Professional Documents
Culture Documents
1 UNIVERSITIPUTRAMALAYSIA
FAKULTI SAINS KOMPUTER DAN TEKNOLOGI MAKLUMAT
QUESTION
VAF Table
Value Adjustment Factors(VAF) scale
1. Does the system require reliable backup and recovery? 5
2. Are specialized data communications required to transfer
0
information to or from the application?
3. Are there distributed processing functions? 5
4. Is performance critical? 4
5. Will the system run in an existing, heavily utilized
3
operational environment?
6. Does the system require online data entry? 2
7. Does the online data entry require the input transaction to
3
be built over multiple screens or operations?
8. Are the ILFs updated online? 4
9. Are the inputs, outputs, files, or inquiries complex? 3
10. Is the internal processing complex? 4
11. Is the code designed to be reusable? 2
12. Are conversion and installation included in the design? 4
13. Is the system designed for multiple installations in
3
different organisations?
14. Is the application designed to facilitate change and ease
2
of use by the user?
**Scale ranges from 0 (not important/applicable) to 5 (absolutely essential)
(*Weighting Factor value is normally built-in the FP tool)
a) Calculate the function point total. Assume cost per FP is approximately RM
670 (RM 670/FP). Estimate the total cost for the LMS project.
[Show the procedure (i.e steps) how you generate your answer]
Answer
FP = Function Point
UFP = Unadjusted Function Point
VAF = value adjustment Factor
Calculating UFP
From :
http://groups.umd.umich.edu/cis/course.des/cis525/js/f00/harvey/FP_Ca
lc.html
QUESTION 2 (25 Marks)
QUESTION
The effort adjustment factors for the project are estimated as follow:
Project a b c d
Organic 2.4 1.05 2.5 0.38
Semi Detached 3.0 1.12 2.5 0.35
Embedded 3.6 1.20 2.5 0.32
Given
a=3
b=1.12
c=2.5
d=0.35
Effort = a*klocb
Effort = 3*45.31.12
Effort = 214.75
Duration = c*effortd
Duration = 2.5*214.750.35
Duration = 16.37
Staffing = effort/duration
Staffing = 214.75/16.37
Staffing = 13.11
Explanation: The coefficients are set according to the project mode selected on
the previous page, (as per Boehm,81). The final estimates are determined in
the following manner:
The effort adjustment factors for the project are estimated as follow:
Project mode would be organic type, as the project neither complex nor simple
while there is a mixture of experience personnel for the project.The module size
is also within the range of 2-50 KLOC
TDEV = 9.25
Person = 3.38