Professional Documents
Culture Documents
DOCUMENT NUMBER DOCUMENT TITLE REV. CODE ISSUE STATUS DOCUMENT STATUS
870310-S-1247064-CST-H03-0001 Quality Control Plan Endorsement For Piping Prefab & Erection 04 F- FINAL A. ACCEPTED
NO COMMENTS ORIGINATOR SUPPLIER RESPONSE REASONS NAME &TITLE SECTION AFFECTED COMMENT STATUS
Additional attachment ITP list and forms list refer to A. Agreed, Comment will
2 TEP-930-SPE-QA-BP4-0021_B06_Quality Control MADE WISNAWA PUTRA Comment has been done YUNIARTO Section 5 Agreed - Closed
be implemented
Plan For Piping Work
Revision History
Amendment Revision Amender Name Amendment
Date Number
31/JAN/2019 01 Yodhi R-Submit For Review
28/MAR/2019 02 Yodhi R-Submit For Review
11/JUL/2019 03 Mangojaktua F-Final
23/SEP/2019 04 Yuniarto F-Final
Related documents
Document Document name Description of Content
number
TABLE OF CONTENTS
1. Introduction ........................................................................................................ 4
1.1 PROJECT OVERVIEW .................................................................................................................. 4
1.2 SCOPE & OBJECTIVE ................................................................................................................... 4
1.3 DEFINITION AND ABBREVIATIONS............................................................................................. 5
5. ATTACHMENTS ................................................................................................ 14
5.1 ITP LIST........................................................................................................................................ 14
5.1.1 General ITP for Initial Inspection: ................................................................................................. 14
5.1.2 Specific ITP for Construction: ....................................................................................................... 14
5.2 FORMS LIST ................................................................................................................................ 14
5.2.1 Inspection and Test Report Forms: .............................................................................................. 14
1. Introduction
1.1 PROJECT OVERVIEW
BP Berau Ltd, hereafter know as COMPANY, is the operator as TANGGUH LNG, a two train natural
gas (NG) liquefaction facility in Bintuni Bay, Papua Indonesia. The facility includes associated onshore
infrastructure, two onshore platforms, pipelines and twelve wells. These facilities as are the Train 1 and
2 developments at Tangguh.
COMPANY has initiated the Tangguh Expansion Project to commercialize the incremental resource
into high margin gas markets based on a single LNG (liquefied natural gas) train expansion (Train 3).
Tangguh Expansion Project will consist of new offshore facilities, including wellhead platforms and
pipelines, and onshore development on the exisiting Tangguh brownfield site. The new onshore
facilities will include one additional natural gas liquefaction train of a similar desighn and capacity to the
existing trains, an onshore receiving facility (ORF), New LNG and condensate loading berth, additional
boil of gas (BOG) recovery, utilities, flares and the infrastructure to support logistics and the associated
increase in the temporary and permanent workforce.
The Tangguh Expansion project comproses of the following new facilities :
[New] Onshore Receiving Facility (ORF)
[New] LNG Train 3
[New] Condensate Stabilization Train 3
[New/Inter Connection] Plant Utility Facilities
[New] LNG Loading System
[New] Condensate Loading System
[Expansion] Integrated Control and Safety System (ICSS)
[Expansion] Telecommunication System
[New] Trestle Jetty Structure
[Expansion] Onshore Infrastructure
Hazardous and Non-hazardous Waste Management System
This document contain the details of quantity control quantity activities to be done during the execution
of the welding works as following :
Welding Qualification procedure and welding personnel qualification activities.
Welding at Site for pipe-supporting elements and miscellaneous steel structures of electrical /
instrumentations & others.
The quality control plan for welding activities associates with equipment manufacturing or material
supply at vendor or supplier shop premise are not covered by this document. The quality control plan
for that scope should be covered by IDS as written in the Vendor or Supplier Requisition.
The document is issued, at Project Level, as Quality Control Plan complete with project information’s,
Project requirements and contractual obligations.
Certificate : Record of the inspection results, kept on the applicable predefined form
and signed by all parties as per involvement code (see 3.3)
Construction
Organization : Organization Performing the installation and/or fabrication and/or
construction
Contractor : Organization appointed by OWNER to perform the Works
Discipline : A certain branch of knowledge, an area of activity
DWG : Drawing
EPC : Engineering, Procurement and Construction
IDS : Inspection Data Sheet
INSPECTION : Critical appraisal involving examination, measurement, testing, gauging,
and comparison of materials or items, in order to determine if the material
or item is in proper condition and quantity, and if it conforms to the
applicable or specified requirements.
ITR : (Inspection and Test Report); a formal written record detailing the results
of an inspection organized in a narrative, graphic, or tabular form,
dentified for each QC Code (see § 3.2). Once signed by the involved
parties it becomes a Certificate. It includes also the traceability versus the
inspected Item.
ITP : (Inspection and test Plan); Specific Section(s) of QCP that identify and
define Inspection sequences. It is prepared in accordance with all the
applicable contractual, engineering and Supplier’s provisions and
requirements. The ITP(s) provide references to applicable
procedures,acceptance criteria, documentation, quality records and
inspection attendance to be performed, in chronological order, from initial
inspection, throughout final inspections and mechanical completion. The
ITP(s) provide reference for the Inspection Forms to be used.
Organization : Group of people and facilities with an arrangement of responsibilities,
authorities and relationship
OWNER : External entity to CONTRACTOR defining product requirements and
paying for it
Any other terms related to quality and not listed above conform to section 3 “Terms and Definitions” of
ISO 9000:2005 “Quality Management System – Fundamentals and vocabulary”.
2. REFERENCE DOCUMENTATION
API 600 Steel Gate Valves – Flanged and Butt-welding Ends, Bolted Bonnet
API 602 Steel Gate, Globe and Check Valves for Sizes DN100 and Smaller for
the Petroleum and Natural Gas Industries.
API 607 Fire Test for Quarter-turn Valves and Valves Equipped with Non-
metallic Seats
API 608 Metal Ball Valves-Flanged, Threaded and Welding Ends
API 609 Butterfly Valves: Double Flanged, Lug-and Wafer-Type.
API Spec 6D Specification for Pipeline Valves.
API Spec 6FA Fire Test for Valves
API 941 Steels for Hydrogen Service at Elevated Temperatures and Pressures
in Petroleum Refineries
ASME BPVC Sect. 1 Section 1 Rules for Construction of Power Boiler.
ASME BPVC Sect. 2 Material Specification.
ASME B1.1 Unified Inch Screw Threaded (UN and UNR Thread Form)
ASME B1.20.1 Pipe Threads, General Purpose (Inch)
ASME B16.5 Pipe Flanges and Flanged Fittings NPS ½ Through NPS 24
ASME B16.9 Factory Made Wrought Steel Butt Welding Fittings
ASME B16.11 Forged Fittings, Socked Welding and Threaded
ASME B16.20 Metallic Gaskets for Pipe Flanges-Ring Joint Spiral Wound and
Jacketed
ASME B16.21 Non Metallic Flat Gaskets for Pipe Flanges
ASME B16.25 Butt-welding Ends
ASME B16.47 Large Diameter Steel Flanges NPS 26 Through NPS 60
ASME B16.48 Steel Line Blanks
ASME B31.1 Power Piping
ASME B31.8 Gas Transmission & Distribution Piping System
ASME B36.10M Welded and Seamless Wrought Steel Pipe
C205 Cement-Mortar Protective Lining and Coating for Steel Water Pipe
and Larger-Shop Applied.
C602 Cement-Mortar Lining of Water Pipeline in Place 4in. and Larger.
ASTM A105 Standard Specification for Carbon Steel Forgings for Piping
Application
ASTM A350 Standard Specification for Carbon and Low-Alloy Steel Forgings,
Requiring Notch Toughness Testing for Piping Components
ASTM B466 Standard Specification for Seamless Copper-Nickel Pipe and Tube
ASME B16.47 Large Diameter Steel Flanges. NPS 26 Through NPS 60.
ASME B16.20 Metallic Gaskets for Pipe Flanges. Ring-Joint, Spiral-Wound, and
Jacketed
ASTM A333 Standard Specification for Seamless and Welded Steel Pipe for Low
Temperature Service
ASME B16.42 Ductile Iron Pipe Flanges and Flanged Fittings: Classes 150 and 300
ASTM F1120 Standard Specification for Circular Metallic Bellows Type Expansion
Joints for Piping Applications
BS ISO 10497 Testing of Valves: Fire Type– Testing Requirements.
EEMUA No. 153 EEMUA Supplement to ASME B31.3
EEMUA No 182 Specification for Integral Block & Bleed Valve manifolds for Direct
Connection to pipework.
EEMUA Guide to the Specification, Installation and Maintenance of Spring
Publication 200 Supports for Piping.
ISO 13703 Petroleum and natural gas industries – Design and installation of
piping systems on offshore production platforms
ISO 14692 Petroleum and natural gas industries-Glass-reinforced plastic (GRP)
piping
ISO 15649 Petroleum and natural gas industries – Piping
ISO 17925 General Requirements for the Competence of Testing and
Calibrations Laboratories
SP-44 Steel Pipeline Flanges
SP-45 Bypass and Drain Connections
SP-58 Pipe Hangers and Supports
Norsok L-CR-003 Piping Details
PCIFL000 Flow Measurement Installation details.
PNF0200 Vents, Drains, and Instrument Connection Details.
PNFJ8000 Jacketed Piping Fabrication and Installation Details.
PNSC0035 Steam Tracing Details.
PNSC0036 Installation of High Density Polyethylene (HDPE)Piping.
UKOOA EHS15 Guidelines for the Management of Integrity of Bolted Pipe Joints
UKOOA EHS16 Installation guidelines for the Management, Design, and Maintenance
of Small Bore Tubing Systems.
Unless otherwise specified in the contract documents, the applicable revision or edition of applicable
specifications and standards is the last valid at the time when the contract or agreement are made to
enter into effective date.
Inspections and tests required by local regulations are out from the scope of this specification.
However, they shall be strictly adhered to and documented by SUBCONTRACTOR. Copy of such
records shall be submitted to CONTRACTOR.
The order of precedence of the codes and standards quoted in the specifications shall be:
3. Project specifications.
4. This Specification.
SUBCONTRACTOR shall negotiate the matter with the Authorities concerned and keep
CONTRACTOR informed of any resulting deviation from design requirements.There shall be no
deviation to Project specification requirements without prior written CONTRACTOR’s approval.
3.1 GENERAL
The inspections, tests and certification to be implemented in performing Piping Prefabrication and
Erection works are detailed in the ITPs and the attendant Inspection Forms listed in Chapter 5.2
The ITPs can be separated into the two following main groups:
General ITPs include the initial necessary checks and verification to be performed, when required,
prior to perform the inspections and tests specified in the dedicated ITP(s) for works QC. The
frequency of the addressed inspections and tests are defined by the applicable Specifications,
Standards and/or Codes.
Specific ITPs include inspection and tests which are or can be directly related to specific items
and/or part of the works that can be identified and traceable by means of the engineering drawings.
First and second columns contain the split of the ITP ID number as identified in the ITP Title box, third
column contains the progressive number of the inspection phase which includes also the suffix for the
connection with the relevant works phase as to :
Hold Point (H) : A point which mandatory requires the presence of the involved
parties (CONTRACTOR/COMPANY/Third party/Migas) for the
inspection when the activity is performed and before that any
further processing is permitted.
Surveillance Point (S) : Involvement for monitoring a phase of work activities. A written
notification (RFI) is not requested by the Construction
Organization. Periodic review by the CONTRACTOR and or
COMPANY representative on an activity, operation , process of
documentation by Construction Subcontractor
Perform/Submit (P) : Perform works and when requested by W/H points for other
parties prepare inspection and submit RFI.
Request for inspection (RFI) : The notification of inspection is a formal written request to be
issued by CONTRACTOR in order to allow all parties involved to
participate to the inspection and test as they are planned in the
applicable ITP(s). The Subcontractor QC shall notify COMPANY
through QC of Contractor to perform an in process inspection at
least 48 hours in advance of any HOLD point or 24 hours for
Witness inspections as soon as a representative portion of the
particular feature of work has been accomplished. In process
inspections include, but are not limited to,
- Fit-up inspection;
- Visual inspection;
- material;
- E&I inspection;
5. ATTACHMENTS
___ ___ ___ Joint fit-up Inspection, Welding Process ___ ___ Refer to QCP No. TEP-930-
implementation, Visual Inspection & NDE of SPE-QA-BP4-0023 for Welding
weldment
Piping bulk material receiving Material manag.nt OSDR Warehouse
___ ___ ___ procedure, packing Log Book
List,certification
PIP 0101 01M a. Physical verification of incoming
Project standard TEP-ITR-PIP--119* P H W W *(Phase to be included only when
materials: verification of identification TEP-900-SPE-PP-BP4-0002 Project material is provided
marks, tags, colour coding, thickness, without Material Release report)
TEP-900-SPE-PP-BP4-1015
dimensions, distortions, shape, any
evidence of damage
Final Inspection of Fabricated Item: TEP-ITR-PIP-101
PIP 0101 02M AFC DWGs.- P H W W
Completeness of the assembly check
Welding-induced distortion or TEP-900-SPE-MM-BP4-
deformation or warping check 0003
Related geometries, dimensions and TEP-900-STD-PP-BP4-
tolerances check 0002
Surfaces free from damages, rust &
scale, and cleaned
Erection marks for identification
Release of Pipe–Supporting Elements for TEP-ITR-PIP-102 Verify with respect to QC
PIP 0101 03M further activities or shipping: AFC DWGs P H W W
Code -01M.
Visual & Dimensional checks TEP-900-SPE-MM-BP4-
Welding and NDE 0003 Refer to Welding Data
PWHT (if required), Hardness test Base as per QCP No. TEP-
TEP-900-STD-PP-BP4-
930-SPE-QA-BP4-0023 for
0002
Cleanliness Welding
Preservation
___ ___ ___ Joint fit-up inspection, Welding process ___ ___ Refer to QCP No. TEP-930-
implementation, Visual inspection & NDE of SPE-QA-BP4-0023 for Welding
weldment.
PIP 0103 04M Valves, quill and other Line-Equipment AFC Dwgs. TEP-ITR-PIP-108 P H S S
installation: TEP-900-SPE-MM-BP4-
0003
-Ensure the correct location and positioning as
per AFC Dwgs. and Stds.
PIP 0103 05M Bolted Flange Joints inspection (pipe to pipe AFC Dwgs. TEP-ITR-PIP-109 P H W S
and pipe to strain sensitive equipment): TEP-900-SPE-MM-BP4-
0003
- Joint assembly members condition.
TEP-900-SPE-PP-BP4-
- Cleaning and examination for condition of 1005
flange and fastener contact surfaces.
- Alignment of Flanges.
- Installation of Gasket.
- Installation and Tightening of Bolts.
PIP 0103 06M Screwed Pipework inspection: AFC Dwgs. TEP-ITR-PIP- P H S S Care of Welding Inspector
TEP-900-SPE-MM-
110
- Minimum threads engagement and
BP4-0003
maximum exposed pipe threads in TEP-ITR-PIP-
threaded connections check. 109
- Seal welds check.
PIP 0103 07M Orifice Flanges installation inspection AFC Dwgs. TEP-ITR-PIP- P H W W For inspection of flow orifice plate, refer to
111 QCP No. TEP-930-SPE-QA-BP4-0031for
- Visual Inspection of weld root profile TEP-900-SPE-MM-
Instrumentat..
BP4-0003
- Pressure Taps orientation Care of Welding inspector
Refer to QCP
___ ___ ___ Pipe external wrapping for UG piping (Tape ___ ___
No. TEP-930-SPE-
wrapping). if applicable QA-BP4-0037for
Lining & Refractory
Works at Site.
P&ID’s Conformity checks report for process AFC Dwgs. P H H* H H *The activity is supervised
PIP 0103 12P TEP-ITR-PIP-125 and controlled by CSTS
Subsystem
CO
TEP-900-PRC-OP-BP4- P H H* H H *The activity is supervised
PIP 0103 13P Blowing/Flushing of Piping TEP-ITR-PIP-126 and controlled by CSTS
0007
CO
TEP-900-PRC-OP-BP4- P H H H H *The activity is supervised
PIP 0103 14P Instrument Lines Blowing TEP-ITR-PIP-127 and controlled by CSTS
0007
CO
missing **Applicable for Non
Critical Lines where
Boroscope is negative
and for Critical Lines.
ORGANIZATION CODE INVOLVEMENT CODE
CC – Construction Organization CO –CONTRACTOR Commissioning P – Perform/Submit W – Witness (Minimum 20% Inspection rate)
QC – QC Construction organization TP – PJIT/DGMIGAS S – Surveillance H – Hold Point (100% Inspection rate)
JO – CSTS Joint Operation/CONTRACTOR CL – COMPANY R – Review
P&ID’s Conformity checks report for AFC Drawings. TEP-ITR-PIP-125 P H H* H H *The activity is
IP 0104 06P supervised and controlled
process Subsystem by CSTS CO
TEP-900-PRC-OP-BP4-0007 *The activity is
PIP 0104 07P Blowing/Flushing of Piping TEP-ITR-PIP-126 P H H* H H
supervised and controlled
by CSTS CO
Document ref.:
SIGNATURE SIGNATURE
SIGNATURE SIGNATURE
C= CONFORMING NC= NOT CONFORMING
NOTES: INSPECTION NOTIFICATION
REFERENCE
RFI No.:
____________________
Subcontractor QC CONTRACTOR COMPANY TPI
NAME NAME NAME NAME
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
Form Code:TEP-ITR-PIP-101
PAsS
FAIL
PASS
FAIL
NA
PASS
FAIL
NA
PASS
FAIL
YES
NO
No.
Form Code:TEP-ITR-PIP-102
PASS
FAIL
PASS
FAIL
NA
PASS
FAIL
NA
PASS
FAIL
YES
NO
No.
Form Code:TEP-ITR-PIP-105
SLOPE
No. Rev. C NC C NC C NC C NC C NC NA
C= CONFORMING NC= NOT CONFORMING NA=NOT APPLICABLE
LOCATION
STRAIGHTNESS
ISO DRAWING ELEVATION & LEVEL / BOP / TOP
TAG ITEM / SPOOL OR ELEMENT
SLOPE
SUPPORT
SEATING
No. Rev. C NC C NC C NC C NC C NC NA C NC NA
STEM ORIENTATION
C NC C NC C NC NA REMARKS
DRAWING FLANGE
JOINT No.
No. Rev. SPEC. SIZE TYPE FACING FINISH MATERIAL
GASKET
SPEC. TYPE (see note 1) SIZE RATING MATERIAL
OUTER INNER FILLE
WINDING
RING RING R
SPECIFICATION
SIZE
MATERIAL
LUBRICANT TYPE AND BRAND NAME :
CHECK PASS FAIL CHECK PASS FAIL
ROTATIONAL
FLANGE FACINGS FINISH
TWO-HOLE
Form Code:TEP-ITR-PIP-110
C NC C NC C NC NA REMARKS
2.6 DRAINS ARE PROVIDED AT ALL LOW POINTS OF THE PIPING SYSTEM
ISOLATION VALVES ARE VERIFIED TO HAVE BEEN BODY AND/OR SEAT TESTED
2.9 PRIOR TO INSTALLATION THROUGH VERIFICATION OF FIELD TEST
CERTIFICATES
SUBCONTRACTOR: REPORT Sh of
No.
PRESSURE TEST REPORT
APPLICABLE SPEC. / PROCEDURE
LINE No. / SECTION No. TEST PACKAGE No. & Rev.
No. & Rev.
3.b PIPE CLAMPS ARE TIGHTENED AND IN FULL CONTACT WITH THE PIPE.
APPLICABLE SPEC. /
LINE No. / SECTION No. REF. P&ID No. & Rev.
PROCEDURE No. & Rev.
Installation instructions :
Support drawing where the spring support is included : ________________________________________________
POS. CHECK DESCRIPTION YES NO NOTES
IS THE TAG ITEM READABLE AND THE NUMBER OF THE INSTALLED SPRING
1 SUPPORT THE SAME AS THE ITEM NUMBER INDICATED ON PROJECT
DOCUMENTS: DATA SHEET, ISOMETRIC, PIPING ERECTION DRAWING ?
ARE THE DATA INDICATED ON THE NAMEPLATE(S) OF THE INSTALLED SPRING
2 SUPPORT IN COMPLIANCE WITH THE DATA INDICATED IN THE DATA SHEET,
INCLUDED THE TWO TRAVEL INDICATING INDEXES ?
RFI No.:
____________________
Subcontractor QC CONTRACTOR COMPANY TPI
NAME NAME NAME NAME
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
APPLICABLE SPEC. /
LINE No. / SECTION No. REF. P&ID No. & Rev.
PROCEDURE No. & Rev.
APPLICABLE SPEC. /
LINE No. / SECTION No. REF. P&ID No. & Rev.
PROCEDURE No. & Rev.
Installation instructions :
________________________________________________
POS. CHECK DESCRIPTION YES NO NOTES
ARE THE ITEM NUMBER AND FLOW DIRECTION OF THE INSTALLED
EXPANSION JOINT THE SAME AS THE ONES INDICATED ON PROJECT
1 DOCUMENTS: PROJECT SPECIFICATION, ISOMETRIC, PIPING ERECTION
DRAWING?
NOTES: INSPECTION NOTIFICATION
REFERENCE
RFI No.:
____________________
Subcontractor QC CONTRACTOR COMPANY TPI
NAME NAME NAME NAME
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
SUBCONTRACTOR:
CHECKING OF HEATING BLANKET APPLICATION AND CURING TIME
LINE No. / SECTION No. TEST PACKAGE No. & Rev. APPLICABLE SPEC. / PROCEDURE No. & Rev.
870310
PLANT LOCATION:
QCP
BINTUNI BAY,PAPUA - INDONESIA QC CODE
REFERENCE
PIP- PIP-010_
PROJECT TITLE: 010____
TANGGUH EXPANSION PROJECT
REPORT No. Sh of
SUBCONTRACTOR:
P&ID’S CONFORMITY CHECKS REPORT FOR PROCESS SUBSYSTEM REPORT
Item no Commissioning Subsystem no P&ID no Service
INSPECTION
DESCRIPTION OF THE INSPECTION RESULT REMARKS
CONFIRMITY CHECK WITH P&ID’S
CONFIRM THAT ALL THE PROCESS P&ID NOTES ARE CORRECTLY
IMPLEMENTED
CHECK SUPPORTS ARE FIXED CORRECTLY
CHECK SPRING HANGERS ARE RELEASED & SET AT COLD SETPOINT MARK.
870310
PLANT LOCATION:
QCP
BINTUNI BAY,PAPUA - INDONESIA QC CODE
REFERENCE
PIP- PIP-010_
PROJECT TITLE: 0103____
TANGGUH EXPANSION PROJECT REPORT No. Sh of
SUBCONTRACTOR:
BLOWING/FLUSHING OF PIPING REPORT
Item no Commissioning Subsystem no P&ID no Service
CONTRACTOR TPI
Subcontractor QC COMPANY
Construction Commissioning
NAME NAME NAME NAME NAME
SIGNATURE SIGNATURE SIGNATURE SIGNATURE SIGNATURE
SUBCONTRACTOR: 1 1
CHECK LIST
FLOW DIRECTION
IDENTIFICATION
CONNECTIONS
CONNECTIONS
CONNECTIONS
DOWNSTREAM
, PRESSURE)
ELECTRICAL
LINE READY
PNEUMATIC
UPSTREAM/
(FLUSHED
STRAIGHT
PROCESS
LENGTH
TAG/ITEM DESCRIPTION
REMARKS
CONFORMITY WITH SPC. NON CONFORMITY WITH SPC.
NOTES: INSPECTION NOTIFICATION
REFERENCE
NOTES: INSPECTION NOTIFICATION
REFERENCE
Tempertature
Build up Build up Cooling Welding
Jointer Heat of Heating
Joint Pressure Time Time Bead
Line Number Stamp No./ Lot. Plate
No.
No. No. NC NC NC C NC C NC
C C C
NOTES: INSPECTION NOTIFICATION REFERENCE
RFI No.: _________________
QC
CONSTRUCTION CONTRACTOR COMPANY TPI
ORGANIZATION
NAME NAME NAME NAME
SIGNATURE SIGNATURE SIGNATURE SIGNATURE
DATE DATE DATE DATE
Form code: TEP-ITR-RFI-129
Coordinate Elevation
Ref.
Joint Benc Cover
Line Number Remarks
No. h Top of (b - a)
Mark Top of
the
Northing Easting Pipe
Ground
(a)
(b)
No. Material Description P.O. P.O. Stock No. Material Quantity UOM Heat Unique Mill cert status Remark
No item Grade Order Receive No. No ac rej
No c