INSTRUCTION: Select the correct answer to each of the following questions. Write the letter of your
choice in the examination booklet.
MULTIPLE CHOICE:
1. Which method of selecting an architect is often used by government agencies or private institutions
undertaking a project?
2. Which method of selecting an architect is often used by an individual undertaking a relatively small
project?
3. Which of the following describes the architectural competition method in selecting an architect?
4. Which compensation method for architect's services is made by adding all costs of technical services
and uses a multiplier to take care of overhead and profit?
5. Which compensation method for architect's services is flexible and any change will not affect owner-
architect agreement?
6. Which of the following does not describe the multiple of direct personnel expenses method of
compensation?
8. Among the methods of compensation for architect's services, which is considered the most fair to
both architect and client?
9. In the architect's regular design services, under which phase does preparation of forms for contract
letting, invitation/instruction to bidders, and bidders' proposals fall? Bidding or Negotiation Phase
10. In the architect's regular design services, under which phase does submission of
probable/preliminary project construction cost fall?
11. In the architect's regular design services, under which phase shall the preparation of construction
drawings, specifications and Bill of Quantities fall?
12. Which of the following activities of an architect does not fall under Construction phase?
13 Upon completion of contract documents phase, what percentage of the fee is expected to have been
given to the architect by the owner? (50%-90%)
a. 65 % c. 70%
b. 85% d. 90%
14. If the architect's professional fee is P 200,000.00, which of the following amount shall be paid to the
architect upon signing of the Agreement? (5% of Recommended Professional Fee)
a. 10,000.00 c. 15,000.00
b. 20,000.00 d. 5,000.00
15. For a residential project worth P 3,000,000.00, which of the following amount shall be the architect's
professional fee if the method of compensation used is percentage of construction cost and the rate is
based on UAP Schedule of Minimum Basic Fee? (10% of Recommended Professional Fee)
a. 300,000.00 c. 200,000.00
b. 100,000.00 d. 400,000.00
16. An architect has done the renovation of a residence in Valenzuela. Project construction cost is P
3,000.000.00. Using UAP standards, how much does the architect expect to receive as minimum basic
fee from his client? (150% of Recommended Professional Fee)
a. 450,000.00 c. 600,000.00
b. 200,000.00 d. 300,000.00
17. If the architect's fee is three million pesos, how much is he expected to receive upon completion of
the project, assuming that he has been compensated fully for the first three phases of his services? (15%
of Construction Cost)
18. What percentage of project construction cost is the architect's minimum basic fee for projects
involving extensive detail, such as furniture design, interiors, landscape designs, etc.? (RPF for
Architectural Interiors & Site Development Planning: 10%-15%)
a. 20% c. 15%
b. 18% d. 10%
18. What percentage of project construction cost is the architect's minimum basic fee for monumental
buildings/other facilities requiring consummate design skills/precise detailing? (12%, DAEDS\7.5%,
DADS)
a.20% c. 15%
b. 12% d. 10%
19. What is generally the basis of the architect's minimum basic fee?
20. In a typical owner-architect agreement, who is responsible for payment of taxes on professional
services (exclusive of income taxes)?
a. architect c. owner
b. contractor d. project manager
21. In a typical owner-architect agreement, which of the following is chargeable to the owner?
a. structural/electrical/sanitary engineering c. miniature models
b. drafting fee d. five sets of contract documents
22. In a typical owner-architect agreement, which of the following, is not part of architect's professional
fees?
23. Under the owner-architect agreement, which of the following include (s) the contract documents
phase of architect's basic services?
24. Who is responsible for payment of professional services required by architect such as normal
structural, electrical, plumbing and mechanical engineering services?
25. Which of the following is not included in the Project Construction Cost?
26. Which of the following must be paid separately by the Owner to the Architect if designed and
planned by the Architect?
a. landscaping c. architectural
b. structural d. electrical
27. Who is responsible for insurance for liabilities on materials, workmanship, labor and property?
a. architect c. contractor
b. construction manager d. owner
28. For every day of delay in construction time, contractor is obligated to pay the owner. What do you
call this payment?
29. Under the owner-contractor agreement, who pays for taxes, licenses, permits, and fees? (taxes,
licenses, permits are Reimbursable Fees)
30. In a typical owner-general contractor agreement, which of the following is generally NOT included?
31. Under what condition may owner exercise the right to terminate a contract?
32. Under General Conditions, who is generally responsible for payment of permits, taxes and licenses?
a. architect c. owner b. building supervisor d. contractor 33. Within what period is the effectivity of a
contractor guarantee bond ensuring all materials/workmanship installed are of good quality?
33. Within what period is the effectivity of a contractor guarantee bond ensuring all
materials/workmanship installed are of good quality?
34. Within how many days from receipt of request for payment must the architect check the billing of
the contractor?
a. 10 days c. 15 days
b. 20 days d. 30 days
35. Within how many days from receipt of written notice by the Owner must the Contractor rectify
defective work?
a. 10 days c. 15 days
b. 20 days d. 30 days
36. Which of the following is not a requirement for the release of the final payment?
a. earthquakes c. flood
b. typhoon d. mutiny
38. Which of the following is not a valid reason for suspension or termination of contract by the
contractor?
39. Who shall be responsible for the death or injury of any employee or laborer of the Contractor?
40. What do you call the amount of money that is being deducted from the contractor every billing until
50 % of the contract has been accomplished and which shall be released 3 months after the date of final
payment?
a. guarantee c. retention
b. performance bond d. security
41. Within what period should a contractor file a request for time extension from occurrence of delay?
a. 21 days c. 10 days
b. one month d. 15 days
42. When should a contractor give a written notice to architect prior to beginning, suspending or
resuming of work (except in case of accidents)?
a. 10 days c. 15 days
b. 30 days d. 21 days
43. Which of the following is NOT a reason for Owner to terminate a construction contract?
a. engineer c. foreman
b. contractor d. architect
46. In master development plan formulation, which component is concerned with movement of
people/goods from one place to another?
a. economic c. physical
b. socio-cultural d. transport
47. In the architect's specialized allied services, under which category does the architect prepare plans
of contiguous sites for industrial estates, tourist center, housing subdivisions and the like?
48. In the architect's specialized allied services, under which services does the architect prepare
schedules of shrubs, trees and other plants and other landscaping elements?
49. Which of the following conditions describe the design build services on guaranteed maximum cost?
a. 1,2,3 c. 1,3,4
b. 2,3,4 d. 5
50. Which of the following specialized allied services describes landscape design?
51. Which of the following post construction services is concerned with the monitoring of security and
janitorial services?
52. When the architect rejects materials, equipment or workmanship which are not in conformity with
the Contract Documents, he is fulfilling his responsibility to whom?
a. Contractor c. Owner
b. Client d. People
53. In the formulation of the master development plan, which component is concerned with the
locality's assets and its management?
a. physical c. economic
b. transport d. socio-cultural
54. In the formulation of the master development plan, which component is concerned with land use
and changes/activities occurring within the physical environment?
a. socio-cultural c. economic
b. physical d. transport
55. Under the architect's specialized allied services, under what category does the architect lead the
formulation of a master development plan consisting of several planning components?
56. One of the specialized allied services of the architect is comprehensive planning services which,
together with other specialists, include the preparation of a development plan. What do you call this
development plan?
57. Which of the following is NOT part of specialized services of the architect?
58. What is the normal fee for interior design as a specialized allied service of the architect?
a. 15 to 20% c. 10 to 20%
b. 12 to 20% d. 10-15%
59. Under the architect's design-build services on a guaranteed maximum cost, which of the following
conditions should be observed?
61. Which of the following conditions is NOT TRUE in design-build services on guaranteed maximum
cost?
a. Architect's fee is 10 percent of project construction cost in addition to fee for regular design services.
b. More than 10 percent excess of guaranteed maximum cost paid by architect.
c. Architect's fee is built-in in guaranteed maximum cost including fee for regular design services.
d. 10 percent excess of guaranteed maximum cost divided between architect and client.
62. Under the design-build services by administration, what would be the architect's fee if the project
cost is 700 million pesos? (7% of RPF)
64. For the preparation of detailed engineering drawings and specifications on roads, drainage,
sewerage, power and communication system, an additional fee of how many percent of the cost of the
development is to be charged?
a. 2% c. 4%
b. 3% d. 5%
66. Under BP 220, which among the following is maximum length of a block?
a. 250 m c. 400 m
b. 350 m d. 300 m
67. Under BP 220, which among the following is the minimum lot area requirement for detached
dwelling unit? (72m² for Economic; 64m² for Socialized)
a. 63 sq.m. c. 72 sq.m.
b. 70 sq.m. d. 81 sq.m.
68. Which among the following is the minimum corner lot area requirement for semi-detached dwelling
unit under BP 220? (54m² for Corner Lot; 36m² for Row House)
a. 63 sq.m. c. 54 sq.m.
b. 72 sq.m. d. 36 sq.m.
69. Which among the following is the minimum lot area requirement for rowhouses under BP 220?
(36m² for Economic; 28m² for Socialized)
a. 63 sq.m. c. 54 sq.m.
b. 72 sq.m. d. 36 sq.m.
70. Which among the following is the minimum horizontal dimension of courts & yards under BP 220?
a. 2.30 m. c. 2.00 m.
b. 2.60 m. d. 3.00 m.
71. Which among the following is the minimum floor area for multi-family dwelling unit under BP 220?
(22m² for Economic; 18m² for Socialized)
72. Which among the following is the minimum floor area for single-family dwelling unit under BP 220?
(22m² for Economic; 18m² for Socialized)
73. Which of the following is the parking requirement for multi-family dwelling under BP 220? (1 Slot
Per 8 Living Units)
74. Which among the following is the maximum saleable lots for subdivision projects with an area of 1
hectare under PD 957?
a. 70% c. 65%
b. 60% d. 75%
75. Which among the following is the minimum lot area requirement for duplexes under PD 957? (96m²
for Open Market; 80m² for Medium Cost)
77. For residential condominium projects, which among the following is the minimum floor area for
household dwelling unit under PD 957? (36m² for Open Market; 22m² for Medium Cost)
a. 31 sq.m. c. 36 sq.m.
b. 40 sq.m. d. 45 sq.m.
78. For residential condominium projects, which among the following is the minimum floor area for
single occupancy dwelling unit under PD 957? (36m² for Open Market; 22m² for Medium Cost)
a. 31 sq.m. c. 36 sq.m.
b. 40 sq.m. d. 45 sq.m.
79. For residential condominium projects, which among the following is the parking requirement under
PD 957?
80. Which among the following is the minimum no. of elevator for a 4-storey residential condominium
under 957?
a. 0 C. 1
b. 2 d. 3
81. Which among the following is an integrated network of hydraulically designed piping installed in a
building structure with outlets arranged in a systematic pattern which automatically discharges water
when activated by heat or combustion products from fire?
82. Which among the following is the maximum distance of elevators from the entrance of a building?
a. 40 m. c. 30 m.
b. 50 m. d. 20 m.
83. Which among the following is the minimum clear width of ramps?
a. 1.20 m. c. 1.30 m.
b. 1.40 m. d. 1.50 m.
84. Which among the following is the maximum gradient of ramps?
a. 1:10 c. 1:11
b. 1:12 d.1:13
a. 4 m. c. 5 m.
b. 6 m. d. 8 m.
86. Which among the following is the minimum dimension of elevator? (1.40m x 1.2m)
87. Which among the following is the minimum clear width of corridors?
a. 1.20 m. c. 1.30 m.
b. 1.40 m. d. 1.50 m.
88. Which among the following is the minimum area of water closet stall?
89. Which among the following is the minimum distance of eaves over required windows from the side
and rear property lines?
a. 0.75 m. c. 0.80 m.
b. 0.70 m. d. 0.85 m.
90. Which among the following is the minimum open space requirement for an inside lot?
a. 25% c. 10%
b. 20% d. 15%
91. Which among the following is the minimum horizontal dimension of court?
a. 2.00 m. c. 2.30 m.
b. 2.60 m. d. 3.00 m.
92. Which among the following is the minimum ceiling height for habitable rooms provided with natural
ventilation?
a. 2.50 m. c. 2.60 m.
b. 2.70 m. d. 3.00 m.
93. Which among the following is the minimum area of rooms for human habitation?
94. Which among the following is the required no. of exits for a storey of a building
having an occupant load of 700? (3 Exits for Occupants of 500-999)
a. 3 c. 2
b. 1 d. 4
95. Which among the following is the required total width of exits of a storey of a building having an
occupant load of 1650? (The total width of exits in meters shall not be less than the total occupant
load served divided by 165.)
a. 8 m. c. 9 m.
b. 10 m. d. 11 m.
96. Which among the following is the maximum distance of a point in a building without sprinkler
system from an exterior exit door? (45m w/ Sprinklers; 60m w/out Sprinklers)
a. 45 m. c. 50 m.
b. 55 m. d. 60 m.
97. Which among the following is the minimum width of court and/or yard at fifth floor of a building?
a. 2.30m. c. 2.60m
b. 2.90m. d. 3.20m.
98. Which of the following is not a condition in the granting of temporary/special permit to a foreign
national?
a. his country permits Filipino professionals to practice his profession
b. he is legally qualified to practice architecture in his country
c. must work with a Filipino counterpart
d. must register with SEC
99. How many years is the liability 'of the architect for the building he design under the Civil Code?
a. 5 years c. 10 years
b. 15 years d. 20 years
100. Which of the following is not a qualification of applicant for licensure examination?
a. Filipino citizen
b. of good moral character
c. graduate of Bachelor of Science in Architecture
d. 21 years old
PRAC X
Page 1 of 3
Professional Practice
47 Who shall pay for the services of a licensed surveyor for confirmation and certification of
the location of column centers, piers, walls, pits, trenches, pipe work, culvert work, utility Contractor
lines, and other similar works required by the contract.
48 Professional Fee for the Architect as a full-time supervisor. 1-1.5%
49 Professional fee for the Construction Manager. 1.5-3%
50 Firm Fixed Price
Fixed Price Incentive
Four types of Contracts for construction management
CPIF / CPAF
Cost Plus Fixed Fee
51 Under PD 1096, what should be the proportion of sidewalk width to that of the road right-
(1/6)
of-way?
52 At what interest rate per month should a client pay the architect should the former fail to
2%
pay the latter beyond 30 days from receipt of billing?
53 What code holds the architect responsible for the building/structure he designed for a
Civil Code
certain period of time.
54 What type of compensation is applied to cases where the architect's personal time is
Per Diem+Reimb. Expenses
required, such as conferences, joint venture activities, etc.?
55 What type of bond guarantees payment on all obligations arising from the contract? Payment Bond
56 What type of compensation is applied to most of Gov't projects and entails more paper
Lump Sum / Fixed Fee
works and is advantageous to both client and architect.
57 Professional Fee for the Project Manager. 2-5%
58 If the Project Manager is hired by the owner, who shall have the responsibility of hiring
Project Manager
the Construction Manager?
59 True or false, based on the Civil Code, the Project Manager has no legal responsibility
TRUE
insofar as design and construction is concerned.
60 His primary responsibility is the exercise of overall cost control which relieves the owner
of many of the anxieties that usually beset , particularly those concerned with forecasting Project Manager
cost and completion dates.
61 In the architect's code of ethics, to whom does the architect has responsibility to seek
Public / People
opportunities for constructive service in civic and urban affairs?
62 What PD created the PRC which regulates the practice of various professionals. PD 223
63 Architect XYZ uses paid advertisements without sanction by professional consensus and
People / Public
years of experience. His action is unethical with respect to his relation to whom?
64 Additional information on contract documents issued to bidders before date of bidding. Bid Bulletin
65 The offer of a bidder to perform the work described by the contract documents when made
Proposal
out and submitted on the prescribed proposal form, properly signed and sealed.
66 The cashier's check or surety bond accompanying the proposal submitted by the bidder,
as a guarantee that the bidder will enter into a contract with the owner for the construction Proposal Bond
of the work, if the contract is awarded to him.
67 Instructions which may be issued prior to the bidding to supplement and/or modify
Special Provisions
drawings, specifications, and/or general conditions of the contract.
68 Written or printed description of work to be done describing qualities of material and mode
Specifications
of construction.
69 Means information, advice or notification pertinent to the project delivered in person or
sent by registered mail to the individual, firm or corporation at the last known business Written Notice
address of such individual, firm or corporation.
70 Includes labor or materials or both as equipment, transportation, or other facilities
Work
necessary to commence and complete the construction called for in the contract.
71 Means to build-in, mount in position, connect or apply any object specified ready for the
Install
intended use.
72 Means to purchase and/or fabricate and deliver to jobsite. Furnish
73 Means to furnish and install. Provide
74 No further retention shall be made on the balance of the contract when how many percent
50%
of the contract has been completed?
75 No payment shall be made on contracts in excess of how many percent of the contract
65%
price.
76 The guarantee bond is equal to how many percent of the contract price? 30%
77 How many percent of the architect's fee is payable to the architect upon completion of the
30%
preparation of the schematic design phase and up to final design development phase?
78 Standard factor computed for changes and/or revisions made on completed contracts. 2.5
79 Approximately, how many square meters of office space for the architect is built by the
12 sqm.
contractor as temporary facilities for the project.
80 All trees and other plants that need to be transplanted elsewhere within ___ meters
50 / Contractor
shall be done by the ___ at his own expense.
81 If there is a variance/discrepancy between the drawings and specifications, what shall
Specifications
be followed?
82 How many days prior to bidding shall the contractor seek the architect's
15 Days
clarification as to the particular areas of work which requires evaluation of the architect?
83 How many days upon written notice can a contractor terminate a contract with a valid
15 Days
reason?
Page 2 of 3
Professional Practice
84 Suspension of work for ___ days by order of any court or other public authority through
90 Days
no act or fault of the contractor gives the him the right to terminate contract.
85 True or false, the contractor can terminate contract if the owner should fail to pay the
False (30 days)
contractor any sum within 15 days after its award by arbitration
86 True or false, the contractor can terminate contract if the owner should fail to act upon
False (15 days)
any request for payment within 30 days after its certification by the architect.
87 Who declares bankruptcy as a valid reason for the termination of a contract? Contractor
88 True or false, upon termination of contract and upon the decision of the architect that
materials and equipment left by the contractor which do not belong to him can be used TRUE
and rent of such shall be borne by the failing contractor.
89 True or false, in case of suspension of work, all unpaid work executed including expenses
TRUE
incurred during suspension shall be evaluated by the architect and charged to the owner.
90 True or false, the owner has no right to claim liquidated damages if he takes over the
FALSE
work from the contractor for failure to complete the project.
91 How many days prior to canceling an insurance be given to the owner stipulating the
10 days
intention to cancel?
92 How many percent of the contract amount is the Performance Bond? 15%
93 How many percent of the contract amount is the Payment Bond? 15%
94 A contract provision setting forth the damages a party must pay in the event of his breach. Penalty Clause
95 Basic Fee for Physical Planning Type 1 or site such as industrial estates, commercial
5,000 for First 50 Hectares
centers, sports complex, resorts, etc.
96 Predecessor of PD 1096 R.A. 6451
97 What presidential decree institutionalized the profession of environmental planning? PD 1308
98 It is a right enforceable against specific property to secure payment of an obligation. Liens
99 Minimum basic fee for simple projects. 6%
100 Minimum basic fee for alterations/renovations. 50%
101 When the architect is engaged to render opinion or advise, clarification or explanation
200 / hr
on technical matters pertaining to his profession, the minimum basic fee shall be ___.
102 When rendering service as an expert witness, the architect is compensated ___/ hr. 500
103 Minimum basic fee for Group 5 Projects (monumental). 12%
104 What is Group 6 Project classification? Repetitive Construction
105 10% of 1st unit
Minimum Basic fee for housing projects. 60% 2nd-10th Unit
30% 11th and above
106 Under what classification of Project does Hospitals and Medical Buildings fall? Group 3 (Exceptional Character)
107 Under what classification of Project does Stadium fall? Group 3 (Exceptional Character)
108 Minimum Per diem paid to the architect if work is beyond 50 kms. From office. PHP 750.00
109 On the remaining 15% work fee of the architect, where does the 5% go. Construction Phase Service
110 Repairs and corrective works at the expense of the contractor should be done within how
5 days
many days after written notice by owner?
111 Failure on the part of the contractor to remove condemned work shall give the owner right
to remove said work at contractor's exepense and contractor shall pay the owner the 10 days
expenses incurred within how many days from removal by the owner of said work?
112 Contract time reckoning shall commence on the ___ from receipt of ___. 7th day / Notice to Proceed
113 An area of a city where municipal buildings are grouped. Civic Center
114 Any article of property not consisting of or affixed to land plus any interest in land that is
Chattel
less than a freehold.
115 No person who is not a citizen of the Philippines may take the board exams or practice
Reciprocity
the profession unless the country of his relation allows the same ___.
Page 3 of 3
UAP DOCS.
People / public Architects XYZ uses paid
advertisements without sanction by
professional consensus and years of
experience. His action is unethical with
respect to his relation to whom?
Bid Bulletin Additional information on contract
documents issued to bidders before
date of bidding
Proposal The offer of a bidder to perform the
work described by the contract
documents when made out and
submitted on the prescribed proposal
form, properly signed and sealed
Proposal Bond The cashier’s check or surety bond
accompanying the proposal submitted
by the bidder, as a guaranteed that the
bidder will enter into a contract with the
owner for the construction of the work.
If the contract is awarded
Special Provision Instructions which may be issued prior
to the bidding to supplement and or/
modify drawings, specifications and/ or
general conditions of the contract
Specifications -Written or printed description of work
to be done describing qualities of
material and mode of construction
-if there is a variance/discrepancy
between the drawing and specifications,
what shall be followed?
Written Notice Means information, advice or
notification pertinent to the project
delivered in person or sent by
registered mail to the individual, firm or
corporation at the last known business
address of such individual firm or
corporation
Work Includes labor or materials or both as
equipment, transportation, or other
facilities necessary to commence and
complete the construction called for in
the contract
Install Means to build in, mount in position,
connect or apply any object specified
ready for the intended use
Furnish Means to purchase and / or fabricate
and deliver to jobsite
Provide Means to furnish and install
50 % No further retention shall be made on
the balance of the contract when how
may percent
65 % No payment shall be made on contracts
in excess of how many percent of the
contract price
80 % The guaranteed bond is equal to how
many percent of the contract price?
30 % How many percent of the architect’s fee
is payable to the architect upon
completion of the preparation of the
schematic design phase and up to final
design development phase?
25 Standard factor computed for changes
and/or revisions made on completed
contracts
12 sq. m Approximately, how many square
meters of office space for the architect
is built by the contractor as temporary
facilities for the project
50 / contractor All trees and other plants that need to
be transplanted elsewhere within ___
meters shall be done by the ___at his
own expenses
15 days How many days prior to bidding shall
the contractor seek the architect’s
clarification as to the particular areas of
work, which requires evaluation of the
architects?
15 days How many days upon written notice can
a contractor terminate a contract with a
valid reason?
90 days Suspension of work for ___ days by
order of any court or other public
authority through no act or fault of the
contractor gives to him the right to
terminate contract
False (30 days) True or false, the contractor can
terminate contract if the owner should
fail to pay the contractor any sum
within 15 days after its award by
arbitration
False (15 days) True or false, the contractor can
terminate contract if the owner should
fail to act upon any request for
payment within 30 days after its
certification by the architect
Contractor Who declares bankruptcy as a valid
reason for the termination of a
contract?
True True or false, upon termination of
contract and upon the decision the
architect that materials and equipment
left by the contractor which do not
belong to him can be used and rent of
such shall be borne by the failing
contractor
False True or false, owner has no right to
claim liquidated damages if the takes
over the work from the contractor for
failure to complete the project
10 days How many days prior to canceling
insurance be given to the owner
stipulating the intention to cancel?
15 % How many percent of the contract
amount is the performance bond?
15 % How many percent of the contract
amount is the payment bond?
Penalty clause A contract provision setting forth the
damages a party must pay in the event
of his breach
5,000 to first 50 hectares Basic fee for Physical Planning type 1 or
site such as industrial estates,
commercial centers, sports complex,
resorts etc.
R.A 6451 Predecessor of PC 1096
PD 1308 What presidential decree
institutionalized the profession of
environmental planning?
Liens It is a right enforceable against specific
property to secure payment of an
obligation
6% Minimum basic fee for simple projects
150 % Minimum basic fee for
alterations/renovations
200/hr When the architect is engaged to render
opinion or advice, clarification or
explanation on technical matters
pertaining to his profession, the
minimum basic fee shall be __
500/hr When rendering service as an expert
witness, the architects is compensated
___/hr
12 % Minimum basic fee for Group 5 projects
(monumental)
Repetitive construction What group 6-project classification?
Major Road 1. A street or road linking the site and serves as the main traffic artery within the project
site and shall traverse the longer axis of the property
Collector Road 2. A Street or a road that services pedestrian/vehicular traffic from minor roads leading
to major roads.
Minor Road 3. A road which main function is to provide direct access to lots and other activity centers.
Motor Courts 4. Shall have a right-of-way of not less than 6 meters in width with provision for sufficient
space for vehicular turn around in the form of a cul-de-sac, loop, branch or "T", with a maximum length
of 60 meters inclusive of terminal.
Service Roads 5. Roads which provide for the distribution of traffic among individual lots and activity
centers.
Alley 6. A 2-meter wide walkway which shall be used to break a block and to serve pedestrians and for
emergency purposes. It shall not be used as access to property.
120,100 7. (For pd957) Minimum lot area of single detached (open market and medium cost)
respectively
96, 80 8. (For pd957) Minimum lot area of duplex/single attached (open market and medium cost)
respectively
60, 50 9. (For pd957) Minimum lot area of row house (open market and medium cost) respectively
72, 64 10. (For BP 220) Minimum lot area of single detached (economic and socialized) respectively
54, 48 11. (For BP 220) Minimum lot area of duplex/single attached (economic and socialized)
respectively
36, 28 12. (For BP 220) Minimum lot area of row house (economic and socialized) respectively
12 13. (For 957) minimum lot frontage of single detached corner lot
10 14. (For 957) minimum lot frontage of single detached regular lot
6 15. (For 957) minimum lot frontage of single detached irregular lot
3 16. (For 957) minimum lot frontage of single detached interior lot
8, 8 19. (For BP 220) minimum lot frontage of single detached corner lot (economic and socialized)
respectively
8, 8 20. (For BP 220) minimum lot frontage of single detached regular lot (economic and socialized)
respectively
4, 4 21. (For BP 220) minimum lot frontage of single detached irregular lot (economic and socialized)
respectively
3, 3 22. (For BP 220) minimum lot frontage of single detached interior lot (economic and socialized)
respectively
6, 6 23. (For BP 220) minimum lot frontage of duplex/single attached (economic and socialized)
respectively
4, 3.5 24. (For BP 220) minimum lot frontage of row house (economic and socialized) respectively
5 storeys and beyond 26. In a condominium’s low-cost housing under BP 220, an elevator is
needed if the condominium has storeys of?
2% 27. In Low Cost Housing under BP 220, minimum area of community facilities
allocation for 225 & above dwelling unit per hectare is?
3m & 5m 28. Subdivision projects abutting a main public road must provide
sufficientsetbacks with a minimum dimension of ________ in depth and
_________ in length at both sides of the subdivision entrance to accommodate loading and
unloading of passengers.
1.5 m 29. The minimum front setback of dwelling unit both for economic and
socializedhousing project
1.5m 30. The minimum side setback of dwelling unit both for economic and
socializedhousing project
2.0m 31. The minimum rear setback of dwelling unit both for economic and
socializedhousing project
1.80m & 50% 32. Mezzanine floors shall have a clear ceiling height of not less than____ meters above
and below it, provided that it shall not cover _____of the floor area below it.
42 sqm 36. What is the Minimum floor area for open market housing?
Corner lot 37. A lot situated at the intersection of two or more streets.
Interior lot 38. A lot located at the inner portion of a block with a
minimum of three meter (3-m) wide access which forms part of the lot.
12 sqm 39. What is the net floor area for single occupancy may be allowed intended for
students/employees/workers?
Regular lot 40. A lot fronting on one street and the remaining sides bounded by lot lines.
36 sqm 41. Family dwelling in condominium’s open market housing under PD 957 has a
minimum floor area requirement of?
8 m 42. What is the minimum measurement for access road or right of way for
condominium open market housing under PD 957?
10 meters. 43. In cases where the major road will serve as interconnecting road, it shall have a minimum
right-of-way of ____
2.0 meters 44. Alley shall have a width of ___ intended to break a block and to serve both pedestrian
and for emergency purposes, both ends connecting to streets.
3.0 meters 45. Pathwalk shall have a width of ____intended only to provide pedestrian access to
property for socialized housing projects.
42 square meters 46. Minimum floor area for open market housing shall be ____
30 square meters 47. Minimum floor area for medium cost housing.
20 M 49. Distance between offset intersections should be not less than _____ from corner to corner.
Street level 50. Whenever possible, lot frontage elevation shall be at what level?
When the Owner hires an Architect of a firm to coordinate the whole range of Comprehensive Architectural
Services, it shall constitute?
construction management
project management
construction management
1. Which specialized allied services involves the detailed planning and design to
control sound
transmission for compatibility with the architectural design concept?
Acoustic Design
Interior Design
Landscape Design
8%
9%
10%
11%
Under what Building and Facilities Administration Services does the Architect monitor maintenance and
upkeep services (cleanliness of corridors, lobbies, stairs and other common areas, exits, parking areas,
garbage collection)
Building Management
Building Maintenance
Building Housekeeping
Building Supervision
12%-20%
12%-15%
10% - 12%
12% - 15%
1. The Consulting Architect in this area of practice provides the Owner/Client with
means and
measures to ensure the proper function and maintenance of the building /
structure and site
Facilities Maintenance
Facilities Management
or activity.
Security Evaluation and Planning
Security Management
Security Planning
1. The Consulting Architect in this area of practice places value on the building /
structure condition and defects, and on its repair and maintenance, including the
required improvements.
Building Testing
Architect
Agent
Project Manager
1. The Consulting Architect in this area of practice places value on the building /
structure condition and defects, and on its repair and maintenance, including the
required improvements.
Building Estimate
Building Appraisal
Building Evaluation
a. Post-construction evaluation
c. Building/Equipment Maintenance
b. Functional Analysis
d. Building Functions Evaluation
1. Which specialized allied services involves the detailed planning and design of
light transmission, timing and control for compatibility with the architectural
design concept?
Lighting Design
Illumination Design
1. The Consulting Architect in this area of practice must have much more than the
basic
knowledge of Site Analysis, Space Planning and Management, Architectural
Programming, and
1. Pre-design services
Architectural Programming
Preliminary Services
Preliminary Investigation
Which of the following is not within the scope of full-time supervision?
Quality control of work
keeping of records
award of contract
4
5
commercial applications.
1. The Consulting Architect in this area of practice must have much more than the
basic
knowledge of Green Architecture and Environmental and/or Sustainable
Design and sufficient
Certificate of Occupancy
2,3
2,4
1,2
1,4
6%
7%
8%
9%
1. The Consulting Architect in this area of practice places value on the building /
structure condition and defects, and on its repair and maintenance, including the
required improvements.
Building Estimate
Building Appraisal
Building Evaluation
Building Quantity Surveyin
20.Which among the compensation methods should be used for non-creative works?
Per diem
Lump sum
Per diem
Lump sum
Lump sum
per diem
1. A developer commissioned Architect Francisco to do the design of their residential projects. How should
Architect Francisco charge the developer?
10m
12m
14m
16m
46M
47M
48M
49M
200m
250m
300m
400 m
12m
14m
16m
1. As per BP 344, accessible public washrooms and toilets shall permit easy
passage of wheelchair and must allow how much turning space for
wheelchairs?
2.10 sqm
2.15 sqm
2.20 sqm
2.25 sqm
Lump sum
Per diem
0.70 m
0.71 m
0.72 m
0.73m
1. As per BP 344, a level area of not less than how many meters shall be
provided at the top and bottom of any ramp?
1.50 m
1.60 m
1.70 m
1.80 m
1. A bar which extends across at least one-half of each door leaf, which will
open the door if subjected to pressure.
panic control
panic bar
panic press
Per diem
Lump sum
21.Which compensation method for architects’ services is flexible and any change will not affect owner-
architect agreement?
lump sum
per diem
1. The City of Manila will build a new university for their city. How should
they select their architect?
comparative selection
direct selection
architectural competition
1. As per PD 957, what is the minimum width for roads right-of-way for
residential condominium projects?
6m
8m
10m
12m
1. As per BP 344, how much is the parking slot width for handicapped drivers
and passengers providing sufficient clear space between parked cars to
allow them to transfer to a wheelchair?
3.50m
3.60m
3.70m
3.80m
1. What is the minimum lot area for single detached socialized housing units
as provided for in BP 220?
60 sqm
62 sqm
64 sqm
70 sqm
1. As per BP 344, what is the maximum length of a ramp if the ramp gradient
is 1:12?
6m
7m
8m
9m
1. Mr. and Mrs. Uy plan to have a house of their own. What is the best way for them to select their
architect?
Architectural competition
direct selection
comparative selection
0.60m
0.70m
0.80m
0.75m
20.Which among the compensation methods should be used for non-creative works?
per diem
lump sum
1.00 m
1.10m
1.20m
1.30m
Per diem
lump sum
1. Under the NBC, all inner courts shall be connected to a street or yard either by a pass with a
minimum width of
2. Under the NBC mezzanine floors shall have a clear ceiling height not less than how many?
3. Under the NBC, the minimum dimension for court or near yard from the property lir.e to the
face of the building is
5. Under the NBC, if only two exits are required, they shall b. laced a distance apart of not lass thar.
a. ½ b. 1/3 c. ¼ d. 1/5
6. Under the NBC, window openings shall equal to at least of what percent of the floor area of
room?
7. Under the NBC, for Group A Dv1ellings, stairs shall have o minimum width of
8. Under the NBC exemption from payments of buildings permit fees shall be granted to
10. Under the NBC, open spaces required for inside lots is
11. Under the NBC, habitable rooms with natural ventilation shall have a minimum air space per
person of
12. Under the NBC, a mezzanine floor use other than for storage purposes shall have at least two
stairways to an adjacent floor if the area is greater than?
13. Under the NBC, open space required for interior lots is
14. The purpose of the NBC is to provide for all buildings and structures, a framework of standards
and requirements which is the
15. Under the NBC, the vertical distance between landings shall not be more than
16. Under the NBC, clearance between established grade of the street and/ or sidewalk and the
lowest under surface of any part of the balcony shall not be less than
19. Under the NBC, a building permit shall expire if work authorized is abandoned or suspended at
any time after commencement or a period of
20. Under the NBC, rooms for human habitation shall have a minimum size of
21. Under the NBC, for Group A Dwellings, stairs shall have a minimum run of
22. Under the NBC, every room intended for any use and not provided with artificial ventilation system
shall be provided with a window with a total free area of opening equal to at least how many percent of
the floor area of the room?
23. Under the NBC, the term that shall mean the total number of persons that may occupy a building or
24. Under the NBC, for Group A Dwellings, stairs shall have a clear width of at least
25. Under the NBC, the minimum dimension requirement-= for a parking space is
27. Under the NBC, basic residential building in R-2 zone shall have a minimum front setback of
28. Refers to total floor space within the perimeter of the permanent extema:building wells.
29. This refers to the percentage of the maximum .allowable floor area of any paved, tiled or
hardscaped surface at the ground floor/ grade level in relation to the Total Lot Area (TLA)
a. Incremental Setback
30. Type of construction which is four-hour fire-resistive throughout and·the structural elements are
made of steel,iron,concrete or masonry construction.
31. A building permit shall expire and become null and void if the building authorized therein is not
33. As per PD 1096, under what classification shall factories and workshops using less flammable
34. For residential occupancies, how many percent of an interior lot is open space?
35. As per PD 1096, what is the minimum clear ceiling height for mezzanine floors above and below it?
36. As per PD 1096,wh2t is the minimum ceiling height of the first storey of a habitable room provided
37. As per PD 1096, what is the classification of buildings of masonry and wood construction with a
38. Minimum ceiling height measured from the floor to the ceiling of habitable rooms with natural
ventilation
40. An unoccupied space other than a yard bounced on three sides by building lines with one side
bounded by another open space whether public or private.
41. The required open space left between the outermost face of the building and the property lines,
43. Habitable rooms provided with artificial ventilation shall have ceiling heights not less than hO'.IJ
45. Eaves, canopies, awnings (or media agua) over required windows shall not be less than _ from
the side and rear property lines.
46. Bath and toilet shall have a minimum area of __ with a least dimension of
a. 1.20sqm/900mm c. 1.30sqm/800mm
b. 1.30sqm/900mm d. 1.20sqm/950mm
47. Kitchen hall have a minimum area of ___ with a least dimension of
48. Total Open Space within Lot (TOSL} such as yards, courts, gardens ,lightwells, uncovered
driveways, access roads and parking spaces is the sum of
a. MACA c. TLA
b. AMBF d. AMVB
a. MACA
b. AMBF
c. TLA
d. AMVB