It is known as the process of evaluating overall project performance on a regular

basis to provide confidence that the project will satisfy the relevant quality
standards
A. Quality control
B. Quality assurance
C. Quality planning
D. Quality management
ANSWER: B

It is the process of monitoring specific project results to determine if they


comply with relevant quality standards and identifying ways to eliminate causes of
unsatisfactory performance.
A. Quality control
B. Quality assurance
C. Quality planning
D. Quality management
ANSWER: A

Which of the following is not a project?


A. developing or acquiring a new or modified information system
B. Developing a product
C. building a water system for a community in a developing country
D. running at campaign for political office
ANSWER: B

It identifies which quality standards are relevant to the project, and determining
how to satisfy them.
A. Quality control
B. Quality assurance
C. Quality planning
D. Quality management
ANSWER: C

It includes the physical work scheduled, plus the authorized budget to accomplish
the scheduled work.
A. PV
B. EV
C. AC
D. EC
ANSWER: A

What are the three elements of project plan?


A. Time, scope, people
B. Scope, time, role
C. Cost, scope, time
D. Role, people, time
ANSWER: C

Which of the following is not a feature of a project?


A. Permanent
B. Unique result
C. Temporary
D. Progressive elaboration
ANSWER: A

It includes the physical work accomplished plus the authorized budget for this
work.
A. PV
B. EV
C. AC
D. EC
ANSWER: B

Total costs incurred that must relate to whatever cost was budgeted.
A. PV
B. EV
C. AC
D. EC
ANSWER: C

A project is a continuous endeavour undertaken to create a unique product or


service.
A) True
B) False
ANSWER: B

Previously, this was called the budgeted costs for work scheduled.
A. PV
B. EV
C. AC
D. EC
ANSWER: A

It is the most important step in the process and most complicated.


A. Define
B. Plan
C. Evaluate
D. Implement
ANSWER: B

Product management as a practice is a method of planning and guiding a project from


start to finish.
A) True
B) False
ANSWER: B

Project management is the application of processes, methods, knowledge, skills and


experience to achieve the project objectives.
A) True
B) False
ANSWER: A

Progressive elaboration�work, is a software project to build a new website.


A) True
B) False
ANSWER: A