1. When the owner directly allot a construction /Interior/Landscape job to the Contractor or an agency
known to him it is called Direct Assignment .
2. A Contract is a legal that formally confirms in writing with a seal and signature, an agreement that
binds two parties in a firm commitment in accordance with mutually accepted terms of reference.
5. A system where a few contractors are shortlisted on the basis of predetermined eligibility criteria
decided by the owner and architect is called Tender by Specific Invitation .
6. Which type of tender quotations is invited in case of decorative works like Traffic Islands, Construction of
Sculptures and some parts of Landscape Jobs. C- Tender (Lump Sum Cost Tender)
3. The D.S.R (district schedule rates) is a document containing specifications of all construction
Items.
15. The B-1 (Percentage) Tender is popularly used in Government Projects which
are generally based on the DSR.
16. Which Tender system is used when all details are not finalized before making of
tender? B-2 Tender (Item Rate Tender)
17. In which Tender system Architects/Engineers work load is minimum? C – type lump sum
18. What are the Contractors responsibilities according to Demolition Tender? The
contractor has to make arrangements to cut off existing water supply lines, drainage
lines, electric supply lines etc.
19. The Security Deposit is generally 2.50 % of the total project cost.
23. liquidated damages is the penalty for unpaid due Professional fee within the
contract time.
26. Owner shall furnish contractor 3 sets of drawing and specs for free.
27. The contractor prepares at his own expense and submits 2 copies of
all shop drawings to the architect.
28. Computation of contract time shall commence on the 7th day from the
receipt of the notice to proceed
29. The contractor will notify the building official 10 days prior; stopping,
resuming, termination of construction.
33. Security deposit is split into 2 components that is A 2.50 % INITIAL Security Deposit,
and, b) A 2.50 % as the Retention Percentage. ?
34. What is the responsibility of the architect during the contract document phase of his
services?
35. Which of the following describes the lump sum or fixed fee method?
36. A statement from the architect confirming the amount of money due the contractor for
work accomplished is a certificate of payment
37. In a typical owner-architect agreement, who is responsible for payment of surveys, soil
explorations, and laboratory fees? owner
39. After the Tendering process the Award is declared in favor of some Contractor
who is first given a pre bid meeting
40. All the Clauses listed in the IIA Document as General Conditions Of Contract
are generally found to be
good for all construction projects.
c. Tender by Invitation
3) Explain the B1, B2 , C type tender systems with respect to the following points
a. Method
b. Where used?