HSE INSPECTION CHECKLIST OF INTALLATION OF WIND TURBINE ERECTION

PROJECT NAME
ACTIVITY TYPE
EQUIPMENTS USED
DATE/TIME
AREA/LOCATION
INSPECTED BY
STATUS
NO/
S.N PARTICULARS/ CHECK POINTS YES REMARKS
NOT NA
/OK
OK
1 Is the third party test certificate of crane is available?
2 Did the load chart displaced inside the operator cabin?
3 Operators are authorized or certified.
4 Rigger is certified and designated with visible jacket.
5 Is the ground surface is hard enough for crane activity?
6 Is the Out triggers of crane are fully extended?
7 Alarm is installed.
8 Level meters are installed.
Are the belts, slings and shackles are in good condition and
9
having acceptable capacity to lift?
10 Are riggers in contact with crane operator?
11 Is wind speed measured and permissible for job?
12 Is only authorized staff is inside working area and with PPE’s?
13 Is working zone barricaded?
14 Is Ambulance with first aid is available on site?
15 Erection activity is going on under HSE supervision?
During the tandem lifting the load lifted by each crane does not
16
exceeds 80% of its safe load.