basis to provide confidence that the project will satisfy the relevant quality
standards
A. Quality control
B. Quality assurance
C. Quality planning
D. Quality management
ANSWER: B
It identifies which quality standards are relevant to the project, and determining
how to satisfy them.
A. Quality control
B. Quality assurance
C. Quality planning
D. Quality management
ANSWER: C
It includes the physical work scheduled, plus the authorized budget to accomplish
the scheduled work.
A. PV
B. EV
C. AC
D. EC
ANSWER: A
It includes the physical work accomplished plus the authorized budget for this
work.
A. PV
B. EV
C. AC
D. EC
ANSWER: B
Total costs incurred that must relate to whatever cost was budgeted.
A. PV
B. EV
C. AC
D. EC
ANSWER: C
Previously, this was called the budgeted costs for work scheduled.
A. PV
B. EV
C. AC
D. EC
ANSWER: A