You are on page 1of 23

BILL OF MATERIALS

N ID QTY SIZE DESCRIPTION


1 2'-5 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-4 9/16" 2" PIPE, CS F1545 150LB PTFE, FXF

3 10 7/16" 2" PIPE, CS F1545 150LB PTFE, FXF

4 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

4 1/2"
7 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 1" GASKET, LAMONS MATRIX L110, FXF

9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

/1 6"
'- 19
2

3'-0 1/2"
5 1/8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
1'-
7 7/1 FABRICATION AND INSTALLATION
6" 5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.04.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 EDV 03.11.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-04-A 14-4.1703 NI EDV 03.11.19 6lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.07.19 5 2.00-CIP-14-4.1703-L25-NI-0.00-002
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-4.1703-L25-NI-0.00-002*
3 CIP WP-L3C4 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-6 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-8 15/16" 2" PIPE, CS F1545 150LB PTFE, FXF

3 3 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF


2'-
2 3/4
4 2 15/16" 2" SPACER, PTFE LINED RING, PE
" 5 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

6 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

7 1 2" TEE, CS F1545 150LB PTFE, FXFXF

16" 8 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT


15/
11 9 12 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

10 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

9"
"
1/2
1'-0

4 1/2"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
2'-3 5/8" 3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
5"

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 JF 03.06.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-02-A 14-2.1703 NI JF 03.06.19 8lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 JBF 03.05.19 4 2.00-CIP-14-2.1703-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-2.1703-L25-NI-0.00-001*
3 CIP WP-L3C2 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 2'-2 5/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 4 3/16" 2" PIPE, CS F1545 150LB PTFE, FXF

3 1'-8 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

4 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

7 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

9 1 2" GASKET, LAMONS MATRIX L110, FXF

6 "
1 3/1
1'-

2'-4 7/8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
2'- CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
11 SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
5/8 4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
"
FABRICATION AND INSTALLATION
9 1/2"

5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE

8"
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 JFF 05.02.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-02-A 14-2.1704 NI JFF 05.02.19 11lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 JBF 03.05.19 5 2.00-CIP-14-2.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-2.1704-L25-NI-0.00-001*
3 CIP WP-L3C2 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-8 1/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

3 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

4 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

5 5 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

6 1 1" GASKET, LAMONS MATRIX L110, FXF

7 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

9"
9"

4 1/2"
2'-3"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
5 1/8"

FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE


6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 JF 03.06.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-02-B 14-2.1705 NI JF 03.06.19 4lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.05.19 2 2.00-CIP-14-2.1705-L25-NI-0.00-002
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-2.1705-L25-NI-0.00-002*
3 CIP WP-L3C2 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N 8" ID QTY SIZE DESCRIPTION
1 2'-0 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-0 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

3 9 3/16" 2" PIPE, CS F1545 150LB PTFE, FXF


6"
6 3/1 4 1 2" ELBOW 90 , CS F1545 150LB PTFE, FXF
1'- 1'- 5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF
83
/4" 6 1 2" TEE, CS F1545 150LB PTFE, FXFXF

7 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

8 8 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

9 1 1" GASKET, LAMONS MATRIX L110, FXF

10 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

4 1/2"
2'-7 1/2"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5 1/8"

5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 RB 03.07.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-02-E 14-2.1707 NI RB 03.07.19 7lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.06.19 4 2.00-CIP-14-2.1707-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-2.1707-L25-NI-0.00-001*
3 CIP WP-L3C2 23
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS 1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-0 7/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-9 5/16" 2" PIPE, CS F1545 150LB PTFE, FXF

7/16" 3 2'-0 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF


0
1'- 4 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

/2" 6 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT


41 7 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 1" GASKET, LAMONS MATRIX L110, FXF

9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

4
1/
2"

1'-
95
/16
"

41
/2"

4 1/2"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,

2'-7 1/2"
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
5 1/8"

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 RB 03.11.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-02-E 14 2.1708 NI 7lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RJB 03.11.19 5 2.00-CIP-14 2.1708-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-2.1708-L25-NI-0.00-001*
3 CIP WP-L3C2 17
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS 1
BILL OF MATERIALS
N NORTH ARROW ROTATED FOR CLARITY ID QTY SIZE DESCRIPTION
1 8 3/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2'-0 3/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 6 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

5 2 11/16" 2" PIPE, CS F1545 150LB PTFE, FXF

6 3 9/16" 2" PIPE, CS F1545 150LB PTFE, FXF

9" 7 1 2" ELBOW 45, CS F1545 150LB PTFE, FXF

1'- 8 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF


17
/8" 9 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

10 1 2" TEE, CS F1545 150LB PTFE, FXFXF

16" 11 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT


11/
11 12 14 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

13 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

8"
H
°
45
77 6"
/16 /1
" 77

2'-9 7/8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
1'- INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
77 INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
/8"
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE

5"
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
2 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI
1 EDV 04.18.19 CONSTRUCTION ISSUE
0 MC 12.20.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-03-B 14-3.1705 NI EDV 04.18.19 8lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 JBF 04.18.19 5 2.00-CIP-14-3.1705-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1705-L25-NI-0.00-001*
3 CIP WP-L3C3 0
www.kinetics.net
AREA
1
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
2
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-8 5/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2 5/8" 2" SPACER, PTFE LINED RING, PE

4 1/2"
3 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

4 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

5 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

6 6 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

7 1 1" GASKET, LAMONS MATRIX L110, FXF


22° H 8 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

10
13/ /8"
16" 43

2'-3 5/8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO

5"
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.04.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 RB 03.11.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-04-A 14-4.1704 NI RB 03.11.19 4lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.07.19 2 2.00-CIP-14-4.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-4.1704-L25-NI-0.00-001*
3 CIP WP-L3C4 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 2'-2 13/16" 2" PIPE, CS F1545 150LB PTFE, FXF
"
7 3/8 2 3 13/16" 2" PIPE, CS F1545 150LB PTFE, FXF
1'-

9"
3 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

11° H
4 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF

5 1 2" TEE, CS F1545 150LB PTFE, FXFXF

6 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT

7 8 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF

9 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

3
15
/1
6"
9"
4 1/2"
2'-9 13/16"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
5 1/8"

4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE


FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.04.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 EDV 03.11.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-04-B 14-4.1705 NI EDV 03.11.19 5lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.07.19 3 2.00-CIP-14-4.1705-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-4.1705-L25-NI-0.00-001*
3 CIP WP-L3C4 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
NORTH ARROW ROTATED FOR CLARITY
N 9"
ID QTY SIZE DESCRIPTION
1 1'-1 5/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2'-2 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

3 2'-0 1/16" 2" PIPE, CS F1545 150LB PTFE, FXF

4 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

4 1/2"
5 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT

7 8 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

" 8 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF


1/16
9
2'-
9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

2'-9 3/4"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
1'

2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED


-1

5 1/8"
0
5/

UPON CONTRACT DOCUMENTS


8"

3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL


CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 KJW 02.03.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MLC 03.11.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-04-B 14-4.1706 NI MLC 03.11.19 7lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RB 03.07.19 6 2.00-CIP-14-4.1706-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.04.20
THE PROCESS PEOPLE *2.00-CIP-14-4.1706-L25-NI-0.00-001*
3 CIP WP-L3C4 0
www.kinetics.net
AREA
2
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 2'-0 13/16" 2" PIPE, CS F1545 150LB PTFE, FXF
" 2'-
2 49
2'- /16 2 1'-7 9/16" 2" PIPE, CS F1545 150LB PTFE, FXF
/2" "
31 3 1'-6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 11 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

5 6" 2" PIPE, CS F1545 150LB PTFE, FXF

6 4 1/8" 2" PIPE, CS F1545 150LB PTFE, FXF

7 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

8 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

9 1 2" TEE, CS F1545 150LB PTFE, FXFXF

10 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

3/ 16" 11 13 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

' - 91 12 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF


2

1'-1 1/8"
8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
1'-9" 2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
5"

THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE


7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MC 12.19.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-1.1703 NI JFF 01.31.20 7lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 8 2.00-CIP-14-1.1703-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-1.1703-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C1
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 2'-0 13/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2'-2 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 8 11/16" 2" PIPE, CS F1545 150LB PTFE, FXF

8"
4 4 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

8"
7 9 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

9"
8 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

2'-
11
7/8
1'-1 3/16" "

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


5"

BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR


INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3/ 16" 3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
' - 91 CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
2 SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MC 12.19.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-1.1704 NI JFF 01.31.20 5lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 6 2.00-CIP-14-1.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-1.1704-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C1
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 6" 2" PIPE, CS F1545 150LB PTFE, FXF

2 9 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 6 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

" 2'- 5 1'-9 3/16" 2" PIPE, CS F1545 150LB PTFE, FXF
1 1/2 33
1' - /16 6 5 1/16" 2" PIPE, CS F1545 150LB PTFE, FXF
" 31 7 2 2" ELBOW 45, CS F1545 150LB PTFE, FXF
/2"
8 1 2" ELBOW 90 , CS F1545 150LB PTFE, FXF
H
5° 1
7 14 "
9 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF
/8" /8
71 10 1 2" TEE, CS F1545 150LB PTFE, FXFXF

11 13 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

12 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

1'-3"
4 1/2"
3 1/2"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
1'-7 5/16"

INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN


2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
5"

THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE


7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
2 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI
1 MLC 04.18.19 CONSTRUCTION ISSUE
0 MLC 12.20.181 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-3.1703 NI JFF 01.31.20 8lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 5 2.00-CIP-14-3.1703-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1703-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
2
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 9 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-4 5/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 2'-2 7/16" 2" PIPE, CS F1545 150LB PTFE, FXF

8"
5 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5/
-1
6 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

2'
7 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

8 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

2'-
117
/16
"

8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,

1'-7 3/8"
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
5"

2 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


1 JBF 04.18.19 CONSTRUCTION ISSUE
0 MLC 12.20.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14 3.1704 NI JFF 01.31.20 10lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 5 2.00-CIP-14 3.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1704-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
2
BILL OF MATERIALS
N 1'-
ID QTY SIZE DESCRIPTION
1 1'-9 3/16" 2" PIPE, CS F1545 150LB PTFE, FXF
" 13
'-4 /16 2 1'-0 1/8" 2" PIPE, CS F1545 150LB PTFE, FXF
2 " 1 "
3 1/ 3 6 5/16" 2" PIPE, CS F1545 150LB PTFE, FXF

4 8" 2" PIPE, CS F1545 150LB PTFE, FXF


1'-
35 5 4 3/16" 2" PIPE, CS F1545 150LB PTFE, FXF
/16
" 6 6" 2" PIPE, CS F1545 150LB PTFE, FXF

7 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

8 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

9"
9 1 2" TEE, CS F1545 150LB PTFE, FXFXF

10 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

11 13 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

12 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

"
1/8
1'-9

8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN

2'-6 11/16"
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
2 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI
5"

1 SC 01.09.19 REVISED PER COORDINATION


0 MC 12.20.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-3.1707 NI JFF 01.31.20 5lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 5 2.00-CIP-14-3.1707-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1707-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
2
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-0 1/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 6 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

7 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

8"

1'
-3
3/
4"
1'-9 9/16"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
5"

FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE


6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MLC 12.20.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-3.1708 NI JFF 01.31.20 2lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 3 2.00-CIP-14-3.1708-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1708-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 6 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

2 8 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 5 1/16" 2" PIPE, CS F1545 150LB PTFE, FXF

8"
5 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

6 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

8"
7 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

8 8 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

1'
-2
1/
16
"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO

2'-1 7/8"
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE

5"
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
2 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI
1 MLC 04.17.19 CONSTRUCTION ISSUE
0 JFF 12.20.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
05-H-50-4203-03 14-3.1721 NI JFF 01.31.20 8lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 KJW 01.31.20 3 2.00-CIP-14-3.1721-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-3.1721-L25-NI-0.00-001*
WP CIP 0
www.kinetics.net
AREA
L3C3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
2
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 3'-0 7/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-1 5/16" 2" PIPE, CS F1545 150LB PTFE, FXF

3 1'-0 1/8" 2" PIPE, CS F1545 150LB PTFE, FXF

4 1 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF


1'-
1/8" 95
/16
6 1 2" TEE, CS F1545 150LB PTFE, FXFXF
9
1'- " 7 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT

8 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

9 2 2" VALVE BALL, CS F1545 150LB, CHEMTITE, FXF

10 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF

31
/2"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
3'-8 7/16"

INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY


INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
5"

FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE


6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 RELOCATED VALVE NO CHANGE TO BOM PER RFI


0 JMW 03.25.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-05-A 14-5.1703 NI JMW 03.25.19 5lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RJB 03.23.19 6 2.00-CIP-14-5.1703-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-5.1703-L25-NI-0.00-001*
3 CIP WP-L3C5 0
www.kinetics.net
AREA
3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-0 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

2 2'-0 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

3 3'-0 1/4" 2" PIPE, CS F1545 150LB PTFE, FXF

4 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

5 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF

6 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT

7 8 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

8 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF

9 1 2" VALVE BALL, CS F1545 150LB, CHEMTITE, FXF

/4"
93
1'-

2'-
91
/2"

3'-11 3/4"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE

5 1/8"
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 JMW 03.25.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-05-A 14-5.1704 NI JMW 03.25.19 8lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 RJB 03.23.19 7 2.00-CIP-14-5.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-5.1704-L25-NI-0.00-001*
3 CIP WP-L3C5 0
www.kinetics.net
AREA
3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 1'-9 1/4" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-2 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 4 1/2" 2" PIPE, CS F1545 150LB PTFE, FXF

4 2'-2 3/4" 2" PIPE, CS F1545 150LB PTFE, FXF

5 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF


"
0 5/8 6 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF

/2" 1'- 2'- 7 1 2" TEE, CS F1545 150LB PTFE, FXFXF


31 11
3/4 8 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT
" 9 10 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

10 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF

11 2 2" GASKET, LAMONS MATRIX L110, FXF

12 1 2" VALVE BALL, CS F1545 150LB, CHEMTITE W ACTUATOR, FXF


9"
13 1 2" VALVE BALL, CS F1545 150LB, CHEMTITE, FXF

2'-6 1/4"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE

8"
33° FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
H
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
9 5/8"

"
7 7/8 CLOSEST COLUMN INTERSECTION
1'-
77 1'- 8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
/8"
1 JFF 01.31.20 RELOCATED VALVE NO CHANGE TO BOM PER RFI
0 EDV 03.25.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-06-A 14-6.1703 NI EDV 03.25.19 11lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 DLK 03.24.19 6 2.00-CIP-14-6.1703-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-6.1703-L25-NI-0.00-001*
3 CIP WP-L3C6 0
www.kinetics.net
AREA
3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N NORTH ARROW ROTATED FOR CLARITY ID QTY SIZE DESCRIPTION
1 2'-9 5/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 7 9/16" 2" PIPE, CS F1545 150LB PTFE, FXF

3 1'-6 9/16" 2" PIPE, CS F1545 150LB PTFE, FXF

4 4'-3 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

5 1 2" ELBOW 45, CS F1545 150LB PTFE, FXF

6 3 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

7 1 2"X1 1/2" REDUCER CON, CS F1545 150LB PTFE, FXF

8 1 1 1/2" BOLT KIT, QTY 4 X 0.5 DIA X 3L , 15LB-FT


3'- 9 10 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT
65
/16 10 1 1 1/2" GASKET, LAMONS MATRIX L110, FXF
"
11 1 2" VALVE BALL, CS F1545 150LB, CHEMTITE, FXF
"
0 7/8
5'-

10 5/16"
45° V

"
16
5/
10
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
9"

BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR

6"
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL

1'-10 1/16"
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

5 1/8" 1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 EDV 03.25.19 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-06-A 14-6.1704 NI EDV 03.25.19 11lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 DLK 03.24.19 10 2.00-CIP-14-6.1704-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/01.31.20
THE PROCESS PEOPLE *2.00-CIP-14-6.1704-L25-NI-0.00-001*
3 CIP WP-L3C6 0
www.kinetics.net
AREA
3
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N 8" ID QTY SIZE DESCRIPTION
6" 1 3 5/16" 2" PIPE, CS F1545 150LB PTFE, FXF

2 1'-3 7/8" 2" PIPE, CS F1545 150LB PTFE, FXF

3 6" 2" PIPE, CS F1545 150LB PTFE, FXF

4 1 2" ELBOW 45, CS F1545 150LB PTFE, FXF

5 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

6 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

7 1 2" TEE, CS F1545 150LB PTFE, FXFXF

9"
8 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

9 10 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

10 2 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF


H
"
3/16
0
1'-
8"

1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO


BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
2'-1 3/8"

SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS


4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.
5"

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MC 12.19.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-01-B 14-1.1705 NI MC 12.19.18 2lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 JV 12.18.18 3 2.00-CIP-14-1.1705-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
KJW/02.05.20
THE PROCESS PEOPLE *2.00-CIP-14-1.1705-L25-NI-0.00-001*
3 CIP WP-L3C1 0
www.kinetics.net
AREA
1
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1
BILL OF MATERIALS
N ID QTY SIZE DESCRIPTION
1 2'-1" 2" PIPE, CS F1545 150LB PTFE, FXF

2 3'-2 1/4" 2" PIPE, CS F1545 150LB PTFE, FXF

7" 3 6" 2" PIPE, CS F1545 150LB PTFE, FXF


1'- 4 10" 2" PIPE, CS F1545 150LB PTFE, FXF

5 2 2" ELBOW 90 , CS F1545 150LB PTFE, FXF

6 1 2"X1" REDUCER CON, CS F1545 150LB PTFE, FXF

7 1 1" BOLT KIT, QTY 4 X 0.5 DIA X 2.75L , 10LB-FT

3'
-1
1
8 7 2" BOLT KIT, QTY 4 X 0.625 DIA X 3.5L , 25LB-FT

1/
4"
9 1 2" VALVE BALL, CS F1545 150LB, 200 CHEMTITE,FXF

8"
1. MATERIAL BOM INFORMATION IS FOR REFERENCE ONLY, MATERIAL SELECTION TO
BE DETERMINED PER THE CONTRACT DOCUMENTS. BOM QUANTITIES ARE FOR

2'-10 1/2"
INFORMATION ONLY, ACTUAL QUANTITIES REQUIRED TO BE VERIFIED BY
INSTALLATION CONTRACTOR AGAINST ACTUAL DESIGN
2. INSTALLATION CONTRACTOR RESPONSIBLE FOR HANGER TYPE AND LOCATION BASED
UPON CONTRACT DOCUMENTS
3. INSTALLATION CONTRACTOR RESPONSIBLE FOR VERIFICATION AGAINST ALL
CONTRACT DOCUMENTS TO ENSURE COMPLIANCE WITH ALL DRAWINGS,
SPECIFICATIONS, AND OTHER CONTRACTUAL ITEMS
4. INSTALLATION CONTRACTOR RESPONSIBLE FOR FIELD VERIFICATION BEFORE
FABRICATION AND INSTALLATION
5. ALL RACK MODELUE REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE

5"
6. ALL RACK MODULE ELEVATIONS ARE FROM THE TOP OF THE MOUNTING PLATE OF
THE FARTHEST SOUTHWEST VERTICAL TUBE STEEL OF THE MODULE
7. ALL OFF-RACK REFERENCE DIMENSIONS ARE FROM THE CENTERLINE OF THE
CLOSEST COLUMN INTERSECTION
8. ALL OFF-RACK ISO ELEVATIONS ARE FROM THE 48” BENCHMARK ON THE
ASSOCIATED FLOOR.

1 JFF 01.31.20 VALVE RELOCATED NO CHANGE TO BOM PER RFI


0 MC 12.19.18 ISSUED FOR CONSTRUCTION
REV BY DATE DESCRIPTION
REF. P&ID LINE NUMBER INSULATION SPEC DETAILED BY/DATE FIELD SLOPE CHECK WEIGHT PROJECT NAME PROJECT NUMBER
KD-14-01-B 14-1.1721 NI MC 12.19.18 6lbs PHARMACHEM - PROJECT SUNRISE 623010634
REF. ORTHO LINE SIZE INSULATION THICKNESS EXTRACTED BY/DATE CM/OWNER SLOPE ACCPT. LINEAR FOOTAGE DRAWING NO.
N/A 2.00 0.00 JV 12.18.18 7 2.00-CIP-14-1.1721-L25-NI-0.00-001
FLOOR SYSTEM SPECIAL APP'D BY LEAD/DATE Q.C. VERIFIED SHOP JOINTS REV.
THE PROCESS PEOPLE *2.00-CIP-14-1.1721-L25-NI-0.00-001*
3 CIP WP-L3C1 0
www.kinetics.net
AREA
1
PIPE SPEC
L25
ISO MTO I.F.C. BY SUPER/DATE Q.C. SLOPE VERIFIED FIELD JOINTS
0
1

You might also like