Professional Documents
Culture Documents
ACBIL
21.10.2013
1 Executive Summary 3
3 Project Description 11
4 Site Analysis 24
5 Planning Brief 28
6 Proposed Infrastructure 30
Analysis of Proposal
9 36
(Final Recommendations)
2
Chapter - 1
Executive Summary
i) Consultancy : 45.00
ii) Land : 0.00
iii) Building & Structural : 750.00
iv) Railway Siding : 1500.00
v) Plant & Machinery : 950.00
vi) Miscellaneous Fixed Assets : 800.00
vii) Contingencies : 45.00
4090.00
Say 40.00 Crores of Rupees
3
Chapter - 2
4
The washing plant shall have the following input & outputs:
2.3 Need for the Project and Its Importance to the Country
and or Region
Coal is the most abundant fossil fuel. India is blessed with huge coal
reserve, nearly 7% of total coal in the world. 85% of this reserve is non
Coking Coal, which caters to the need of power, cement and sponge iron
plants. However, most of these reserves are of very low grade coal and
the reserves of good quality coal is fast depleting. On the other hand, the
demand for coal is increasing due to higher demand of steel, power and
cement. The problem of inferior coal is further aggravated due to
extensive mechanised mining. As a result, the users of coal are not
getting desired quality necessitating beneficiation of coal for use in
Sponge Iron Kiln, Power Plant, Cement Plant, etc.
Coal India Limited and its subsidiaries are the only domestic producers
and suppliers of coal. The annual requirement of non-coking coal for
various industrial sectors like power, steel and cement is increasing day
by day. As the reserves of lower ash good coal are depleting and hence
in order to fulfil industry’s demand, huge reserve of inferior grade of coal
is being mined. The problem is further aggravated due to mechanised and
open cast mining of coal. Due to higher demand, selective mining is not
possible. The average ash of coal now being supplied by CIL is around
45%. Also, the quality varies to a great extent since the supplies are
coming from various mines and coal faces.
Government of India statute prohibits transport of Coal of Ash more than
34% to Thermal Power Plants situated at a distance more than 1000 Kms
from Coal Mines which shall get reduced to 500 km from the pit head
5
from Jan 2014. In order to satisfy this statute various State Electricity
Boards are looking for Coal Washery operators to supply washed coal for
their Power Plants. Further, the use of washed coal for the Thermal Power
Plants shall have the following advantages:
1. Supply of consistent quality coal can be ensured thereby
avoiding frequent adjustments in input to boiler and minimising
operators’ error.
2. Higher Thermal efficiency of boiler and higher steam rate.
3. Less wear and tear of the coal grinding mills.
4. Lower capital and operating cost for installing smaller ESP.
5. Less ash handling requirement at power plant & consequently
less requirement of area for ash-pond etc.
Coal India Ltd said in June 2013 that, it would place orders worth Rs
2,000 crore for at least seven coal washeries by the current fiscal.
“The contract for seven coal washeries would be placed by this fiscal with
washing capacity of 15-16 million tonnes (MT) of coal,” CIL General
Manager (project monitoring) T K Sinha said on the sidelines of the CII-
organised India-South Africa cooperation seminar.
“Agreement for two washeries had already been signed and two more
would be signed shortly. The rest would be done during the year,” he
said.
Asked about a low demand for washed coal from consumers, Mr Sinha
said there was demand for washed coal from non-power consumers.
CIL officials said the company has 17 washeries with an installed capacity
of 34 million tonnes.
Mr. Sinha said Coal India would pump Rs 2,000 crore in these seven
washeries, while the decision for the rest would be taken later.
The investment is over and above the Rs 5,000 crore the CIL proposes to
infuse during the current fiscal for purchasing equipment, land, railway
siding, etc, excluding acquisition.
6
The subsidiary-wise details of these proposed coal washeries are as
follows:-
Table No. 1
Capacity
Sl. Name of
(Million Tonne Subsidiary State
No. washery
per annum)
1 Kusmunda 10.0 SECL Chattisgarh
2 Baroud 5.0 SECL Chattisgarh
3 Madhuband 5.0 BCCL Jharkhand
4 Patherdih 5.0 BCCL Jharkhand
5 Patherdih 2.5 BCCL Jharkhand
6 Dahibari 1.6 BCCL Jharkhand
7 Dugda 2.5 BCCL Jharkhand
West
8 Bhojudih 2.0 BCCL
Bengal
9 Ashoka 10.0 CCL Jharkhand
10 Konar 3.5 CCL Jharkhand
11 Karo 2.5 CCL Jharkhand
12 Chitra 2.5 ECL Jharkhand
13 Basundhara 10.0 MCL Orissa
14 Jagannath 10.0 MCL Orissa
15 Hingula 10.0 MCL Orissa
16 Ib-Valley 10.0 MCL Orissa
Total 92.10
Table No. 2
The ash content of domestic coal is 45-50 per cent. The majority of coal
delivered to customers is not washed. This affects plant performance and
imposes the additional burden of environmental impact, ash handling, and
transportation costs.
The existing norms stipulate an ash content of 34 per cent for coal
transported over 1,000 km. This is being reviewed. The changes under
consideration include a reduced distance of 500 km from the pithead and
determination of ash content on a daily average basis instead of the
current practice of annual determination. Implementation of the revised
stipulations could be a key driver for augmenting coal washing capacity in
the country.
There has been increase in coal production and supply during 2012-13. The
details of targets of coal production and supply for 2011-12 and 2012-13
and corresponding achievements are given below.
Table No. 3
(in million tonnes)
Production Ach. Supply Ach.
Year Production Supply
Target in % Target in %
2011-12 554.00 539.950 97.5 559.00 535.299 95.8
2012-13 574.40 557.707 97.1 580.30 569.767 98.2
In 2012-13, the domestic production was 557.707 million tonnes and the
total domestic supply of coal was 569.767 million tonnes. In addition to
the domestic supply of coal, the country imported 137.56 million tonnes
of coal in order to meet the demand. This information was given by the
Minister of State for Coal, Shri Pratik PrakashBapu Patil in a written reply
in Rajya Sabha on 19th August 2013.
10
Chapter - 3
Project Description
The said project can be located in Survey of India Topo sheet No.64 O/9.
The location of said project is demarcated in the Toposheet as shown in
the following Map No. – 01. The project site is bounded by latitude
Latitude 210 53’ 29.2” N to 210 53’ 38.9” N and Longitude 830 43’ 28.9” E
to 830 43’ 38.5” E.
11
Map No. 1
Location Map (Marked in the Toposheet)
12
The Ib Valley Coalfield would serve as source of coal which lies between
latitudes 21041’N and 22006’N and longitudes 83030’E and 84008’E . Map
of Coal fields of MCL is shown in Map No. 02 and Coal Mines of MCL
superimposed on Toposheet shown in Map No. 03. It covers an area of
1,375 square kilometres (531 sq mi). According to Geological Survey of
India, the Talcher Coalfield has reserves of 38.65 billion tonnes, the
highest in India. Ib Valley Coalfield has reserves of 22.3 billion tonnes,
the third highest in India. This coalfield forms part of the large Gondwana
basin that extends across several districts in adjoining Chhattisgarh. Ib
Valley Coalfield is served by South East Central Railway. The main railway
station for passenger traffic is Brajrajnagar on the Tatanagar-Bilaspur
section of Howrah-Nagpur-Mumbai line. The area links to NH 200.
Construction of the 52 km (32 mi) long Jharsuguda-Barpalli rail line is
essential for transportation of coal from the Ib Valley Coalfield with a
potential of 90 million tonnes per annum. Mahanadi Coalfields Limited will
fund this project. This Coalfield is a part of large synclinal Gondowna
Basin of Raigarh-Hingir and Chhattisgarh Coalfields (Mahanadi Valley) and
forms its South Eastern most member. Coal potentiality of this fields was
investigated as early as 1871-75 by Mr.V.Ball of GSI. Some works were
also done by Mr.W.King during 1884-86. During 1900-01 exposures of
various seams were found while constructing bridge over IB River on the
Bombay Howrah Railway line. Further work was undertaken by Geological
Survey of India. During 1977 CMPDIL entrusted the Directorate of Mining
& Geology (Govt. of Orissa) for detail exploration. Barakar & Karharbari
measures are the major coal bearing formations. Barakar formation
contains as many as twenty carbonaceous horizons with quality ranging
from E to G. These horizons have been clubbed and five seams have been
identified in the area, namely Belpahar, Parkhani, Lajkura, Rampur & IB
Seams. Parkhani seam is erratic in quality and thickness. It is generally
not found as mineable. Belpahar seam occurs in the deep side of
Lakhanpur OCP and mining operation in this seam is not foreseen in near
future. Karharbari formation contain only thin coal bands below IB seam.
Basic considerations in deciding the location of plant site are listed below
in order of its significance.
14
Map No. 3
Coal Mines of MCL superimposed on Toposheet
15
3.4 Size or Magnitude of Operation
Like all other Indian coal deposits, the coal deposit at Ib Valley and
nearby locations are of “drift” origin (unlike European, Australian Or
American coal which are of “Insitu” origin), and hence, have very high
Near Gravity Material (NGM). Presence of high NGM (more than 20
units) in ROM coal makes the washing of coal very difficult. Hence,
selection of suitable washing process is of paramount importance for
such coal. Bird’s classification of NGM Vis-à-Vis suitable washing process
are indicated below
10 – 15 Difficult to wash
20 – 25 exceedingly difficult
> 25 Formidable
From the above table it is clear that the HM Cyclone process is the only
suitable process for treating high NGM coal.
16
Moreover, from process efficiency point also, the HM Cyclone process is
most suitable process which gives lowest EP (Ecart Probable – means
Error Probable) i. e; lowest misplacement. A comparison of EP
achievable in various processes is given below:
1. HM Cyclone : 0.025 to 0.035.
2. Jig/Drum Washer : 0.10 to 0.12
3. Barrel : 0.09 to 0.10
Considering all the above mentioned factors, the following processes are
recommended for the proposed expansion:
The raw coal from the ramp is fed to the two grizzly feeders
having 400 TPH capacities each.
Then the -150mm coal from the feeder breaker is fed through belt
conveyor 4 and 4A to the belt conveyor BC – 2.
Then the total -150mm coal is fed to the four nos. 400TPH Double
deck screen for primary screening having top deck of 50mm and
bottom deck of 20mm sieve size.
The +50mm coal is then directed to the two nos. 400TPH crusher
to get desired -50mm coal.
The Secondary Double deck screens have two output which are “-
50 to +20” and “-20mm”
Then these two separate sizes coal is then fed to their separate
surge bunkers having appropriate capacities.
Coal size having -20mm from the Secondary Double deck screens
is then fed to the 2 numbers Heavy media cyclones of 300 TPH
capacities.
18
Drawing No. 1
Process Flow Drawing
19
Main Equipments required for capacity expansion:
Table No. 5
List of the Washery Equipment
20
3.6 Raw material required along with estimated quantity,
likely source, marketing area of final product/s, mode of
transport of raw material and finished product.
The raw material required for the project is only Raw Coal. The quantity is
10 million Tons. The coal for washery will be sourced from the Coal Mines
of Mahanadi Coalfields Limited (MCL) located in Sundargarh district.
Water: The water would be required for working of drum washer and dust
suppression. The total requirement of water is 300 m3/day. The Company
has received a letter from Office of Executive Engineer, Sundergarh
writing to the Superintending Engineer, Hirakund Dam Circle
recommending allocation of 300 m3/day from Brahmani Nallah. The
breakup of the water requirement for the expansion is presented in the
Table No. 6.
Table No. 6
Breakup of make-up water requirement
21
3.9 Quantity of Wastes to be generated (Liquid and Solid) and
Scheme for Their Management / Disposal
During construction, waste generated is limited to levelling of any low
lying areas within the plant premises. 100 % utililization of rejects is
envisaged in the project. These rejects are being used in the captive
power plant of the company located at Bomaloi village in Sambalpur
district. Plant would operate on zero discharge concepts. Thus no waste
water discharge is envisaged in the said project of both existing and
expansion. Drawing No. 02 shows the Waste Water Management Scheme.
Drawing No. 2
Waste Water Management Scheme
22
3.10 Schematic Representations of the Feasibility drawing
which give information of EIA Purpose.
Purpose of preparation of EIA is for prior environmental clearance required as per
EIA notification dated 14th September, 2006 and amended thereafter as the
project proponent proposed for enhancement of Washery from 5.00 MTPA
to 10.00 MTPA. The proposed schematic representation provides information for
preparation of EIA is as per Drawing No. 02 and 03.
Drawing No. 3
Activity of Washery
23
Chapter – 4
Site Analysis
4.1 Connectivity
The proposed project will be set up within the existing premises of Himgir
Coal Washery at village Kanika under Himgir Tehsil in Sundargarh district
of Odisha state. The proposed site is accessible from road and rail
transport.
4.2 Land Form, Land Use and Land Ownership
The total land requirement is of 13.5 ha. The total land has already been
acquired and is owned by the project proponent.
The land available for the project is sufficient for the expansion. The
breakup of the land use for the project area has been described in the
Table No. 7
Table No. 7
Break up of Land use
Land use Area (ha)
Plant area 3.25
Raw coal stock yard 2.5
Clean coal stock yard 1.75
Water Reservoir 1.0
Parking and Rest room area 0.25
Green belt area 4.5
Administrative building 0.25
Total 13.5
Railway siding : ACB (India) Ltd. has already commissioned its own
Railway siding at Himgir railway station for loading of washed coal rakes in
Dec 2012. The location of siding is between Daghora and Himgir Railway
station of South East Central Railway, Bilaspur division. The distance of
the proposed Railway siding from coal washery is 3 Kms. The purpose of
constructing the Railway siding is to supply washed coal to;
Power houses of Maharashtra and Gujrat.
Power houses of West Bengal Power Development Corporation.
Cement and Sponge iron units in Eastern and Central India.
24
The total land required for construction of Railway siding was 10 Acres.
Currently the coal from Gopalpur coal fields is conveyed by road to the
washery and after washing, washed coal would be transported by road to
the siding for loading of rakes. Total cost for construction of Railway siding
is approximately 25 Crores.
25
Distance of Various Physical Features from the Boundary of the Project
Area
There is no national park/wild life sanctuary/biosphere reserve/ tiger
reserve/ elephant reserve in the core (project area) and buffer zone
(10 km radius of the project area).
Barghumra Reserve forest, contour having 298 m AMSL is at a
distance of 50 meters from the project site towards south.
Garjan Pahar Reserve Forest having contour 341 m aMSL is towards
west of project site at a distance of 560 meters.
Chhengapahar Reserve Forest is at distance of 380 meters towards
east of project site and 100 .00 meters towards north of project site.
Brahmani Nala is flowing at a distance of 550.0 meters towards west
of Project site.
Hemagiri Railway Station is at a distance of 2.00 kms from project
site towards South southeast.
South Eastern Railway is passing towards south of project site at a
distance of 2.00 kms.
Hemagiri – Kanika State Road which is east of the project site is
passing at a distance of 380 meters from the project site.
Hemagiri Town is situated at a distance of 6.200 kms towards north
of the project site.
26
Power supply can be easily met from the existing grid / DG Set. Sufficient
land required for expansion of coal washery is available at the plant site.
4.6 Soil Classification
The soil is silty clay in texture and light brown in colour. Slightly acidic
with pH variying from 4.92 to 5.53. Soil is rich in organic matter, Ca and
nitrate. Iron content is high.
4.7 Climate data from Secondary Sources
Meteorological conditions prevailing at any geographical area play an
important role in analyzing its existing air quality and the environmental
conditions. Climate, weather and other meteorological parameters
generally influence and also alter site-specific activities. Meteorological
data, which is averaged over thirty years of data from 1961 to 1990 by
Indian Meteorological Department will be considered while preparing EIA/
EMP report as a secondary data. And on-site meteorological data of
standard parameters such as wind speed, wind direction, temperature,
relative humidity and rain fall for the study period will be collected.
The climate of this region is mainly tropical and is influenced to some
extent by the conditions in Bay of Bengal.
Southwest monsoon season starts from June and extends upto September
with total average annual rainfall of 1314.4 mm out of which 90% of
rainfall is observed in the monsoon season only. The summer is peak
during May – June with temperature as high as 41.89 0C in May. Winter
prevails from December to January. The minimum average temperature
recorded during January is 12.31 0C. The relative humidity varies from 27
% in May to 81 % in August.
5.3 Land Use planning (breakup along with green belt etc.).
The total land requirement is of 13.5 ha. The whole of land already
acquired and is owned by the Project proponent.
The land available for the project is sufficient for the expansion. The plant
lay out is shown below and breakup of the land use plan for the project
area has been described in the Table No. 8.
Table No. 8
Break up of Land use
29
Chapter – 6
Proposed Infrastructure
Table No. 9
Schedule of Green Belt Development
Schedule of plantation
Year Number Total Total no Cumulative Cumulative
of plants area in of increase in increase in
per hectare plants plantation Plants
hectare area
1 2000 0.3 600 0.3 600
2 2000 0.5 1000 0.8 1600
3 2000 1 2000 1.8 3600
4 2000 1.2 2400 3 6000
5 2000 1.5 3000 4.5 9000
Total 4.5 9000
30
Maintenance of green belt
The green belt will be protected by barbered wire or natural
fence.
Any dead plants will be regularly removed and replaced.
Proper watch and ward arrangement will be done.
Regular watering at appropriate intervals will be done and
wastewater from the industry shall be utilized
31
6.6 Drinking Water management (Source & Supply of Water).
The water would be required for working of drum washer and dust
suppression. The total requirement of water is 300 m3/day. The Company
has received a letter from Office of Executive Engineer, Sundergarh
writing to the Superintending Engineer, Hirakund Dam Circle
recommending allocation of 300 m3/day from Brahmani Nallah
Sewerage System
No residential facilities envisaged in the project. However, septic tank with
soak pit will be provided for the employees of the project which are
designed as per BIS specification.
6.7 Industrial Waste Management (Liquid Effluent)
The industrial liquid waste will be treated in Effluent Treatment Plant. As
mostly the use of water will be of recirculation type, Zero Discharge
Method will be adopted.
32
Chapter – 7
Rehabilitation and Resettlement (R & R Plan)
33
Chapter – 8
Project Schedule & Cost Estimate
1. Consultancy : 45.00
2. Land : 0.00
3. Building & Structural : 750.00
4. Railway Siding : 1500.00
5. Plant & Machinery : 950.00
6. Miscellaneous Fixed Assets : 800.00
7. Contingencies : 45.00
Total 4090.00
Say 40.00 Crores
34
Table No. 10
Annual Cost for Environmental Protection
Cost
Sl. No. Particulars
(Rs. In Lakhs)
1 Pollution control 19.22
2 Pollution monitoring 9.32
3 Occupational health 0.64
4 Green belt 1.41
5 Reclamation 3.96
6 Others 3.36
7 Interest on capital cost 3.46
8 Overheads 0.63
Total 42.00
35
Chapter – 9
36
Improvement in Socio-Economic Conditions
Employment: During operation, plant will generate direct employment.
The p reference will be given for local population for employment in the
semi-skilled and unskilled category. Indirect employment is created by
the plant for supply of daily domestic goods.
Health and Safety Measures: The workers engaged in pollution generation
area will be equipped with appropriate protective equipment.
Following measures will be adopted in the plant to keep check on the
safety measures and health:
A periodic health check-up camp will be arranged for the workers in
the plant for occupational diseases. All the employees will have to
undergo medical check- ups at regular time interval to determine
any impact on the health of employees due to the plant atmosphere.
Inspection and maintenance of pollution control systems regularly
All safety measures such as provision of safety appliances,
imparting training, giving-of safety awards, display of posters with
slogans related to safety will be taken
The workers exposed to noisy sources will be provided with ear
muffs/plugs
Adequate facilities for drinking water and sufficient toilets will be
provided for the employees
Social Welfare Measures: The Company shall earmark funds for social
development and welfare measures in the surrounding villages. These
measures shall include funding for:
Repair and improvement of existing schools
Repair and improvement of health centres
Improving the facilities for general lighting
Repair and improvement of community centres, building such as
panchayat halls, baratghars, etc.
Conducting Awareness pro grams
Women and child development programs
Medical camps
Competitions and prizes
Drinking water availability efforts
Rain water harvesting measures
37
Table No. 11
CSR Activity Wise Budget
Fund Allocation
Sl. No Activities Covered under C.S.R (Annual)
Rs. In Lacs
Development of village school and
1 2.5 lacs
maintenance
Conducting medical camps and extending
2 3.0 lacs
medical facilities
38
Chapter – 10
Addendum of EIA - EMP Report of Proposed Expansion
Chapter 3 will cover baseline environmental data and its analysis with
respect to the Study Area (project area and the buffer area).
Chapter 4 will describe the anticipated impacts on the environment and its
mitigation measures. The method of assessment of impacts including
studies to be carried out, modelling techniques to be adopted to assess the
impacts, details of the impacts on the baseline parameters, and the
mitigation measures to be implemented will be given in this chapter.
Chapter 7 will describe the benefits that the project is going to provide to
the locality, neighbourhood, region and nation as a whole. Details of
benefits by way of improvements in the physical infrastructure, social
infrastructure, employment potential and other tangible benefits will also
be discussed.
39
Chapter 8 will be the Environmental Management Plan (EMP), which will
include the administrative and technical setup, summary matrix of EMP,
the cost involved to implement the EMP and provisions made towards the
same including the environmental policy of the company as whole
proposed conceptual-monitoring scheme will also be described in this
chapter.
Ambient air quality was carried out at five sampling stations within the
study area. The concentration of RSPM was found in between 35 to 69
µg/m3, SPM between 81 to 135 µg/m3, SO2 is between 4.5 to 9.5 and
NOX is in the range of 8.4 to 13.5.
The depth to water table over the study area is highly variable ranging
between 6m to 8m below ground during summer season. The rainfall is
the main source of groundwater recharge in the area.
Water quality in the study area shows that physical parameters like colour,
odour, taste, turbidity and temperature. pH, hardness, chloride, total
solids are within the desirable limits. Alkalinity is found within the
desirable limit in most of the samples except at Baradhera and Bishnath
Pur.
The noise level was found to be between 41.50 db[A] to 55.00 db[A]
during day time and 35.00 db[A] to 45.00 db[A] during night. It is
concluded that the existing sound pressure levels in the area are within
the standards specified for respective area categories.
The soil quality analysis show that soil is silty clay in texture and
light brown in colour and slightly acidic, with pH varying from 4.8 to 5.5.
The soil is rich in organic matter, Ca and nitrate. Iron is high, values are
between 29.2 to 39.7 mg/kg.
40
10.3 Specific Issues of Anticipated Impacts and Mitigation
Measures in Existing as well as in Proposed Expansion
Major source of air pollution are discharge of coal into receiving hopper,
discharge of coal at the crusher, discharge of coal at screens and
Primary impact due to transportation. Appropriate pollution control
equipment with adequate capacity is proposed to be installed to avoid
degradation of air environment.
Surface water: - Rain water flowing through the project area will carry
loose soil, thereby increasing suspended solids of receiving water body.
However, the impact is temporary and reversible. Garland drains around
the plant would be provided for rain water
41
However no impact is envisaged on surface water bodies. There will not
be any effluent discharge from the proposed plant. The plant would
operate on zero discharge concept and all the process water would be
clarified and recycled back to the system in a closed circuit module.
Ground water:- Ground water would be sourced from bore holes inside
the plant site. The makeup water requirement for the proposed project is
of the order 600 m3/day. The water demand due to this project is only
0.21% of the available ground water resources in the area. Thus there
will be negligible impact of the ground water withdrawal on the
agricultural and other users of ground water. During the operation there
will not be any direct contact between shallow water table and
effluent/slurries.
The run-off from the coal handling area will flow through garland drains
around the coal storage area and coal handling buildings into a common
basin (settling tank) where settlement of suspended solids shall take
place.
The oil water mixture collected in the separate drains, will lead to an oil-
water separator. The separated water containing less than prescribed
limit of oil and grease will be led into the drainage system which will
finally discharge into station sump. The domestic sewage effluent from
the proposed plant will be treated in septic tank and soak pit system.
Coal washery would operate on zero discharge system.
The noise level will be due to equipment machinery and at coal transfer
points. The noise level near the sources such as crushers, DG set and
other operational points will be higher The noise level at sources like the
generator are anticipated to go as high as 95 dB (A).
42
The noise level will be maintained by providing and maintaining green belt,
noise generating machinery including transportation vehicles, reducing
the exposure time of workers to the higher noise levels.
The raw material transport will be carried out by trucks from coal
deliverance point to the plant. The washed coal will be transported from
plant to the siding by conveyor. Thus, increase in the traffic density is
envisaged for receipt of raw material. The coal received would be 10
MTPA i.e. 30302 TDP using an equal number of 20 T and 30 T trucks. This
would contribute 52 trucks an hour approximately. (26 nos x 20 T +26
nos x 30 T).
Impact on ecology
It has been proposed to create and maintain a green belt in 4.0 Ha i.e.
29.5 % of total land area.
Solid waste
43