Tangguh LNG, a two traion atural gas
(NG) liquefaction facility in Bintuni Bay, Papua Indonesia. The facility includes associated onshore
infrastructure, two offshore platforms, pipelines and twelve wells. These facilities are the Trains 1 and 2
developments at Tangguh.
COMPANY has initiated the Tangguh Expansion Project to commercialise the incremental resource into
high margin gas markets based on a single LNG (liquefied natural gas) train expansion (Train 3).
Tangguh Expansion Project will consist of new offshore facilities, including wellhead platforms and
pipelines, and onshore development on the existing Tangguh brownfield site. The new onshore facilities
will include one additional natural gas liquefaction train of a similar design and capacity to the existing
trains, an onshore receiving facility (ORF), new LNG and condensate loading berth, additional boil off
gas (BOG) recovery, utilities, flares and the infrastructure to support logistics and the associated
increase in the temporary and permanent workforce.
The Tangguh Expansion Project comprises of the following new facilities:
• [New] Onshore Receiving Facility (ORF)
• [New] LNG Train 3
• [New] Condensate Stabilization Train 3
• [New/Inter connection] Plant Utility Facilities
• [New] LNG Loading System
• [New] Condensate Loading System
• [Expansion] Integrated Control and Safety System (ICSS)
• [Expansion] Telecommunication System
• [New] Trestle Jetty Stucture
• [Expansion] Onshore Infrastructure
• Hazardous and Non-Hazardous Waste Management System
2 Scope
This Procedure applies for receiving Inspection of the materials for piping and pipe support pre-
fabrication which supplied by CONTRACTOR.
3 Purpose
The purpose of this procedure is to describe the inspection to be taken on the receiving materials to be
performed by Material Controller and Material Inspector in carrying out the work accordingly to the stated
requirements of Tangguh Expansion Project.
4 Reference Document
5.1 Definition
PROJECT : TEP - TANGGUH EXPANSION PROJECT
COMPANY : BP Tangguh
CONTRACTOR : Ciyoda Saipem Tripatra Sae
SUBCONTRACTOR : PT. Prospera Brillar Indonesia
PMT : CONTRACTOR Project Management Team
VENDOR : Supplier of materials tools and/or equipment including related documentation
and sevices
5.2 Abbreviations
CPI : Company Provided Items
ITP : Inspection and Test Plan
MIR : Material Inspection Report
MRF : Material Request Form
MRR : Material Receiving Report
MTT : Material Traceability Table Approved for Construction
NCR : Non Conformity Report; Document recording a non-fulfillment of a
requirement.
OSDR : Overage Shortage and Damage Report
PL : Packing List
PO : Purchase Order
6 SUBCONTRACTOR Responsibilities
QHSE Manager/Coordinator shall be responsible and Material Inspector responsible to carry out this
procedure accordingly.
Material Inpsector is responsible for verifying the quality and conformity of the materials based on the
applicable standards/requirements listed on the QCP/ITP, prepare and revieweing the Inspection and
Testing Reports.
Material Inspector responsible for raising NCR if any non-conformance identified on receipt of materials.
Material Controller is responsible for receiving, storing, preservation arrangement and issuing material
and liasising with the Material Inspector for inspection.
Material Controller is responsible to transferring identification with stamping to all materials, and ensure
that all prior issued to Construction shall clear identification, mill certificates and other relevant
documents of all material.
Storeman is responsible to managing all functions of stock materials. They ensure that stock levels and
track inventory spending, as well as keeping records. And they also will be mark all materials received.
QC Inspector is responsible for preparing Material Traceability Table upon verification of approved MRIR
and identification in materials. Material Traceability Table prepared according to cutting plans and
approved isometric/fabrication drawings.
7.4 Reporting
Once the material accepted by SUBCONTRACTOR Material Inspector, is placed into the store/laydown
area, and issue a Material Receiving Inspection Report (MRIR) for CONTRACTOR and COMPANY
review.
The MRIR shall include the following information:
• Date of Inspection.
• The PO No. and the numbers of items inspected.
• Material description (including dimension).
• Reference to the Material Certificates.
• The Heat No or the Part No/Tag No., MTC No or COC no. from suppliers/vendors.
• The quantities inspected.
• Status of Inspection Result (accept/reject/hold)
• System/Sub System as applicable
• Any non-compliance, which may require Overage Shortage and Damage Report (OSDR) and or
Non-Conformity Report (NCR) to solve a specific problem.
Material Traceability Table (MTT) will be prepared by QC Inspector during inspection of Marking and
Cutting process. QC Inspector will be record all identification that transferred to materials. As material
traceability record, MTT will be issue for CONTRACTOR and COMPANY review.
PLANT LOCATION:
LOCATION:BINTUNI BAY,PAPUA - INDONESIA QC CODE QCP REFERENCE
PROJECT TITLE:TANGGUH
TANGGUH EXPANSION PROJECT PIP-010201M
010201M PIP-0102
SUBCONTRACTOR
SUBCONTRACTOR: Report No.: Page 1 of
No. Material Description P.O. P.O. Stock No. Material Quantity UOM Heat Unique Mill cert status Remark
No item Grade No. No
Order Receive acc rej
No
TANGGUH
ANGGUH EXPANSION– PROJECT
ROJECT EXECUTE
LNG EPC
Location: Location:
IRID No.:
Position:
Date:
TANGGUH
ANGGUH EXPANSION– PROJECT
ROJECT EXECUTE
LNG EPC
Date:
Accepted as proposed
Accepted with
Comments
Rejected
Position:
Date:
Position:
Date:
REMARKS: